a)

Summary Introduction

To draw: The precedence diagram.

a)

Expert Solution
Check Mark

Answer to Problem 20P

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 9, Problem 20P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 3 -
B 6 -
C 7 A
D 5 A, B
E 2 B
F 4 C
G 5 F
H 7 D, E
I 1 H
J 6 E
K 4 G, I, J
Total 50  
  • Number of hours / day is 24
  • Output is 96 instruments / day.

Precedence diagram:

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 9, Problem 20P , additional homework tip  2

b)

Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

b)

Expert Solution
Check Mark

Answer to Problem 20P

The  cycle time is 15 minutes / unit.

Explanation of Solution

Formula to calculate cycle time:

Cycle time=Number of hours per dayDaily production× Number of minutes / hour

Calculation of cycle time:

Cycle time=2496×60=1,44096=15 minutes / unit

The  cycle time is 15 minutes / unit.

c)

Summary Introduction

To determine: The production rate.

c)

Expert Solution
Check Mark

Answer to Problem 20P

The  production rate is 144 units / day.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate production rate:

Cycle time=Number of hours per dayCycle time× Number of minutes / hour

Calculation of cycle time:

Cycle time=2410×60=1,44010=144 units / day

The  production rate is 144 units / day.

d)

Summary Introduction

To determine: The theoretical minimum number of workstations.

d)

Expert Solution
Check Mark

Answer to Problem 20P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=5010=5 workstations

The theoretical minimum number of workstations is 5 workstations.

e)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

e)

Expert Solution
Check Mark

Answer to Problem 20P

The efficiency is 83.3%.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Number of workstations = 6

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

f)

Summary Introduction

To determine: The total idle time per cycle.

f)

Expert Solution
Check Mark

Answer to Problem 20P

The  idle time is 10 minutes / cycle.

Explanation of Solution

Given information:

Number of workstations = 6

Cycle time = 10

Calculation of total idle time per cycle:

Total idle time=(Number of workstations×Cycle time)-Total task time=(6×10)-50=60-50=10 minutes / cycle

The  total idle time is 10 minutes / cycle.

g)

Summary Introduction

To assign: The different tasks to different workstations and identify the efficiency.

g)

Expert Solution
Check Mark

Explanation of Solution

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (minutes) Available cycle time (minutes)
1 10
A, B A 3 7
B B 6 1
1 (Idle time)
2 10
C, D, E C 7 3
3 (Idle time)
3 10
D, E, F D 5 5
E, F E 2 3
3 (Idle time)
4 10
F, G, H, I F 4 6
G, H, I G 5 1
1 (Idle time)
5 10
J, H, I, K H 7 3
H, I, K I 1 2
2 (Idle time)
6 10
K, J J 6 4
K K 4 0
Workstation Task assigned Idle time
1 A, B 1
2 C, D 3
3 D, E 3
4 F, G 1
5 H, I 2
6 J, K 0
Total 10

Efficiency:

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Describe a simple sales information system for an online store, including its products, branches, and its appraisal, so that it captures the attention of an average person without a university degree or a particular career, and develop a report about it.
Note: A waiting line model solver computer package is needed to answer these questions. The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) La = L = Wa W = h…
Burger Dome sells hamburgers, cheeseburgers, french fries, soft drinks, and milk shakes, as well as a limited number of specialty items and dessert selections. Although Burger Dome would like to serve each customer immediately, at times more customers arrive than can be handled by the Burger Dome food service staff. Thus, customers wait in line to place and receive their orders. Burger Dome analyzed data on customer arrivals and concluded that the arrival rate is 40 customers per hour. Burger Dome also studied the order-filling process and found that a single employee can process an average of 56 customer orders per hour. Burger Dome is concerned that the methods currently used to serve customers are resulting in excessive waiting times and a possible loss of sales. Management wants to conduct a waiting line study to help determine the best approach to reduce waiting times and improve service. Suppose Burger Dome establishes two servers but arranges the restaurant layout so that an…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College