A new system development project is being planned for Consti Corporation. The invoicing, cash receipts and accounts payable modules are all going to be updated. You are the controller of Consti Corporation and you are a little anxious about the aforementioned project. The last systems development project that affected your department was not very successful, and the employees in the accounting department did not accept the new system very well at first. You feel that the systems personnel did not interact sufficiently with the users of the systems in the accounting department. Required: Prepare a memo that you will send to Anna Marie, the head of the information systems department. In the memo, provide some suggestions about the new project, including your concern about the accounting personnel in the systems development project. Give persuasive arguments why prototyping would be helpful to the workers in the accounting department.
1. A new system development project is being planned for Consti Corporation. The invoicing, cash
receipts and accounts payable modules are all going to be updated. You are the controller of Consti
Corporation and you are a little anxious about the aforementioned project. The last systems
development project that affected your department was not very successful, and the employees in the
accounting department did not accept the new system very well at first. You feel that the systems
personnel did not interact sufficiently with the users of the systems in the accounting department.
Required: Prepare a memo that you will send to Anna Marie, the head of the information systems department. In the memo, provide some suggestions about the new project, including your concern about the accounting personnel in the systems development project. Give persuasive arguments why
prototyping would be helpful to the workers in the accounting department.