Concept explainers
(a)
Interpretation:The network representing the assembly operation is to be determined.
Concept Introduction:
The method which is used for the graphical representation of task or assembly operation by using the different symbol indicating different operation is known as network diagram.
(b)
Interpretation:The minimum cycle time and the balance which results from ranked positional weight technique are to be determined.
Concept Introduction:
The method which is used for the graphical representation of task or assembly operation by using the different symbol indicating different operation is known as network diagram.
(c)
Interpretation: The minimum cycle time which can be achieved from the three-station cycle is to be determined.
Concept Introduction:
The method which is used for the graphical representation of task or assembly operation by using the different symbol indicating different operation is known as network diagram.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- Please helparrow_forwardEmployees Layoffs at the University Medical Center The University Medical Center is medium-sized, 300-bed capacity hospital at Dasmarinas Cavites. The facilities have grown gradually over the years and are now the 2nd largest in the town of Dasmarinas. It is entirely nonunion and has never experienced an employee layoff since its inception. Sister Veronica Cornista, the Chief Executive Officer of the hospital for 8 years presented a rather bleak financial of the BOD. This according to her is the result of the declining occupancy rate which has affected the hospital’s revenues to such an extent that it ran a deficit for the first time last 1998. Such declines have not been unusual for this industry because of increasing competition. So far, the only response to these changes has been tightening of requirements for equipment or supply purchases. The projected deficit for the coming year is around 1,300,000 unless some additional revenues were identified or some additional savings…arrow_forwardManufacturing Company uses FIFO method of accumulating costs in a two-department process. Materials are introduced at the inception of the process except for a special material which is added in department 2 at 60% completion as to overhead. Inspection is done at the end of the process in both departments. Production data for Department 2 are given below: In process, beginning, (80% labor, 70% overhead)2,000 Transferred in 14,900 In process, ending (40% labor, 20% overhead) 3,000 Normal spoilage 200 Abnormal spoilage (found at 30% completion as to laborand 15% as to overhead due to internal failure) 400 Cost data for the month:In process beginning:Transferred in 15,020 Special materials 1,900 Direct labor 4,388 Overhead 11,044 Current costs:Transferred in 137,080 Special materials 14,030 Direct labor 46,000 Overhead 113,564 The cost of units transferred to finished goods is?The cost of spoilage charged to revenue is?arrow_forward
- Below is information related to: historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B routing and standard times to produce Product B • the product structure for Product B • a MPS covering 3 periods for Products A and B. MPS in Units End Product 2 Processing Time A 50 45 25 Historical % End Product Hours/Unit wC B. 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1 1.25 D (3 required) D 50 200 0.07 100 200 0.08 F 100 300 0.04 (2 required) A. Develp a rough cut capacity plan for the three work centers based on historical factors. Please fill in the table below with your final calculations. Show your work in the space belov Historical Total Work Center Percentage 1 2 3 Hours 100 200 300 Total Required Capacity Show any work here:arrow_forwardBriefly explain the Drum-Buffer-Rope methodology.arrow_forwardAn assembly line is to be designed to operate 7.5 hours per day and supply a steady demand of 300 units per day. a)assign tasks to workstations using the longest operating time b)suppose demand increase by 10%.how would you react to this?assume you can operatee only 7.5 hours per day TASK PRECEDING TASKS PERFORMANCE TIME(seconds) a - 70 b - 40 c - 45 d a 10 e b 30 f c 20 g d 60 h e 50 i f 15 j g 25 k h,i 20 l j,k 25arrow_forward
- Up, Up, and Away is a producer of kites and wind socks.Relevant data on a bottleneck operation in the shop for theupcoming fiscal year are given in the following table:Item Kites Wind SocksDemand forecast 30,000 units/year 12,000 units/yearLot size 20 units 70 unitsStandard processing time 0.3 hour/unit 1.0 hour/unitStandard setup time 3.0 hours/lot 4.0 hours/lotThe shop works two shifts per day, 8 hours per shift, 200 daysper year. Currently, the company operates four machines,and desires a 25 percent capacity cushion. How many ma-chines should be purchased to meet the upcoming year’s de-mand without resorting to any short-term capacity solutions?arrow_forwardTheories and concepts: Cause of the difficulties In this section, I will explain the causes of the difficulties which I have explained above. The reason for the missing cages uses to be that the cage is still being picked or not and if the picker is still using the cage to pick the items then request the picker to drop the cage off to the packing department so that the items can be packed and sent out the shipping department for the delivery. Also, if the cage is not in the picking department buffer or pack buffer and is not being picked then as a process guide it was my duty to search for the cage at the packing stations first, and if not found then to escalate to the management so that relevant department can be contacted for the action. During the critical pool time, there were a few shipments IDs use to get sent down from the picking department which they couldn’t send into the picker’s scanners as either the batch assigned for the item by the stowing department would be wrong or…arrow_forwardWhich operation is the bottleneck of this process? a. Stocking b. Pricing c. Spotting d. Shipping e. Impossible to determinearrow_forward
- Figure 9.22 illustrates an architect's drawing of Arnold PalmerHospital's new circular pod system. If nurse Susan Jones's dayincludes 7 trips from the nursing pod to each of the 12 rooms(back and forth), 20 trips to central medical supply, 6 trips tothe break room, and 12 trips to the pod linen supply, how many miles does she walk during her shift? What are the differences in the travel times between the two nurses for this random day?arrow_forwardOperation managemetnarrow_forwardTo meet holiday demand, Alex's Pie Shop requires a production line that is capable of producing 50 pecan pies per week, while operating only 40 hours per week. There are only four steps required to produce a single pecan pie with respective processing times of 5 minutes, 5 minutes, 45 minutes, and 15 minutes. a. What should be the line's cycle time? b. What is the smallest number of workstations Alex could hope for in designing the line considering this cycle time? c. Suppose that Alex finds a solution that requires only four stations. What would be the efficiency of this line?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,