PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7, Problem 3CS
Summary Introduction
Case summary:
RM Company is looking to change its numerically controlled machines into a flexible manufacturing system. The transition will handle about 30% of RM Company’s work. There will be additional costs for startup process. The new system is likely to reduce the inventory, floor space, production time and number of labors required.
The annual labor savings is a huge sum on the implementation of the new process. The company’s
To determine: The case of an optimistic sales manager to move on forward with the flexible manufacturing system (FMS).
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Rochester Manufacturing’s Process Decision - Process Strategy
Rochester Manufacturing Corporation (RMC) is considering moving some of its production from traditional numerically controlled machines to a flexible manufacturing system (FMS). Its computer numerical control machines have been operating in a high-variety, low-volume manner. Machine utilization, as near as it can determine, is hovering around 10%. The machine tool sales people and a consulting firm want to put the machines together in an FMS. They believe that a $3 million expenditure on machinery and the transfer machines will handle about 30% of RMC’s work. There will, of course, be transition and start up costs in addition to this.
The firm has not yet entered all its parts into a comprehensive group technology system, but believes that the 30% is a good estimate of products suitable for the FMS. This 30% should fit very nicely into a “family.” A reduction, because of higher utilization, should take place in the number…
Refer to Problem 7.1. If a contract for the secondand third years is pending, what a re the implications fo r processselection?
Robot Manufacturing Optimization
FAY Technologies is deciding whether it should begin production of a new toy robot. It has manufactured children’s toys before but nothing as advanced as its latest robot so historical data is at a minimum. The company believes that they can secure the materials for manufacture for between $65-85 per unit and labor costs would be between $15-25 per unit. Management’s expectations are that materials will cost $70 per unit and labor $25 per unit and that 800 units will be sold monthly.
Should FAY decide to manufacture the robots in-house, maintenance of the factory machine would cost $15,000 per month. However, management has found that another alternative is for the company to outsource the labor for a flat rate of $35 per unit. The company expects to sell between 750-1000 units per month initially at a price of $149.
Provide recommendations for FAE technologies that will maximize profit. Also include base, worst, and best case…
Chapter 7 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Considering the following excel sensitivity report: Variable Cells Cell $B$12 Product 1= $B$13 Product 2= $B$14 Product 3= $B$15 Product 4= Constraints Name Cell SH$6 Process 1 (hrs) Usage $HS7 Process 2 (hrs) Usage SH$8 Process 3 (hrs) Usage SH$9 Process 4 (hrs) Usage O 8 O 9 Name 13 O 14 Final Value O None of the above 0 30.64516129 Final Value 0 12.09677419 225.8064516 268.5483871 300 250 Reduced Objective Cost Coefficient -1 0 -1 0 Shadow Constraint Price R.H. Side 0 0 10 12 11 13 0.5 1.5 Allowable Increase 1 46.5 1 6.2 Allowable Increase 1E+30 1E+30 150 Which one of the following values of the second objective function coefficient (c₂) would generate a different optimal solution (remember: all of the other variables remain the same)? 600 500 300 250 281.372549 Allowable Decrease 1E+30 3.1 1E+30 1.291666667 Allowable Decrease 374.1935484 231.4516129 237.5 83.33333333arrow_forwardHow important is matching process capabilities to product requirements?arrow_forwardProcess choice is demand driven?arrow_forward
- A manufacturer plans to introduce a new shirt based on the following information. The selling price is $57.00; variable cost per unit is $18.00; fixed costs are $7800.00; and capacity per period is 500 units. b) Draw a detailed break-even chart, making sure to label the variables on the y- and x-axes, as well as all other significant points in the chart c) Showing your calculations, calculate the break-even point (in units) if fixed costs are reduced to $7020arrow_forwardOrpheum Productions in Nevada is considering three mutually exclusive alternatives for lighting enhancements to one of its recording studios. Each enhancement will increase revenues by attracting directors who prefer this lighting style. The cash flow details, in thousands of dollars, for these enhancements are shown in the chart below. MARR is 10%/year. Based on a future worth analysis, which alternative (if any) should be implemented?arrow_forwardExplain the importance of matching process capabilities with product requirements?arrow_forward
- Explain the two conditions that are required in process flexibility ?arrow_forwardMetters Cabinets, Inc., needs to choose a production method for its new office shelf, the Maxistand. To help accomplish this, the firm has gathered the following production cost data: Metters Cabinets projects an annual demand of 24,000 units for the Maxistand. The Maxistand will sell for $120 per unit.a) Which process type will maximize the annual profit from producing the Maxistand?b) What is the value of this annual profit?arrow_forwardWhy is process flexibility desirable? What two conditions are required?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.