Given the table below: Activity A B C D E F G H I Dependency A A A B B,C C,D FG E,F,H Duration (weeks) 2 10 9 4 6 12 4 6 3 Max Crash Time (weeks) N/A 2 3 3 5 3 2 1 1 If the indirect cost savings is $1,300,000 per week a) Draw the network diagram b) What is the critical path? Total Crash Cost ($000,000) 16 15 18 10 9 14 9 11 c) Provide the steps and process to crash this project d) What is the maximum time that this project can be crashed, what is the total crashing cost, and what is the new duration? e) Provide the final network diagram (using the maximum crash time)
Text Book Question 4C-12
Please answer the question fully and do not use CHAT GPT. I will report if I am not given honest help. I am struggling with these questions and am in need to get the best help to prepare for my final. So please be wise and do honest work in helping me. Thanks!
- - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Given the table (see picture)
If the indirect cost savings is $1,300,000 per week
a) Draw the network diagram
b) What is the critical path?
c) Provide the steps and process to crash this project
d) What is the maximum time that this project can be crashed, what is the total crashing cost, and what is the new duration?
e) Provide the final network diagram (using the maximum crash time)