a)
To determine: The number of volunteers to be called in if a care package is to be completed every 10 minutes, to determine the efficiency, and number of packages to be assemble in four-hour period.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
b)
To determine: The efficiency of the line and number of packages to be assembled in four-hour period.
Introduction:
The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
- Francis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forwardKarina Nieto works for New Products Inc., and one of hermany tasks is assigning new workers to departments. Thecompany recently hired six new employees and would likeeach one to be assigned to a different department. The em-ployees have completed a two-month training session ineach of the six departments from which they received theevaluations shown below (higher numbers are better).Determine how the new employees should be assigned todepartments so that overall performance is maximized.arrow_forward
- 7.14. The Henry Street Mission uses volunteers to assemble care packages for needy families during the holiday season. The mis- slon would like to organize the work as efficiently as possible. A list of tasks, task times, and precedence requirements follows: Task Precedence Time (Mins) A B A B. 7. D. C, D 4 a. If the mission wants to complete a care package every 10 min- utes, how many volunteers should be called in? Balance the line and calculate the efficiency. How many packages can be assem- bled in a four-hour period? b. Suppose that volunteers are plentiful. Balance the line to max- imize output. What is the efficiency of the line? How many care packages can be assembled in a four-hour period?arrow_forwardA company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Time Task Predecessor (seconds) A 50 A 36 26 22 E B, D 70 F C, E 30 What is the required cycle time in seconds in order to meet the projected demand? (Answer with two decimal places i.e. 26.00, 326.80) Answer: B C Darrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B с D E F G H I Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Time (hrs) 20 60 100 30 20 10 20 10 30 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activites E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H A B C- D- E F G H- H 0 20 40 60 80 100 120 140 160 180 200 Q ✔arrow_forward
- You are alone at home and have to prepare a bread sandwich for yourself. The following preparation activities and time taken are given in the table below: Task Description Predecessor Time (Minutes) A Purchase of bread - 20 B Take cheese and apply on bread A 5 C Get onions from freezer A 1 D Fry onions with pepper B,C 6 E Purchase sauce for bread - 15 F Toast bread B,C 4 G Assemble bread and fried onions F 2 H Arrange in plat G 1 Determine: a. While purchasing sauce, you met a friend and spoke to him for 6 minutes. Did this cause any delay in the preparation?arrow_forwardWaldorf Astoria Spa & Health Club at Waldorf Astoria Chicago offers high-quality hair-styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The process comprised of five tasks that are completed in the sequence described below. (The time required for each task is shown in parenthesis). Task 1: Welcome a guest and offer homemade herb tea (10 minutes) Task 2: Wash and condition hair (10 minutes) Task 3: Neck, shoulder, and back stress release massage (10 minutes) Task 4: Design the hairstyle and do the hair (25 minutes) Task 5: Check out the guest (5 minutes) Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 completes Task 1. S2 completes Tasks 2 and 3. S3 completes Tasks 4 and 5. Assume a wage rate of $18 per hour. What are the direct labor costs for one guest?arrow_forwardIf you can hire an additional worker in order to improve the process capacity you should assign the worker to ?arrow_forward
- Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forwardUpdike Upholstery cuts and sews fabric for customordered chairs, ottomans, and sofas. Often, the more com-plicated patterns are for the smaller pieces, where cuttingis more time consuming than sewing. Thus, cutting andsewing times vary. Today’s list of jobs, shown below, arefor an important customer who needs them shipped out(in one shipment) as soon as possible. Determine thesequence of jobs that will complete the customer’s orderas quickly as possible, and notify the customer when theorder is expected to ship.arrow_forwardThe table below shows the time for each work element in an manual assembly process, along with the predecessor(s) required for each element. The ideal cycle time is 1.4 minutes, the repositioning time is 0.1 minutes, and there is one worker at each station. Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3 0.2 Immediate predecessors - A A B B C E,F D,E G,H I 1. Using the ranked positional weights method, assign work elements to stations.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.