PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 7.S, Problem 15P

10 minutes per unit. Part 2 is simultaneously processed at work-station C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D. w here the two parts are assembled. The time at workstation D is 15 minutes.

a) What is the bottleneck of this process?

b) What is the hourly capacity of the process?

•• S7.15 A production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).

a) Which operation is the bottleneck?

b) What is the bottleneck time?

c) What is the throughput time of the overall system?

d) If the firm operates 8 hours per day. 20 days per month, what is the monthly capacity of the manufacturing process?

Chapter 7.S, Problem 15P, 10 minutes per unit. Part 2 is simultaneously processed at work-station C for 20 minutes per unit.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The bottleneck operation.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Answer to Problem 15P

The bottleneck operation is Welding.

Explanation of Solution

Given information:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 7.S, Problem 15P , additional homework tip  1

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the Number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30>10, 10, 25, 10, 28.57). Hence, the bottleneck time of the system is 30 minutes per unit.

Therefore, the bottleneck operation is Welding.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The bottleneck time of the bottleneck operation.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Answer to Problem 15P

The bottleneck time of the bottleneck operation is 30.

Explanation of Solution

Given information:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 7.S, Problem 15P , additional homework tip  2

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30 > 10, 10, 25, 10, 28.57).  The bottleneck operation is Welding.

Hence, the bottleneck time of the bottleneck operation is 30 minutes per unit.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The throughput time of the time of the overall system.

Introduction:

Throughput time:

The throughput time of a system is the time taken for a product to pass from the raw materials stage to the finished goods stage. The higher the throughput time the more efficient the system will be.

Answer to Problem 15P

The throughput time of the overall system is 140.71 minutes.

Explanation of Solution

Given information:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 7.S, Problem 15P , additional homework tip  3

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate throughput time:

Throughput time=Maximum ((Sum of process times of Sawing, Sanding, Welding, Assembly),(Sum of process times of Drilling, Welding, Assembly))

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of throughput time:

The throughput time is calculated by identifying the maximum value of the summation of process times of Sanding, Sawing, Welding, assembly and the summation of process times of Drilling, Welding, and Assembly.

Throughput time=Maximum((10+10+30+85.71),(25+30+85.71))=Maximum(135.71,140.71)=140.71

Hence, the throughput time of the overall system is 140.71 minutes.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The monthly capacity of the manufacturing process.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Monthly capacity:

The monthly capacity is the number of units the firm is able to produce in a month’s time. It will be calculated taking into consideration of the resources and constraints present in the manufacturing process.

Answer to Problem 15P

The monthly capacity of the manufacturing process is 320 units per month.

Explanation of Solution

Given information:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 7.S, Problem 15P , additional homework tip  4

Operating time = 60 minutes / 8 hour / day

Number of days = 20 / month

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Formula to calculate monthly capacity:

Monthly capacity=Operating time×Number of days per monthBottleneck time

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the Number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30 > 10, 10, 25, 10, 28.57). Hence, the bottleneck time of the system is 30 minutes per unit.

Calculation of monthly capacity:

The monthly capacity is calculated by multiplying the operating time per day with the number of days per month and dividing the resultant value with the bottleneck time of the system.

Monthly capacity=Operating time×Number of days per monthBottleneck time=8×60×2030=9,60030=320units

Hence, the monthly capacity of the manufacturing process is 320 units per month.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Below is information related to: historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B routing and standard times to produce Product B • the product structure for Product B • a MPS covering 3 periods for Products A and B. MPS in Units End Product 2 Processing Time A 50 45 25 Historical % End Product Hours/Unit wC B. 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1 1.25 D (3 required) D 50 200 0.07 100 200 0.08 F 100 300 0.04 (2 required) A. Develp a rough cut capacity plan for the three work centers based on historical factors. Please fill in the table below with your final calculations. Show your work in the space belov Historical Total Work Center Percentage 1 2 3 Hours 100 200 300 Total Required Capacity Show any work here:
Manufacturing Company uses FIFO method of accumulating costs in a two-department process. Materials are introduced at the inception of the process except for a special material which is added in department 2 at 60% completion as to overhead. Inspection is done at the end of the process in both departments. Production data for Department 2 are given below: In process, beginning, (80% labor, 70% overhead)2,000 Transferred in 14,900 In process, ending (40% labor, 20% overhead) 3,000 Normal spoilage 200 Abnormal spoilage (found at 30% completion as to laborand 15% as to overhead due to internal failure) 400 Cost data for the month:In process beginning:Transferred in 15,020 Special materials 1,900 Direct labor 4,388 Overhead 11,044 Current costs:Transferred in 137,080 Special materials 14,030 Direct labor 46,000 Overhead 113,564   The cost of units transferred to finished goods is?The cost of spoilage charged to revenue is?
J 1 ue K Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $5,000. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 75% Total Time 5.589 Unit Time .477 80% Total Time 6.315 Unit Time .583 85% Total Time 7.116 X

Chapter 7 Solutions

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB

Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY