Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000’s) TBC 1 2 3 4 5 Task 1 40 10 15 10 5 Task 2 23 6 10 5 2 Task 3 15 9 4 2 Task 4 6 3 3 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000’s) 1 2 3 4 Task 1 15 21 12 6 Task 2 2 5 6 3 Task 3 1 5 5 Task 4 2 What is the CAC at the end of week 4? Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40% 62% 85% 100% Task 2 15% 25% 75% 90% Task 3 2% 7% 45% Task 4 10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000’s) TBC 1 2 3 4 5 Task 1 40 10 15 10 5 Task 2 23 6 10 5 2 Task 3 15 9 4 2 Task 4 6 3 3 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000’s) 1 2 3 4 Task 1 15 21 12 6 Task 2 2 5 6 3 Task 3 1 5 5 Task 4 2 What is the CAC at the end of week 4? Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40% 62% 85% 100% Task 2 15% 25% 75% 90% Task 3 2% 7% 45% Task 4 10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question
- Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows:
|
|
Budgeted Per Week (in 000’s)
|
||||
|
TBC |
1 |
2 |
3 |
4 |
5 |
Task 1 |
40 |
10 |
15 |
10 |
5 |
|
Task 2 |
23 |
6 |
10 |
5 |
2 |
|
Task 3 |
15 |
|
|
9 |
4 |
2 |
Task 4 |
6 |
|
|
|
3 |
3 |
What is the total cumulative TBC? What is TBC at the end of week 4?
- Assume 4 weeks have passed and these are the actual costs per week:
|
Actual Costs Per Week (in 000’s) |
|||
|
1 |
2 |
3 |
4 |
Task 1 |
15 |
21 |
12 |
6 |
Task 2 |
2 |
5 |
6 |
3 |
Task 3 |
|
1 |
5 |
5 |
Task 4 |
|
|
|
2 |
What is the CAC at the end of week 4?
- Below is the cumulative percentage of work complete per task per week:
|
Cumulative Percentage Complete |
|||
|
1 |
2 |
3 |
4 |
Task 1 |
40% |
62% |
85% |
100% |
Task 2 |
15% |
25% |
75% |
90% |
Task 3 |
|
2% |
7% |
45% |
Task 4 |
|
|
|
10% |
What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,