Scenario 2 – role of the contractor, QS and unit rate estimating – in CMA1 The inexperienced client is interested in understanding the cost breakdown of the project and has asked you to review the estimating data in the table below. Use this to assess the unit rates produced by the Contractor QS and the returned priced Bill of Quantities included in the CMA. Estimating data for unit rate pricing Material Details Waste Cost Mortar: 1:3 gauged mortar mix 5% Cement Sand 1m3 cement,1400kg 3m3 sand, 4800kg Shrinkage 25% £90.00 per tonne £30.00 per tonne Bricks Assume 10m2 102.5mm brickwork, to be in Staffordshire Smooth Blue Facing Perforated. Laid in stretcher bond, gauged mortar 1:3 0.05m3 mortar for 10m2 7% 600 half-brick £250.00 per thousand delivered to site, Unloading Cement Bricks Per tonne NA 1 labourer £30 Included in cost of material Labour details Gang Output cost Brickwork 2 Bricklayers 1 labourer Output of 1 bricklayer 60 brick per m2 1 Bricklayer £60.00 per hour 1 labourer £30 per hour Plant Type of Plant Output Cost Mortar Mix 100-litre mixer 4m3/hour £20.00 per hour Allow 15 % for overheads and profit

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 9RQ: Calculate the cost per cubic yard to place concrete using each of the alternatives described. The...
icon
Related questions
Question

Scenario 2 – role of the contractor, QS and unit rate estimating – in

CMA1

The inexperienced client is interested in understanding the cost breakdown of the project and has

asked you to review the estimating data in the table below. Use this to assess the unit rates

produced by the Contractor QS and the returned priced Bill of Quantities included in the CMA.

Estimating data for unit rate pricing

Material Details Waste Cost

Mortar: 1:3 gauged mortar mix 5%

Cement

Sand

1m3 cement,1400kg

3m3 sand, 4800kg

Shrinkage

25%

£90.00 per tonne

£30.00 per tonne

Bricks

Assume 10m2

102.5mm brickwork, to

be in Staffordshire

Smooth Blue Facing

Perforated. Laid in

stretcher bond, gauged

mortar 1:3

0.05m3 mortar for 10m2

7% 600 half-brick

£250.00 per thousand

delivered to site,

Unloading Cement

Bricks

Per tonne

NA

1 labourer £30

Included in cost of

material

Labour details Gang Output cost

Brickwork 2 Bricklayers

1 labourer

Output of

1

bricklayer

60 brick

per m2

1 Bricklayer £60.00

per hour

1 labourer £30 per

hour

Plant Type of Plant Output Cost

Mortar Mix 100-litre mixer 4m3/hour £20.00 per hour

Allow 15 % for overheads and profit

Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning