Why is it recommended that the estimator begin a takeoff of concrete work by measuring the quantity of concrete in an item rather than the amount of formwork?
The reason recommended for the estimator to begin a takeoff of concrete work by measuring the quantity of concrete in an item rather than the formwork amount.
Explanation of Solution
Taking off concrete work must start with the estimator measuring the concrete as the actual concrete descriptions are usually given on the drawings, whereas the details of the formwork are not given. The estimator can then review the needs for the formwork by measuring and estimating the volume of concrete needed followed by the requirements of finishing.
Since only the area of forms in contact with the concrete is measured, at the time of the takeoff, the estimator does not have to review the descriptions of the forms design.
Want to see more full solutions like this?
Chapter 5 Solutions
Fundamentals Of Construction Estimating
- Why is it also preferable to measure the concrete and all other work associated with an item before going on to measure the concrete in another item?arrow_forwardHello! can you please help me with this? I'm stuck because we need to provide explanation and I don't know how to explain. Thank you in advance! Q: What is your process for testing the workability of concrete?arrow_forwardHow do engineers weigh concrete inside the container?arrow_forward
- Q: a) What are the broad types of admixtures? b) How would you improve the bond of fresh concrete to hardened concrete? SIR, PLS GIVE ME PROPER AND CORRECT ANSWER WITH FULL DETAILS. THANKSarrow_forwardWhat is the w/cm ratio of concrete produced using 225 kilograms of portland cement, 75 kilograms of Fly Ash, and 120 kilograms of water?arrow_forwardWhat do you mean by concrete's workability, why do we need it, and how do different aggregate qualities impact concrete's workability?arrow_forward
- help me. number 2arrow_forwardOne of the most critical processes in construction is transporting and managing concrete. Explain each way of carrying and managing concrete in detail.arrow_forwardA reinforce concrete column with the cross-section showed in figure below have the dimensions of 350*350 mm and the clear space between reinforcement and form of 50 mm. The minimum clear space between reinforcement is 230 mm. What is your recommendation for the maximum size of coarse aggregate for the following situation? 230 mm $50 mm 350 mmarrow_forward
- Instruction: Transporting and handling concrete are one of the most important process during constructions. Explain in details each methods of transporting and handling concrete.arrow_forward20 The figure below shows relative frequency histogram for 50 concrete cubes classified according to compressive strength of the cubes. While x- axis represents the class midpoints of compressive strength, y-axis represents relative frequency for concrete cubes. Determine the harmonic mean of compressive strength * .of the cubes Relative Frequency Chart 0.45 0.4 0.35 0.3 0.25 능 0.2 7 0.15 0.1 0.05 25.5 35.5 45.5 55.5 Class Midpoints of Compressive Strength Relative Frequency for Concrete Cubesarrow_forwardQUESTION 5 if there is a concrete slab that is 915' long by 565' 3" wide and 2' 7" thick, how many cubic yards of concrete are needed to pour it? Please round up to the nearest whole number.arrow_forward
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,Construction Materials, Methods and Techniques (M...Civil EngineeringISBN:9781305086272Author:William P. Spence, Eva KultermannPublisher:Cengage Learning