Question
Chapter 7, Problem 27P
Summary Introduction
To determine: The arrangement of process into cells.
Introduction: The capacity in term of business refers to the capability of the business to conduct its production process. It determines the level of productive goods produced by the businesses.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A DIY product manufacturing company wishes to create a ‘product’ focused layout for the manufacture of their new cordless drill. There order book requires them to produce 480 drills per eight hour day. The assembly operations for the drill and the associated information are given in the table below. Therefore the key tasks are to:
Management has decided to cut down 3 seconds from each operation (operation 1 - 8) to improve overall effectiveness.
(a) calculate the maximum cycle time
(b) calculate the minimum number of work stations
(c) produce the precedence diagram
(d) produce the line design which achieves the required cycle time
(e) calculate balancing loss
J.C. Howard’s medical testing company in Kansas
wishes to assign a set of jobs to a set of machines. The follow-ing table provides the production data of each machine when
performing the specific job:
MACHINEABCD1 7 9 8 102 10 9 7 63 11 5 9 64 9 11 5 8
a) Determine the assignment of jobs to machines that will maxi-mize total production.
b) What is the total production of your assignments?
A company needs to rebalance a product layout for producing sweet sour lollipop wrap. They plan to use the assembly line for an output rate of 4 units per minute each day. The following table describes the tasks involved in the production of this product:
Work
Element
Time
(seconds)
Immediate
Predecessor(s)
A
12
--
B
6
A
C
8
A
D
4
B
E
7
B, C
F
10
E
G
6
D, F
Determine how many stations are required for the line to produce the desired output.
Select one:
A. 5.0 workstations
B. 4.0 workstations
C. 3.0 workstations
D. 3.5 workstations
E. 4.5 workstations
Chapter 7 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 7.S - Prob. 1QCh. 7.S - Prob. 2QCh. 7.S - Prob. 3QCh. 7.S - Prob. 4QCh. 7.S - Prob. 5QCh. 7.S - Prob. 7QCh. 7.S - Prob. 1PCh. 7.S - Prob. 2PCh. 7.S - Prob. 3PCh. 7.S - Prob. 4P
Ch. 7.S - Prob. 5PCh. 7.S - Prob. 6PCh. 7.S - Prob. 7PCh. 7.S - Prob. 8PCh. 7.S - Prob. 12PCh. 7.S - Prob. 13PCh. 7.S - Prob. 14PCh. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Prob. 18PCh. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 1.1CPCh. 7 - Prob. 1QCh. 7 - Prob. 2QCh. 7 - Prob. 3QCh. 7 - Prob. 4QCh. 7 - Prob. 5QCh. 7 - Prob. 8QCh. 7 - Prob. 9QCh. 7 - Prob. 10QCh. 7 - Prob. 11QCh. 7 - What are the fixed and variable cost tradeoffs...Ch. 7 - What is the difference between block diagramming...Ch. 7 - Prob. 14QCh. 7 - What are the objectives of line balancing?...Ch. 7 - How are manufacturing cells formed? How does the...Ch. 7 - Prob. 17QCh. 7 - Prob. 18QCh. 7 - Prob. 19QCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Rent-With-Us Management Inc. has purchased a large...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - The TLB Yogurt Company must be able to make 600...Ch. 7 - The Speedy Pizza Palace is revamping its...Ch. 7 - Professor Garcia has assigned 15 cases in his OM...Ch. 7 - McCauleys Heating and Air in Phoenix, Arizona,...Ch. 7 - The precedence diagram and task times (in minutes)...Ch. 7 - The Costplus Corporation has set a processing...Ch. 7 - Hanover Hospital beds can transform from a bed to...Ch. 7 - Fines Furniture is known for its fine cedar...Ch. 7 - Prob. 25PCh. 7 - The Wet Wellies Corporation produces waterproof...Ch. 7 - Prob. 27PCh. 7 - Jetaway, a small manufacturer of replacement parts...Ch. 7 - Workout Plus Workout Plus is a health club that...Ch. 7 - Photo Op-Please Line Up Tech is modernizing its...Ch. 7 - Photo Op-Please Line Up Tech is modernizing its...Ch. 7 - Photo Op-Please Line Up Tech is modernizing its...
Knowledge Booster
Similar questions
- Use excel to show formulas 1. A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?arrow_forwardDistinguish between a work center, a GT cell, and an assembly line.arrow_forwardFrancis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forward
- Please answer me in typed versions, I have problems with hand-writingarrow_forwardA company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forwardesign Layout References Mailings Review View Help 、三 目三==。 v11 、 ab х, х* А Normal No Spacing Heading 1 Editing A Aa v A A の、困、 Font Paragraph Styles 1. The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining the figures in the diagram below. la. Compute the labor productivity per worker for each of the six weeks. ( on an excel file with shown formula) Week Crew Size Yards Installed 4 96 3. 72 3. 92 50 69 6. 2. 52 I> 3. 1, 2.arrow_forward
- Please do not give solution in image format thankuarrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B с D E F G H I Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Time (hrs) 20 60 100 30 20 10 20 10 30 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activites E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H A B C- D- E F G H- H 0 20 40 60 80 100 120 140 160 180 200 Q ✔arrow_forward1. Find one example of a process layout in local businesses. Draw a picture of the locations of departments. 2. Find examples of a product layout in local businesses. Draw a picture to show the workstations and the tasks performed.arrow_forward
- Line balancing As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. a. Develop your own scenario (quantitative example) of this line balancing problem. Include all relevant information. b. Draw the precedence diagram for the problem that you set up in part “a" above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forwardProfessor Garcia has assigned 15 cases in his OM Seminarclass to be completed in a 15-week semester. The students, of course, are moaning and groaning that the caseload can-not possibly be completed in the time allotted. Professor Garcia sympathetically suggests that the students work in groups and learn to organize their work efficiently. Know-ing when a situation is hopeless, the students make a list of the tasks that have to be completed in preparing a case. These tasks are listed here, along with precedence require-ments and estimated time in days. Assuming students will work five days a week on this assignment, how many stu-dents should be assigned to each group, and what is the most efficient allocation of tasks? Can 15 cases be com-pleted in a semester? Explain your answer.arrow_forwardXYZ company provides labor and space for the manufacturing and assembly operations and stocking various inventory items for production such as wire, cables, some electronic components, etc. XYZ company orders a variety of components and raw materials by contract. The company recently hired 100 part-time employees working four to six-hour shifts. Skilled employees must do several raw material conversions for packaging—there are currently three (3) such employees. The plant layout is a typical process layout - machines of similar types are located together. Each machine and employee must be scheduled over the day and the standard time period for planning is one (1) hour. Material handling is mainly done manually, although the company would like to consider conveyors or other automation to aid in automating their processes. XYZ company forecasts planned production for two (2) years on a rolling quarterly basis. Often, the customer changes the forecast, and these changes can occur as…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.