a)

Summary Introduction

To draw: The precedence diagram.

b)

Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

c)

Summary Introduction

To determine: The production rate.

d)

Summary Introduction

To determine: The theoretical minimum number of workstations.

e)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

f)

Summary Introduction

To determine: The total idle time per cycle.

g)

Summary Introduction

To assign: The different tasks to different workstations and identify the efficiency.

Blurred answer
Students have asked these similar questions
A paced assembly line has been devised to manufacture​ calculators, as the following data​ show:                                                                                                                            LOADING... Station Work Element Assigned Work Element Time​ (min) S1 A 4.0 S2 ​D, E 0.9​, 1.5 S3 C 5.0 S4 ​B, F, G 1.1​, 1.0​, 1.3 S5 ​H, I, J 1.1​, 0.5​, 1.8 S6 K 4.0 a. What is the maximum hourly output rate from this​ line? ​(Hint​: The line can only go as fast as its slowest​ workstation.)   The maximum hourly output rate is nothing calculators per hour. ​(Enter your response as an​ integer.) B. What cycle time corresponds to this maximum output rate? C. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each? 10-hour shift? D. What is the line's efficiency?
Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line activities are:                                                                                                               a) Draw the precedence diagram.b) Tf the daily (24-hour) production rate is 96 units, what is the highest allowable cycle time?c) If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate?d) With a 10-minute cycle time, what is the theoretical minimum number of stations with which the line can be balanced?e) With a I 0-minute cycle time and six workstations, what is the efficiency?f) What is the total idle time per cycle with a I 0-minute cycle time and six workstations?g) What is the best workstation assignment you can make without exceeding a I 0-minute cycle time, and what is its efficiency?
Please help
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.