Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

Question
Book Icon
Chapter 9.5, Problem 3P

a.

Summary Introduction

Interpretation:The concept of term“flow shop” is to be explained.

Concept Introduction: This term relates to the manufacturing operations and signifies a distinct type of shop layout with equipment installed to provide a flow of products from one process to another. The products can be in single piece (the utopian objective) or may be in batches. The idea is to minimize the throughput time of the products and also the in-process inventory.

b.

Summary Introduction

Interpretation: The concept of theterm “job shop” is to be explained.

Concept Introduction: Theterm job shop relates toa manufacturing establishment having a number of processing stations with a capability of handling a variety of customer orders (may be customized) in small to medium batches. Say there are ‘n’ processing stations. The jobs that are received and accepted have to be processed on ‘m’ of THESE very stations where ‘m’ < ‘n’. If ‘m’ is > ‘n’, the job shop has arrangements to outsources the processes not available internally.

At any time, normally a job shop shall be working on more than one order.

C.

Summary Introduction

Interpretation:Sequential v/s parallel processing are to be briefly explained.

Concept Introduction: As the names imply:

  • Sequential processing means a number of jobs being processed in a certain sequence i.e. one after the other.
  • In parallel processing on the other hand, when there is more than one job to be processed, some of the jobs are processed simultaneously-means in parallel.

D.

Summary Introduction

Interpretation:The term “MAKESPAN” in manufacturing operations is to be explained.

Concept Introduction: In manufacturing, when there are a number of jobs in a particular schedule, MAKESPAN is the total time elapsed between the start of the first job (in the schedule) to the exit of the last item of the last job (in the schedule). Thus it is a parameter signifying the efficiency of the scheduling process.

E.

Summary Introduction

Interpretation:The term “tardiness” as applicable to manufacturing operations is to be explained.

Concept Introduction: Tardiness is a term used in scheduling as almost equivalent to ‘delay in delivery’. If during a specific time period, n jobs are to be delivered each with its specific delivery requirements and some jobs are sure to be late (due to the plant capacity), the total delay/s in all the jobs or the number of jobs delayed is called the tardiness.

Blurred answer
Students have asked these similar questions
Dyson, a high-tech home appliance maker, has cut ties with Malaysian supplier ATA IMS Bhd following an audit of the company's labour practices and allegations by a whistleblower. ATA is already under US investigation over forced labour allegations. Dyson has terminated its contracts and is in talks with its customer over the audit findings. ATA, which produces parts for Dyson's vacuum cleaners and air purifiers, tumbled 30% to its lowest since April 2020. The termination is a significant blow for Malaysia, a major electronics manufacturing hub, which has faced scrutiny this year over claims of abusive working and living conditions. Dyson terminated the relationship with six months' contractual notice, hoping it would give ATA the impetus to improve and enable an orderly withdrawal in the interests of the workers they employ. Former ATA worker Dhan Kumar Limbu was beaten by police in Malaysia after sharing information about conditions at the factory with activists. ATA denied all…
Question content area Part 1 Oakwood Hospital is considering using ABC analysis to classify laboratory SKUs into three​ categories: those that will be delivered daily from their supplier​ (Class A​ items), those that will be controlled using a continuous review system​ (B items), and those that will be held in a two bin system​ (C items).   The following table shows the annual dollar usage for a sample of eight SKUs. Fill in the blanks for annual dollar usage below. ​(Enter your responses rounded to the nearest whole​ number.)   Part 2 Rank the SKUs in descending order on the basis of their annual dollar usage and fill in the table with the ranked​ SKU's percentage of dollar usage. ​(Enter your responses rounded to two decimal​ places.)
Sam's Pet Hotel operates 51 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $13.00 per bag. The following information is available about these bags: > Demand 70 bags/week > Order cost $58.00/order > Annual holding cost 30 percent of cost > Desired cycle-service level = 80 percent >Lead time 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 70 bags is incorrect and actual demand averages only 45 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College