Duration (Days) Activity IPA Optimistic (To) Most Likely (Tm) Pessimistic (Tp) A Н BCDEFGHI В с A, B 6 3 B D D, E C, F, G C. G H, I 2 6494750832 4363547632 11 6 15 11 10 8 10 16 10 62

Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter19: Service Panel Trim-out
Section: Chapter Questions
Problem 7RQ
icon
Related questions
Question

Do the CPM calculations based on most likley durations draw the network diagram select the longest 3 paths and calculate the expected duration and standard deveationfor each path. What would the estimated duration of the project be at minimium 90% confidence

Duration (Days)
Activity
IPA
Optimistic (To)
Most Likely (Tm)
Pessimistic (Tp)
A
Н
BCDEFGHI
В
с
A, B
6
3
B
D
D, E
C, F, G
C. G
H, I
2
6494750832
4363547632
11
6
15
11
10
8
10
16
10
62
Transcribed Image Text:Duration (Days) Activity IPA Optimistic (To) Most Likely (Tm) Pessimistic (Tp) A Н BCDEFGHI В с A, B 6 3 B D D, E C, F, G C. G H, I 2 6494750832 4363547632 11 6 15 11 10 8 10 16 10 62
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning