Concept explainers
Interpretation: The performance according to sequencing rules FCFS, SPT, EDD and CR in relation to minimizing average tardiness has to be evaluated.
Concept Introduction:
Optimal sequence: It is supposed to be sequence or series of jobs that has to take place to minimize the idle time and at the same time all the jobs are completed.
Answer to Problem 30AP
When all the 4 sequencing rules are compared, it is found that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Explanation of Solution
Given information:
The information given to us is as follows:
Cars | Repair time (days) | Promised date |
1 | 3 | 5 |
2 | 2 | 6 |
3 | 1 | 9 |
4 | 4 | 11 |
5 | 5 | 8 |
Let us know calculate the mean flow time and average tardiness.
An important fact to be kept in mind is that in a situation where the due time is greater than the completion time, the tardiness should be considered as 0.
Calculation of average tardiness and number of tardy jobs using FCFS rule:
FCFS rule states that the person or job coming first will be attended first.
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 2 |
| 6 | 0 |
3 | 1 |
| 9 | 0 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total |
| 7 |
Completion time is calculated by considering the cumulative of repair time values.
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to FCFS rule of sequencing is 1.4 days and the total number of tardy jobs is 1.
Calculation of average tardiness and number of tardy jobs using SPT rule:
SPT when expanded becomes shortest processing time. In the rule, the jobs must be arranged in increasing order according to the processing time.
Cars | Repair time (days) | Ranking done in increasing order |
(1) | (2) | (3) |
1 | 3 | 3 |
2 | 2 | 2 |
3 | 1 | 1 |
4 | 4 | 4 |
5 | 5 | 5 |
Total |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars | Repair time after ranking (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
3 | 1 |
| 9 | 0 |
2 | 2 |
| 6 | 0 |
1 | 3 |
| 5 | 1 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total | 35 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to SPT rule of sequencing is 1.6 days and the total number of tardy jobs is 2.
Calculation of average tardiness and number of tardy jobs using EDD rule:
EDD when expanded becomes Earliest due date. In the rule, the jobs must be arranged in increasing order according to the promised time.
Cars | Repair time (days) | Promised date | Ranking of promised date done in increasing order |
1 | 3 | 5 | 1 |
2 | 2 | 6 | 2 |
3 | 1 | 9 | 4 |
4 | 4 | 11 | 5 |
5 | 5 | 8 | 3 |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars (corresponding values according to ranks) | Repair time (days)
(corresponding values according to ranks) | Completion time | Promised date after ranking | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 5 |
| 6 | 0 |
5 | 5 |
| 8 | 2 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 44 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to EDD rule of sequencing is 1.6 days and the total number of tardy jobs is 3.
Finally, let us calculate the average tardiness and total number of tardy jobs according to CR rule.
CR when expanded becomes Critical Ratio. The formula to be used is as follows:
Let us that the current time is 0.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
5 | 5 | 8 |
|
Hence, the job having a minimum critical ration should be considered first. In our case, the car 5 has the minimum critical ratio of 1.6. So, it should be considered first for repair. After repair, car 5 can be ignored for further calculations.
Now, the current time for next critical ratio can be calculated as below:
Using this new current time, the critical ratio can be calculated for the rest of the cars.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, the minimum critical ratio is 0 of Car 1. Hence car 1 should be considered for repair.
Further, a new current time has to be calculated.
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 2 has minimum critical ratio of -1. So, it has to be repaired after car1.
Further, a new current time has to be calculated for the remaining 2 cars
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 3 has minimum critical ratio of -1. So, it has to be repaired after car 2 and the remaining job i.e., repair of car 4 should be done last.
Therefore, the sequence we get using Critical ratio rule is
After deriving the sequence, we have to calculate the completion time and tardiness.
Calculation of completion time and tardiness:
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
5 | 5 |
| 8 | 0 |
1 | 3 |
| 5 | 3 |
2 | 2 |
| 6 | 4 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 49 | 13 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to CR rule of sequencing is 2.6 days and the total number of tardy jobs is 4.
When all the 4 sequencing rules are compared, we find that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Want to see more full solutions like this?
Chapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- The results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value. Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be includedarrow_forwardi). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.arrow_forwardIn the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why. ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.arrow_forward
- i). Complete the table for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible. You should support your answer with numerical data derived from Table 3. In comparing the costs, state any other assumptions made.arrow_forwardi). Complete for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible.arrow_forwardComplete the table for a Chase production plan.arrow_forward
- How much can the garden centre expect to sell during each quarter of next year (Year 3) accounting for seasonality? Your forecast must make use of seasonal indices. All workings must be shown in full. (NOTE: Please round your calculations to three decimal places).arrow_forwardPS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forwardTisjTzktxyduduarrow_forward
- Not use ai pleasearrow_forwardNot use ai pleasearrow_forwardWhat is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impactarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing