Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 95-time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 2 decimal places in your task time and variance calculations and at least 3 decimal places in your z value calculation. Enter your final probability answer to 3 decimal places.) Acct. ID 1 2 234567 3 4 Ч 7 Description Design package Design product Build package Secure patent Build product Paint Test market Predecessor None 1 12222 3,4,5 Optimistic Most Likely Pessimistic (a) 6 15 4 24 17 4 13 The probability of completing the project in 95 time units is 2212219 27 16 (b) 24 28 10 36 47 12 19 Activity Variance Time (te) [(ba)/6]² Critical? 9 X X 13 19.83 7 28 30 7.33 16 4.69 1 4 25 1.78 1 xxx

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

please answer within 30 minutes..

Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 95-time
units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 2 decimal places in your task
time and variance calculations and at least 3 decimal places in your z value calculation. Enter your final probability answer to 3
decimal places.)
Acct. ID
1
2
3
4
5
6
7
Description
Design package
Design product
Build package
Secure patent
Build product
Paint
Test market
Predecessor
None
1
1
2
2
3,4,5
6
Optimistic Most Likely Pessimistic
(a)
(m)
(b)
6
12
24
15
19
28
4
7
27
29
7
16
24
17
4
13
The probability of completing the project in 95 time units is
10
36
47
12
19
Activity
Variance
Time (te) [(ba)/6]2 Critical ?
9
13
19.83
7
28
30
7.33
16
4.69
1
4
25
1.78
1
X
X
X
X
X
Transcribed Image Text:Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 95-time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 2 decimal places in your task time and variance calculations and at least 3 decimal places in your z value calculation. Enter your final probability answer to 3 decimal places.) Acct. ID 1 2 3 4 5 6 7 Description Design package Design product Build package Secure patent Build product Paint Test market Predecessor None 1 1 2 2 3,4,5 6 Optimistic Most Likely Pessimistic (a) (m) (b) 6 12 24 15 19 28 4 7 27 29 7 16 24 17 4 13 The probability of completing the project in 95 time units is 10 36 47 12 19 Activity Variance Time (te) [(ba)/6]2 Critical ? 9 13 19.83 7 28 30 7.33 16 4.69 1 4 25 1.78 1 X X X X X
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.