a)
To determine: The precedence diagram for the manufacturing in the given case.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
b)
To determine: The flow time required for assembling one briefcase and desired cycle time to assemble 50 case in a 40-hour week.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
c)
To determine: The balance line and efficiency.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
d)
To determine: The line to be changed when 80 case are produced per week.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations and Supply Chain Management 9th edition
- Professional Image Briefcases is an exclusive producer ofhandcrafted, stylish cases. The company assembles eachcase with care and attention to detail. This laborious processrequires the completion of the six primary work elementslisted here.a. Construct a precedence diagram for the manufacturingof briefcases.b. Compute the flow time required for assembling onebriefcase and the cycle time necessary to assemble 50cases in a 40-hour week.c. Balance the line and compute its efficiency.d. How would you change the line to produce 80 casesper week? Work Element Precedence Time (min)A Tan leather — 30B Dye leather A 15C Shape case B 10D Mold hinges and fixtures — 5E Install hinges and fixtures C, D 10F Assemble case E 10arrow_forwardProfessional Image Briefcases is an exclusive producer ofhandcrafted, stylish cases. The company assembles eachcase with care and attention to detail. This laborious processrequires the completion of the six primary work elementslisted here a. Construct a precedence diagram for the manufacturingof briefcases.b. Compute the flow time required for assembling onebriefcase and the cycle time necessary to assemble 50cases in a 40-hour week.c. Balance the line and compute its efficiency.d. How would you change the line to produce 80 casesper week?arrow_forwardTed Short, manager of procurement at the Lake Luna Medical Center (LLMC), is starting a process to examine at the general process that is followed at his center for procurement of medical supplies at his facility. His first step is to develop a flowchart for the current process that employees at his center follow. He has asked you to draw that flowchart for him and make any obvious changes to shorten the process. Here are the key steps that are followed: The LLMC employee fills out a paper requisition and sends that to his department head for approval. The department secretary first examines the requisition to see if all needed information is present. If it is, then she sends to the department head for approval. If not, she returns to the employee for any needed corrections. The employee then returns the requisition to the department secretary for review again. Requisitions with the correct information are sent to the department head. The department head reviews the item to determine…arrow_forward
- According to this textual description, please develope each of the diagrams (3):a) Document flow chart:The document flow chart visually represents the flow of documents through Nova Terra's cash disbursement process. It starts with the invoice sent by DM to Nova Terra, which is then manually recorded by María Fuentes in the accounts payable subsidiary. The recorded invoice is sent to Mr. Martín Mendoza in the Cash Disbursement Office, who processes it and prepares a check for payment. The check and invoice are sent to Laura Rivera, who is the treasurer of Nova Terra and approves and signs them before mailing the check to the supplier. Subsequently, the canceled invoice is returned to Martín Mendoza for his registration in the cash disbursements journal and file. b) Business process diagram (BPD):The business process diagram shows the activities and sequence of Nova Terra's cash disbursement process in more detail. It includes the following steps: billing and registration, payment…arrow_forward1. Define and discuss the advantages and disadvantages the following Process Strategies: Make-to-Stock Make-to-Order Assemble-to-Orderarrow_forwardThe bill of materials shows all the parts required to make Select one: a work-in process inventory b. the MPR c.raw materials inventory d.one itemarrow_forward
- The janitorial staff at the local secondary school have reported that they were low on several cleaning products. New supplies would be required in the next couple of weeks. What kind of process will likely be in place for this situation? A) a routine purchase process B) a supplier review C) a modified rebuy routine D) an order and reorder routine E) a new-task purchasearrow_forwardPlease dont answer in image ormat,Do type. Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or…arrow_forwardCanine Kernels Company (CKC) manufactures two differenttypes of dog chew toys (A and B, sold in 1,000-count boxes)that are manufactured and assembled on three differentworkstations (W, X, and Y) using a small-batch process (seeFigure 5.12). Batch setup times are negligible. The flowchartdenotes the path each product follows through the manu-facturing process, and each product’s price, demand perweek, and processing times per unit are indicated as well.Purchased parts and raw materials consumed during pro-duction are represented by inverted triangles. CKC can makeand sell up to the limit of its demand per week; no penaltiesare incurred for not being able to meet all the demand. Eachworkstation is staffed by a worker who is dedicated to workon that workstation alone, and is paid $6 per hour. Totallabor costs per week are fixed. Variable overhead costs are$3,500/week. The plant operates one 8-hour shift per day, or40 hours/week. Which of the three workstations, W, X, or Y,has the highest…arrow_forward
- No. 10arrow_forwardThe hierarchy of components, their description, and the quantity of each needed to make one unit of a product are documented in: Select one: a. an engineering drawing. b. a list of group technology. c. a roadmap. d. a list of materials. and. a work order.arrow_forward○ E. Founded in 1970, ABC is one of the world's largest insurance companies with locations in 28 countries. Given the following description, flowchart the new policy setup process as it existed in 1970: Individual customers who wanted to set up a new policy would visit one of ABC's 70 branch offices or make contact with an agent. They would then fill out an application and sometimes attach a check. The branch office then sent the application package through company mail to the XYZ division in London. In addition, a customer might also fill out the application at home and send it directly to any number of ABC locations, which would then transfer it to the London operation. Once received, XYZ separated the various parts of the application, then scanned and digitized it. The electronic image was then retrieved from a server and delivered to an associate's desktop client computer. The associate was responsible for entering the information on the form into the appropriate database. If the…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,