2.2.1 Draw the project network diagram. 2.2.2 Identify the project critical path. 2.2.3 What is the expected project completion time.
2.2.1 Draw the project network diagram. 2.2.2 Identify the project critical path. 2.2.3 What is the expected project completion time.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
please answer all parts within 30 minutes
![2.2 The renovation project for an office park in
Sandton has the following ten (10) activities. The
activity times as well as the precedence relationships
are shown below.
Activity
Duration (days) Predecessors/s
A
8
None
B
4
None
C
5
A
D
6
A,B
E
3
B,D
F
6
C,E
G
7
E,F
H
5
G
I
2
E,G,H
4
1
2.2.1 Draw the project network diagram.
2.2.2 Identify the project critical path.
2.2.3 What is the expected project completion time.
2.2.4 Complete the table below.
Activity Duration Predecessors/s Early Early Late Late Slack
start finish start finish
(days)
8
A
None
B
4
None
с
5
A
D
6
A,B
E
3
B,D
F
6
C,E
G
7
E,F
H
5
G
1
2
E,G,H
4
I
J](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fa7b3ae88-5fa8-4d37-9c2b-c3989c43976d%2F92dce6a6-a398-42ba-b6ac-9e731d947044%2Fkhaf73n_processed.jpeg&w=3840&q=75)
Transcribed Image Text:2.2 The renovation project for an office park in
Sandton has the following ten (10) activities. The
activity times as well as the precedence relationships
are shown below.
Activity
Duration (days) Predecessors/s
A
8
None
B
4
None
C
5
A
D
6
A,B
E
3
B,D
F
6
C,E
G
7
E,F
H
5
G
I
2
E,G,H
4
1
2.2.1 Draw the project network diagram.
2.2.2 Identify the project critical path.
2.2.3 What is the expected project completion time.
2.2.4 Complete the table below.
Activity Duration Predecessors/s Early Early Late Late Slack
start finish start finish
(days)
8
A
None
B
4
None
с
5
A
D
6
A,B
E
3
B,D
F
6
C,E
G
7
E,F
H
5
G
1
2
E,G,H
4
I
J
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.