Summary Introduction
To determine: The number of servers that must report to work at the beginning of each period.
Introduction:
Linear programming:
It is a linear optimization technique followed to develop the best outcome for the linear programming problem. The outcome might be to maximize profit, minimize cost, or to determine the optimal product mix. The outcome will take the constraints present in achieving the solution into consideration.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Don't used Chat gpt
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 What is the direct labor content (in seconds per unit)?
A Support Labor Staff lifts bricks from 30, 53-ft long trailers in their 8-hr shift using forklifts. The typical
53-ft trailer holds 26 pallets of bricks. The warehouse receives in the first half of the shift and ships in the second
half of the shift. The work standard for forklift operations is listed below:
Load/unload pallet from trailer
45 sec
Move from dock to warehouse or warehouse to dock
120 sec
Load/unload pallet from Truck
30 sec
Move within warehouse
60 sec
Calculate the number of forklifts needed to process all the pallets is most nearly:
А. 7
В. 9
С. 10
D. 11
Chapter B Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. B - Prob. 1DQCh. B - Prob. 2DQCh. B - Prob. 3DQCh. B - Prob. 4DQCh. B - Prob. 5DQCh. B - Prob. 6DQCh. B - Prob. 7DQCh. B - Prob. 8DQCh. B - Prob. 9DQCh. B - Prob. 10DQ
Ch. B - Prob. 11DQCh. B - Where a constraint crosses the vertical or...Ch. B - Prob. 13DQCh. B - The LP relationships that follow were formulated...Ch. B - Prob. 2PCh. B - Prob. 3PCh. B - B.4. Consider the following linear programming...Ch. B - Prob. 5PCh. B - Prob. 6PCh. B - Green Vehicle Inc. manufactures electric cars and...Ch. B - Prob. 8PCh. B - Prob. 9PCh. B - Prob. 10PCh. B - Prob. 11PCh. B - Prob. 12PCh. B - Prob. 13PCh. B - Prob. 14PCh. B - Prob. 22PCh. B - A fertilizer manufacturer has to fulfill supply...Ch. B - Prob. 25PCh. B - Prob. 26PCh. B - Prob. 27PCh. B - Prob. 28PCh. B - Prob. 29PCh. B - Prob. 30PCh. B - How many corner points are there in the feasible...Ch. B - Prob. 34PCh. B - Prob. 35PCh. B - Prob. 36PCh. B - Prob. 37PCh. B - Prob. 38PCh. B - Bowman Builders manufactures steel storage sheds...Ch. B - Prob. 40PCh. B - Prob. 41PCh. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Prob. 1.1VCCh. B - Prob. 1.2VCCh. B - Prob. 1.3VCCh. B - Prob. 1.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- William Beebe owns a small shoe store. He has 10 pairs of shoes that requireresoling and polishing. He has a machine that can resole one pair of shoes at atime, and the time required for the operation varies with the type and condition of theshoe and the type of sole that is used. Shoes are polished on a machine dedi-cated tothis purpose as well, and polishing is always done after resoling. His assistant generally does the polishing while Mr. Beebe does the resoling. The resoling and polishingtimes (in minutes) are Shoes Resoling Time Polishing Time1 14 32 28 13 12 24 6 55 10 106 14 67 4 128 25 89 15 510 10 5In what order should the shoes be repaired in order to minimize the total makespanfor these 10 jobs?arrow_forwardPanini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. The table below provides demand data: Grilled Vegetables Grilled Chicken Pastrami Demand per hour 25 9 12 There are up to five steps in the process of making sandwiches listed below with activity times (if no activity time, then than step is not done for that sandwich). Only 50% of customers want their sandwich toasted, no matter which sandwich is ordered. Step Grilled Vegetables(in minutes) Grilled Chicken(in minutes) Pastrami(in minutes) Cut bread 1 1 1 Grill 1.2 1.2 Slice meat 2 Toast 1.2 1.2 1.2 Wrap 0.8 0.8 0.8 Suppose Panini employs 1 worker at each step. a) Does Panini have enough capacity to fulfill the current demand for sandwiches? (b) What is the current capacity cushion for Panini? (as a %) c) If demand for Pastramis increase with the percentage indicated below, how much additional workers should Panini hire (if any), and where…arrow_forwardA process improvement team is working to improve the production output at the Johnson Manufacturing plant’sHeader Cell that manufactures a key component, headers, used in commercial air conditioners. A header is partof the circulatory system of a commercial air conditioner that moves coolant between various components suchas the evaporator coil and the condenser coil. Currently, the header production cell is scheduled separately fromthe main work in the plant. Often, individual headers are not sequenced to match the product they go into on thefinal assembly line in a timely fashion, and so the product can sit in queue waiting for a headerarrow_forward
