a)
To draw: The precedence diagram.
a)

Answer to Problem 20P
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 3 | - |
B | 6 | - |
C | 7 | A |
D | 5 | A, B |
E | 2 | B |
F | 4 | C |
G | 5 | F |
H | 7 | D, E |
I | 1 | H |
J | 6 | E |
K | 4 | G, I, J |
Total | 50 |
- Number of hours / day is 24
- Output is 96 instruments / day.
Precedence diagram:
b)
To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
b)

Answer to Problem 20P
The cycle time is 15 minutes / unit.
Explanation of Solution
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 15 minutes / unit.
c)
To determine: The production rate.
c)

Answer to Problem 20P
The production rate is 144 units / day.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate production rate:
Calculation of cycle time:
The production rate is 144 units / day.
d)
To determine: The theoretical minimum number of workstations.
d)

Answer to Problem 20P
The theoretical minimum number of workstations is 5 workstations.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 5 workstations.
e)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
e)

Answer to Problem 20P
The efficiency is 83.3%.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Number of workstations = 6
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
f)
To determine: The total idle time per cycle.
f)

Answer to Problem 20P
The idle time is 10 minutes / cycle.
Explanation of Solution
Given information:
Number of workstations = 6
Cycle time = 10
Calculation of total idle time per cycle:
The total idle time is 10 minutes / cycle.
g)
To assign: The different tasks to different workstations and identify the efficiency.
g)

Explanation of Solution
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (minutes) | Available cycle time (minutes) |
1 | 10 | |||
A, B | A | 3 | 7 | |
B | B | 6 | 1 | |
1 (Idle time) | ||||
2 | 10 | |||
C, D, E | C | 7 | 3 | |
3 (Idle time) | ||||
3 | 10 | |||
D, E, F | D | 5 | 5 | |
E, F | E | 2 | 3 | |
3 (Idle time) | ||||
4 | 10 | |||
F, G, H, I | F | 4 | 6 | |
G, H, I | G | 5 | 1 | |
1 (Idle time) | ||||
5 | 10 | |||
J, H, I, K | H | 7 | 3 | |
H, I, K | I | 1 | 2 | |
2 (Idle time) | ||||
6 | 10 | |||
K, J | J | 6 | 4 | |
K | K | 4 | 0 |
Workstation | Task assigned | Idle time |
1 | A, B | 1 |
2 | C, D | 3 |
3 | D, E | 3 |
4 | F, G | 1 |
5 | H, I | 2 |
6 | J, K | 0 |
Total | 10 |
Efficiency:
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
Want to see more full solutions like this?
Chapter 9 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Do you feel there is anything positive about rework?arrow_forwardDo you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forward
- Have you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forwardResearch a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forward
- Do you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forwardGiven the significant impact on finances, production timelines, and even equipment functionality, as you pointed out, what do you believe is the most effective single strategy a company can implement to significantly reduce the occurrence of rework within their operations?arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forward
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forwardRead the project statement and answer ALL of the questions that follow PROJECT STATEMENT The African Integrated High-Speed Railway Network (AIHSRN). African nations are preparing to invest billions in a significant overhaul of their rail infrastructure as part of an ambitious plan for the continent. One of the key projects underway is the African Integrated High-Speed Railway Network (AIHSRN), which aims to connect Africa's capital cities and major commercial centres with a high-speed railway network to enhance continental trade and competition. This network will span 2,000 km (1,243 miles) and connect 60 cities, including Nairobi, Lagos, Cairo, and Dakar. It will improve access to essential markets, enhance economic cooperation, and encourage regional collaboration. The plan is poised to revolutionise intra-African trade by reducing travel times and lowering transportation costs, making trade between African nations more competitive. The trains will be capable of reaching speeds of up…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning