The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 7.6. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each (lay the project lasts beyond day 14.
- What is the project’s duration if only normal times are used?
- What is the minimum-cost
schedule ? - What is the critical path for the minimum-cost schedule?
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Additional Business Textbook Solutions
Principles Of Operations Management
Operations Management, Binder Ready Version: An Integrated Approach
Operations Management
Operations Management
Operations and Supply Chain Management 9th edition
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- Justify the use of earned value management (EVM) to control expenses and monitor the effectiveness of a project, and speculate as to why it is not used more often. How can one determine if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is favorable or unfavorable? What are some general criteria to follow?arrow_forwardWhy is earned value management (EVM) not utilized more frequently? Describe how it may be used to manage expenses and gauge project effectiveness. What are some broad guidelines for judging the quality of figures for cost variation, schedule variance, cost performance index, and schedule performance index?arrow_forwardYou are the manager of a project to improve a billing processat your firm. Table 7.7 contains the data you will need toconduct a cost analysis of the project. Indirect costs are $1,600per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the ear-liest completion time of the project using “normal” timesand the minimum-cost schedule you derived in part (a)?arrow_forward
- You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in 7.10. Your interest is in minimizing the cost of theproject to the community center.a. Using the normal times for each activity, what is the earliest date you can complete the project?b. Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule.arrow_forwardThe project manager of Good Public Relations gathered the data shown in Table 7.15 for a new advertising campaign.a. How long is the project likely to take?b. What is the probability that the project will take more than 38 weeks?c. Consider the path A–E–G–H–J. What is the probability that this path will exceed 38 weeks?arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Based on the outcome of the calculations(image attached), draw the five (5) S-Curves as well as the total Project's CVAR.arrow_forwardUse Critical Path Method to estimate in how many weeks the project below will be submitted and find the critical path (Choose 2 answers weeks and critical path) Activity A: Prepare Initial design B: Identify now potential clients C: Develop prospectus for tenants A D: Prepare final design E: Obtain planning permission F: Obtain finance from bank G: Select controctor H: Construction I: Finalize tenant contracts J: Tenants move In dependent time 3. 8. 3. G, F В, с, Е I, H 17 13 34 Weeks 29 Weeks Critical path : A-G-E-F-H-J Critical path : A-D-E-F-H-J O Critical path : A-C-E-F-H-J 35 weeks Click Save and Submit to save and submit. Click Save All Answers to save all answers.arrow_forwardWhat makes cost estimating such a crucial part of project planning? Discuss how it relates to the project timeline and the Work Breakdown Structure.arrow_forward
- You are the project manager of the softwaration project in the table below. You would like to find the minimum-cost schedule for your project. There is a $500-per-week penalty for each week the prop delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. 9 Normal Activity Immediate Predecessor(s) Time (weeks) 1 A B C D E F G H 1 a. What would be your target completion week? The target completion week is week A A, B B D E. F G C.F (Enter your response as an integer.) b. How much would you save in total project costs with your schedule? Total Savings S (Enter your response as an integer) 79832N 10 12 8 Normal Cost (S) 3,000 3,000 10,000 3,000 4,000 2,000 3,000 5,000 2,000 Crash Time (weeks) 1 58829136 Crash Cost ($) 3,000 6,000 12,000 9,000 5,000 5,000 9,000 7,000 8,000arrow_forward. 1. Project Scope & Constraints The new payroll system project has been approved. The new system will reduce clerical time and errors, improve morale in the payroll department, and avoid possible fines and penalties for noncompliance. The system must be installed by January 1st to meet new federal reporting rules, all expenses must be approved in advance, and the system should have a modular design if possible. The new system is expected to be announced in a year-end report if it is ready by mid-December. 1. Why is it important to define the project scope? How would you describe the scope of the payroll project in this case? 2. Based upon the project scope, identify the constraints, and determine its characteristics: present versus future, internal versus external, and mandatory versus desirable. 3. What questions would you ask to determine the feasibility of this project? 4. Given the project time constraints, could you shorten the typical steps in the preliminary investigation…arrow_forwardTime frame is the project timeline from start (building the factory) to finish (start of production). Remember you can only start production after Government Building inspection and approval. so, what is the time frame of yogurt manufacturer?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.