Question
Chapter B, Problem 8DQ
Summary Introduction
To determine: The number of feasible solutions in a linear program and the ones we need to analyze to find the optimal solution.
Introduction:
Linear programming:
It is a linear optimization technique followed to develop a best outcome for the problem on hand. The outcome might be maximum profit or less cost which are represented by a linear relationship. The outcome will take into consideration the constraints present in achieving the solution.
Feasible solution:
A feasible solution is a set of all the possible values for the defined decision variables. The feasible solution is achieved after satisfying all the constraints.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What is linear programming?
What do Linear programming problems involve?
What are the benefits of linear programming models ?
Chapter B Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. B - Prob. 1DQCh. B - Prob. 2DQCh. B - Prob. 3DQCh. B - Prob. 4DQCh. B - Prob. 5DQCh. B - Prob. 6DQCh. B - Prob. 7DQCh. B - Prob. 8DQCh. B - Prob. 9DQCh. B - Prob. 10DQ
Ch. B - Prob. 11DQCh. B - Where a constraint crosses the vertical or...Ch. B - Prob. 13DQCh. B - The LP relationships that follow were formulated...Ch. B - Prob. 2PCh. B - Prob. 3PCh. B - B.4. Consider the following linear programming...Ch. B - Prob. 5PCh. B - Prob. 6PCh. B - Green Vehicle Inc. manufactures electric cars and...Ch. B - Prob. 8PCh. B - Prob. 9PCh. B - Prob. 10PCh. B - Prob. 11PCh. B - Prob. 12PCh. B - Prob. 13PCh. B - Prob. 14PCh. B - Prob. 22PCh. B - A fertilizer manufacturer has to fulfill supply...Ch. B - Prob. 25PCh. B - Prob. 26PCh. B - Prob. 27PCh. B - Prob. 28PCh. B - Prob. 29PCh. B - Prob. 30PCh. B - How many corner points are there in the feasible...Ch. B - Prob. 34PCh. B - Prob. 35PCh. B - Prob. 36PCh. B - Prob. 37PCh. B - Prob. 38PCh. B - Bowman Builders manufactures steel storage sheds...Ch. B - Prob. 40PCh. B - Prob. 41PCh. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Prob. 1.1VCCh. B - Prob. 1.2VCCh. B - Prob. 1.3VCCh. B - Prob. 1.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- How would you write the optimal solution for these?arrow_forwardShow your step-by-step process using THE SPECIAL PURPOSE LINEAR PROGRAMMING: MODI TRANSPORTATION METHOD to solve this problem. XYZ Incorporated has received a contract to supply gravel to three new road projects located at three different locations. Project A needs 174 truckloads, Project B needs 204 truckloads, and Project C needs 143 truckloads. The company has three gravel warehouses located in three different places. Warehouse 1 has 158 truckloads available, warehouse 2 has 184, and warehouse 3 has 179. The cost of transportation from the warehouse to the projects are: from warehouse 1 to Projects A, B, C = Php 4, Php 8, Php 8 per truckload respectively. From warehouse 2 to Projects A, B, C = Php 16, Php 24, Php 16 per truckload respectively. From warehouse 3 to Projects A, B, C = Php 8, Php 16, Php 24 per truckload respectively. The objective is to design a plan of distribution that will Minimize the cost of transportation.arrow_forwardI need solve this please fastarrow_forward
- Explain linear programming that has feasible region with infinite number of solutions ?arrow_forwardDiscuss several disadvantages of linear programming; clearly explain the reasons for your choices.arrow_forwardKara wants to build a business. She has plenty of capital and potential investors and partners. She wants to avoid the burden of sole liability for her business and wants to be able to close the business when she is no longer interested in it. Which of the following would lead Kara to choose a sole proprietorship organization for her business? Avoidance of sole liability Ability to close the business easily Many potential investors/partners Plenty of capitalarrow_forward
- I need a detailed explanation and assistance to solve this proble: A client asks his stockbroker to invest $100,000 for maximum annual income, subject to the three conditions: Spread the investment over no more than three different stocks. Put no more than 40 percent of the money into any one stock Put a minimum of $10,000 into an oil stock. The broker has identified three stocks for investment. Their estimated annual returns per share and price per share are shown in the following table: Stock Price per Share Estimate Annual Return per Share Oil $120 $11 Auto $52 $4 Pharmaceutical $18 $2 The client wishes to use LP to determine the optimal number of shares to buy for each stock, so as to maximize the total estimated return. a) Write down the decision variables. b) Write down the optimization statement for the objective function. c) Write down the constraints.arrow_forwardYou own a combination architectural/engineering company. I long-ter m client just asked your firm to design a boat dock that can accommodate 20 boats. Please list 12 questions that you would need to ask the client in order to properly design the boat dock to be economical, safe, and long-lasting. Please also explain the purpose of asking each question.arrow_forwardScenario You are going to plant a rectangular flower bed consisting of tulips in the middle surrounded by daisies on the outside. You have the same amount of each flower and will need an equal area for each. You want the border of daisies to be uniform around the tulips in the middle, as shown in the diagram below:arrow_forward
- Sarah has a startup business that makes two distinct bird feeders that she has designed. Sarah is planning on operating a small factory to build the bird feeders. She is looking at two possible locations, A and B. If she chooses location A, the lease on the building will be higher than location B, thus leading to higher fixed costs than what she would have with location B. However, if she makes more than 20,000 units, both locations will likely have to be expanded, both the physical buildings and the manufacturing equipment. Variable costs to produce each unit will vary by location as well as by product. For example, the first design will have variable costs of $10 and $15 in locations A and B respectively, while the second bird feeder design will have variable costs of $20 and $25 respectively depending on location. However, she thinks that variable costs will decrease if she sells more than 5,000 units, as she will receive discounts from her suppliers at that point. She is unsure of…arrow_forwardWhat is the difference between linear programming and non-linear programming? Describe practical examples.arrow_forwardCreative Robotics (CR) manufactures two lightweight robots designed for easier house-cleaning. The Alpha-ONE model is older, heavier, and is designed for carpet cleaning. The Alpha-TWO model is newer, lighter, and is designed primarily for wooden floor cleaning. The management team is trying to identify how to minimize the total costs of producing these two models. Their full-time workers consist of primarily manufacturing experts and about 3 people are required to commit themselves to manufacture the Alpha-ONE model and 4 for the Alpha-TWO model, per day. They have a total pool of 100 full-time workers now but are willing to hire more manufacturers if required. Similarly, the Alpha-TWO model is more complex and management has a pool of 20 part-time technical workers to help with the complexity, every day. Again, they are willing to hire more part-time workers if required to assist with the Alpha-TWO model. As far as staff allocations for additional assistance in manufacturing…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.