CONCEPT
→
Closing Process
16/21
that's 76%
RETAKE
16
questions were answered
correctly
.
5
questions were answered
incorrectly
.
Which of the following is true about the closing process?
Report an issue with this question
●
The closing process should
follow a logical order.
●
The closing process is separate
from the project.
●
The team can be released when
they have finished their
respective deliverables.
●
Documentation can be
completed without having to be
approved.
UNIT 4 — MILESTONE 4
16/21
2
CONCEPT
→
Communicating Lessons Learned
3
Who of the following reviews the final version of the lessons
learned first?
Report an issue with this question
Which of the following reflects a team evaluation criterion?
●
●
●
Entire organization
Project approvers
●
Upper management
●
Project team
●
Ensured completed deliverable
was 95% defect-free
●
Managed conflicts between
stakeholder groups interested in
the project
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Evaluating Project Team
4
Report an issue with this question
Which of the following is an example of a product development
project?
●
●
Met schedule requirements for
completion of project tasks
Worked collectively to manage
identified risks for the project
Manage a project to develop a
new solar-powered camping tent.
●
Manage a project to organize a
convention for new inventors.
●
Manage a project to analyze the
need for a new layout of a retail
store.
●
Manage a project to raise funds
for a national science
competition.
UNIT 4 — MILESTONE 4
16/21
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
CONCEPT
→
Project Management in Context
5
CONCEPT
→
Warehousing Information
6
Report an issue with this question
Which of the following items from a project is stored by an
organization but NOT as a part of project specific files?
Report an issue with this question
Which of the following may occur after the team is released?
●
●
●
Lessons learned
●
Communication plan
Individual evaluations
●
Project schedule
●
Recording lessons learned
Transferring project ownership
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Celebrating Project Completion
7
CONCEPT
→
Evaluating & Reporting Project Success
Report an issue with this question
Which of the following best describes a successful project?
Report an issue with this question
●
●
●
Warehousing project records
Project completion celebration
A project completed on budget
●
A project that finishes early
●
A project that delivers the
specified scope
●
A project completed under
budget
UNIT 4 — MILESTONE 4
16/21
8
CONCEPT
→
Project Life Cycle Review
9
Which activity would Trina perform in Phase 3 of a project to
create a plant nursery at a local hardware store?
Report an issue with this question
Which of the following best describes an individual evaluation?
●
●
●
Verify deliverables are complete.
Manage changes to the
deliverables.
●
Create an estimated timeline for
completion.
●
Develop the work breakdown
structure.
Subjective
●
Specific
UNIT 4 — MILESTONE 4
16/21
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
CONCEPT
→
Evaluating Project Team
10
Report an issue with this question
Which of the following is an example of a lesson learned that is
related to resources used outside the organization?
●
●
Shared
●
Broad
●
A piece of equipment on the
production line broke down and
caused a schedule delay.
●
A deliverable did not meet quality
standards because it was not
tested thoroughly.
One of the groups contracted for
the project failed to meet
production deadlines.
●
The weekly delivery of project
status reports facilitated the
success of the project.
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Documenting Lessons Learned
11
CONCEPT
→
Evaluating Project Readiness
12
Report an issue with this question
In which of the following ways is assessing project impact
different from assessing project readiness?
Report an issue with this question
Which of the following is a reason a project manager might
need to customize the approach taken to manage a project?
●
●
●
Project readiness focuses more
on achieving stated benefits.
●
Project impact focuses more on
the management of risks.
Project impact focuses more on
the project providing value.
●
Project readiness focuses more
on working with the new project
owner.
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Project Management in Context
13
Report an issue with this question
Which of the following do organizations do to ensure future
projects can refer to documentation from past documents?
●
The type of objectives suggested
by stakeholders
●
The level of authority given to the
project manager
●
The educational background of
the project manager
●
The amount of structure the
project manager requires
●
Record project approvals
Warehouse project information
●
Use formal closing process
procedures
UNIT 4 — MILESTONE 4
16/21
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
CONCEPT
→
Warehousing Information
14
CONCEPT
→
Transferring Ownership
15
Report an issue with this question
If the individual taking ownership of a project is identified early
in the project, which information below is NOT reviewed at the
transfer meeting?
Report an issue with this question
During which phase below would a project manager monitor the
work performed to create a deliverable?
●
●
●
Document the paths previous
projects take
●
Project deliverables
●
Outstanding issues
Project scope
●
Project requirements
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Project Life Cycle Review
16
Report an issue with this question
Which of the following statements is true about the post-
transfer follow-up process?
●
●
Phase 2
Phase 3
●
Phase 1
●
Phase 4
●
Following up after the project
should occur indefinitely.
●
Following up should be done in a
face-to-face meeting.
Following up demonstrates
support.
●
Following up takes place
between the project manager
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Transferring Ownership
17
CONCEPT
→
When the Project isn't Ready
18
Report an issue with this question
Which of the following is the main reason a project closing can
be time-consuming?
Report an issue with this question
Which of the following should Will do next in the closing
process after he documents Lessons Learned?
●
●
and the project team.
●
Organizing needed
documentation
●
Evaluating actuals to estimates
●
Releasing the team early
Resolving outstanding issues
UNIT 4 — MILESTONE 4
16/21
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
CONCEPT
→
Closing Process
19
Report an issue with this question
Which of the following do the project approval meeting and the
transfer meeting have in common?
●
●
Transfer ownership of the project.
●
Warehouse project information.
●
Evaluate the project team.
Close outstanding contracts.
Team members attend both
meetings.
●
The deliverable requirements are
reviewed.
●
The schedule is reviewed.
●
The budget is reviewed.
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Project Approval
20
CONCEPT
→
When the Project isn't Ready
21
Report an issue with this question
Which of the following is true when a project is closed and
delivered as is?
Report an issue with this question
●
●
●
The project manager must revisit
project phases to resolve the
issues with deliverables.
●
The deliverables will be improved
over time with new projects.
●
The project team can be released
earlier in the closing process.
The deliverables
are implemented even
though limitations exist.
UNIT 4 — MILESTONE 4
16/21
CONCEPT
→
Evaluating Project Readiness
Which of the following questions should a project manager ask
when evaluating project readiness?
Report an issue with this question
●
How will ownership of the
deliverables be transferred to the
organization?
●
Where will the organization
transfer team members?
●
Will the organization realize the
expected advantages when the
project is implemented?
Will the deliverables meet the
specified requirements?
About
Contact Us
Privacy Policy
Terms of Use
© 2023 SOPHIA Learning, LLC. SOPHIA is a registered trademark of SOPHIA Learning, LLC.
UNIT 4 — MILESTONE 4
16/21