A Make a network diagram and find the project completion time and critical path Activity Activity Description Excavate (7) Estimated Duration (Weeks) Immediate Predecessors 2 B Lay the foundation A 4 C Put up the rough wall B 10 D Put up the roof C 6 E Install the exterior plumbing C 4 F Install the interior plumbing E 5 G Put up the exterior siding D 7 H Do the exterior painting E, G 9 1 Do the electrical work C 7 J Put up the wallboard F, I 8 K Install the flooring J 4 Do the interior painting J 5 M Install the exterior fixtures H N Install the interior fixtures K, L 26
A Make a network diagram and find the project completion time and critical path Activity Activity Description Excavate (7) Estimated Duration (Weeks) Immediate Predecessors 2 B Lay the foundation A 4 C Put up the rough wall B 10 D Put up the roof C 6 E Install the exterior plumbing C 4 F Install the interior plumbing E 5 G Put up the exterior siding D 7 H Do the exterior painting E, G 9 1 Do the electrical work C 7 J Put up the wallboard F, I 8 K Install the flooring J 4 Do the interior painting J 5 M Install the exterior fixtures H N Install the interior fixtures K, L 26
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question

Transcribed Image Text:A
Make a network diagram and find the project completion time and critical path
Activity
Activity Description
Excavate
(7)
Estimated Duration
(Weeks)
Immediate
Predecessors
2
B
Lay the foundation
A
4
C
Put up the rough wall
B
10
D
Put up the roof
C
6
E
Install the exterior plumbing
C
4
F
Install the interior plumbing
E
5
G
Put up the exterior siding
D
7
H
Do the exterior painting
E, G
9
1
Do the electrical work
C
7
J
Put up the wallboard
F, I
8
K
Install the flooring
J
4
Do the interior painting
J
5
M
Install the exterior fixtures
H
N
Install the interior fixtures
K, L
26
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub