1:3 gauged mortar mix Estimating data for unit rate pricing Material Mortar: Details Waste Cost 5% Cement Sand Bricks 1m³ cement, 1400kg 3m3 sand, 4800kg Shrinkage £90.00 per tonne 25% £30.00 per tonne 102.5mm brickwork, to 7% 600 half-brick Assume 10m² be in Staffordshire Smooth Blue Facing £250.00 per thousand delivered to site, Perforated. Laid in stretcher bond, gauged mortar 1:3 0.05m³ mortar for 10m² Unloading Cement Per tonne 1 labourer £30 Bricks ΝΑ Labour details Gang Brickwork 2 Bricklayers 1 labourer 1 Plant Mortar Mix 100-litre mixer Type of Plant bricklayer 60 brick per m² Included in cost of material cost 1 Bricklayer £60.00 per hour 1 labourer £30 per hour Cost Output 4m³/hour £20.00 per hour Output Output of Allow 15% for overheads and profit
1:3 gauged mortar mix Estimating data for unit rate pricing Material Mortar: Details Waste Cost 5% Cement Sand Bricks 1m³ cement, 1400kg 3m3 sand, 4800kg Shrinkage £90.00 per tonne 25% £30.00 per tonne 102.5mm brickwork, to 7% 600 half-brick Assume 10m² be in Staffordshire Smooth Blue Facing £250.00 per thousand delivered to site, Perforated. Laid in stretcher bond, gauged mortar 1:3 0.05m³ mortar for 10m² Unloading Cement Per tonne 1 labourer £30 Bricks ΝΑ Labour details Gang Brickwork 2 Bricklayers 1 labourer 1 Plant Mortar Mix 100-litre mixer Type of Plant bricklayer 60 brick per m² Included in cost of material cost 1 Bricklayer £60.00 per hour 1 labourer £30 per hour Cost Output 4m³/hour £20.00 per hour Output Output of Allow 15% for overheads and profit
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 7RQ
Related questions
Question
Scenario 2 – role of the contractor, QS and unit rate estimating – in
CMA1
The inexperienced client is interested in understanding the cost breakdown of the project and has
asked you to review the estimating data in the table below. Use this to assess the unit rates
produced by the Contractor QS and the returned priced Bill of Quantities included in the CMA.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 7 images
Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,