Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows:       Budgeted Per Week (in 000’s)       TBC 1 2 3 4 5 Task 1 40 10 15 10 5   Task 2 23 6 10 5 2   Task 3 15     9 4 2 Task 4 6       3 3 What is the total cumulative TBC? What is TBC at the end of week 4?   Assume 4 weeks have passed and these are the actual costs per week:   Actual Costs Per Week (in 000’s)   1 2 3 4 Task 1 15 21 12 6 Task 2 2 5 6 3 Task 3   1 5 5 Task 4       2            What is the CAC at the end of week 4?   Below is the cumulative percentage of work complete per task per week:   Cumulative Percentage Complete   1 2 3 4 Task 1 40% 62% 85% 100% Task 2 15% 25% 75% 90% Task 3   2% 7% 45% Task 4       10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
  • Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows:

 

 

 

Budgeted Per Week (in 000’s)

 

 

 

TBC

1

2

3

4

5

Task 1

40

10

15

10

5

 

Task 2

23

6

10

5

2

 

Task 3

15

 

 

9

4

2

Task 4

6

 

 

 

3

3

What is the total cumulative TBC? What is TBC at the end of week 4?

 

  • Assume 4 weeks have passed and these are the actual costs per week:

 

Actual Costs Per Week (in 000’s)

 

1

2

3

4

Task 1

15

21

12

6

Task 2

2

5

6

3

Task 3

 

1

5

5

Task 4

 

 

 

2

           What is the CAC at the end of week 4?

 

  • Below is the cumulative percentage of work complete per task per week:

 

Cumulative Percentage Complete

 

1

2

3

4

Task 1

40%

62%

85%

100%

Task 2

15%

25%

75%

90%

Task 3

 

2%

7%

45%

Task 4

 

 

 

10%

What are the CEV, CPI, and CV at the end or week 4? What is the SPI?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L