Start date: April 8 (Friday) Working days:Monday-Saturday  When will you start renting the sound equipment? When will you start printing the certificates and programme? When will you start disseminating the information?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Start date: April 8 (Friday)

Working days:Monday-Saturday

 When will you start renting the sound equipment? When will you start printing the certificates and programme? When will you start disseminating the information?

As part of the final requirement for the course ES034- Engineering Management, class
M8C1 is planning to conduct an outreach program in Barangay Labangon. The following
are the conceptualized activities necessary to be undertaken for the accomplishment of
this endeavor. Along with conditions, the university president emphasized that the
following action plan shall be carried out within 15 days only.
Activity
A
B
C
D
E
F
G
H
I
Description
Project Team Planning
Consultation with the Barangay Officials
Reservation of Guest Speakers
Estimation of Materials & Equipment
Expenses
Fund Raising
Canvassing & Procurement of Materials
Renting of Sound Equipment
Printing of Certificates & Programme
Information Dissemination
Precedent
Activity
None
A
A
B
C, D
E
E
F
G, H
Time
Estimate
S
(Days)
2
1
2
1
???
1
1
1
3
Transcribed Image Text:As part of the final requirement for the course ES034- Engineering Management, class M8C1 is planning to conduct an outreach program in Barangay Labangon. The following are the conceptualized activities necessary to be undertaken for the accomplishment of this endeavor. Along with conditions, the university president emphasized that the following action plan shall be carried out within 15 days only. Activity A B C D E F G H I Description Project Team Planning Consultation with the Barangay Officials Reservation of Guest Speakers Estimation of Materials & Equipment Expenses Fund Raising Canvassing & Procurement of Materials Renting of Sound Equipment Printing of Certificates & Programme Information Dissemination Precedent Activity None A A B C, D E E F G, H Time Estimate S (Days) 2 1 2 1 ??? 1 1 1 3
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.