- CC Car Wash specializes in car cleaning services. The servicesoffered by the company, the exact service time, and the resources needed for each of them aredescribed in the table following: service description processing time resources used A. Wash Exterior car washing anddrying 10 min. 1 automated washingmachine B. Wax Exterior car waxing 10 min. 1 automated waxingmachine C. Wheel cleaning Detailed cleaning of all wheels 7 min. 1 employee D. Interior cleaning Detailed cleaning inside thecar 20 min. 1 employee The company offers the following packages to their customers: Package 1: Includes only car wash (service A). Package 2: Includes car wash and waxing (services A and B). Package 3: Car wash, waxing, and wheel cleaning (services A, B, and C). Package 4: All four services (A, B, C, and D).Customers of CC Car Wash visit the station at a constant rate (you can ignore any effects ofvariability) of 40 customers per day. Of these customers, 40 percent buy Package 1, 15…arrow_forwardAbbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make one large production run per model type. Plastic injection molding machines are used to make these parts, and it is time consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with a one-hour lunch break and one-half hour for operator breaks. Consolidated Work Orders Model XVT-5 Case Model UYT-3 Case Model KLY-6 Case Work Order Quantity 9,600 panels 7,900 12,000 Setup (Changeover) Time per Work Order (minutes) 98 160 What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place. The total workload is hours. How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number. To do this work in 1 day they need machine(s). machine(s). To do this…arrow_forwardAbbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make one large production run per model type. Plastic injection molding machines are used to make these parts, and it is time consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with a one- hour lunch break and one-half hour for operator breaks. Consolidated Work Orders Model XVT-5 Case Model UYT-3 Case Model KLY-6 Case Work Order Quantity 8,800 panels 8,700 12,400 Setup (Changeover) Time per Work Order (minutes) 86 63 135 Processing Time per Panel (seconds) 2.50 2.22 4.11 What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place. The total workload is hours. How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number. To do this work…arrow_forward
- Can someone please help solve.arrow_forwardJOHNSON’S RULE Five specialty jobs at a La Crosse, Wisconsin, tool and die shop must be processed through two workcenters (drill press and lathe). The time for processing each job follows:Work (processing) Time for Jobs (hours)JOBWORK CENTER 1(DRILL PRESS) WORK CENTER 2(LATHE)A5 2B3 6C8 4D 10 7E 7 12arrow_forwardMacon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. D Demand Forecast Component A B C Time Standard Processing Setup (hr/unit) (hr/lot) 0.04 1.0 0.20 4.4 0.05 8.5 Lot Size (units/lot) 50 75 100 Demand Forecast Pessimistic Expected Optimistic Pessimistic 16,000 10,000 18,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next…arrow_forward
- Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 25 percent capacity cushion is best. i Demand Forecast Component A B C Time Standard Processing (hr/unit) 0.04 0.20 0.05 Setup (hr/lot) 1.0 4.4 8.5 Lot Size (units/lot) 50 75 100 Demand Forecast Pessimistic Expected 16,000 17,000 10,000 12,000 18,000 24,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next…arrow_forward请整理图中问题,并回答arrow_forwardMacon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 30 percent capacity cushion is best. Time Standard Demand Forecast Setup (hr/lot) Lot Size Processing (hr/unit) Component Pessimistic Expected Optimistic (units/lot) A 0.05 1.0 50 16,000 16,000 27,000 В 0.30 4.6 80 11,000 12,000 17,000 C 0.05 8.3 100 16,000 23,000 35,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,