Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
12th Edition
ISBN: 9780134855424
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 22P
In Solved Problem 2, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Determine the amount of time in weeks that gives a probability of 97.5% until the seventh event in the network.
Act.
1-2
2-3
2-5
2-4
3-4
3-7
5-6
6-7
4-7
0
8
4
7
7
4
7
10
10
4
M
10
5
8
9
6
8
14
14
5
24
12
21
11
8
15
24
24
Question 4: The
following, and then find the following
12
The possibility of completing the project with a period of less than TE by 4 weeks
what is it
What is the probability of completing the project with a period exceeding TE by 2 weeks?
Note: end of the question answer also given.
I want A&D only.
Onc aagain remember I want only A&D part
A. What is the probability that path A-B-D-F-G will take from 100 to 120 days to complete? Answer = 40.2%
B. What is the probability that path A-C-E-G will take less than 85 days to complete? Answer = 32.64%
C. If the contract for the above project is 120 days, what is the chance of meeting the schedule? Answer = 86.3%
D. What duration (number of full days) should be used to be at least 90% confident of finishing on time? Answer = 125 days - Probability of 93%
Please do not give solution in image formate thanku.
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 4 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $400, E is $415 and all other activities is : $100 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1000 per week, E is $1200 per week and for all other activities is $200 per activity per week. You have a maximum crashing budget of $2505. The maximum possible reduction in the project duration will be:
a. 2 weeks
b. 3 weeks
c. 4 weeks
d. 5 weeks
e. 6 weeks
Chapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Case: Downtown Kingston Transport Centre/ Project management The downtown Kingston and Saint Andrew Centre were built for $400 million JAD in 2010 (Reid, 2012). The Centre is owned by the Jamaican Urban Development Corporation (UDC) and was formerly managed and operated by the Kingston and Saint Andrew Municipal Corporation (KSAMC) (Reid, 2012). Built as a multipurpose bus and taxi part the centre’s main function was to alleviate traffic congestion in downtown Kingston, especially in the parade area. The centre has become dilapidated and unmanageable due to a lack of usage by transport operators, commuters, implementation, enforcement, and a failure to have an effective transportation policy (Teachdem. n.d.). “The transportation Centre, which was designed to restore order to the public transportation system in downtown Kingston has failed miserably as most commuters, bus and taxi operators have ignored the facility which detractors say was built in the middle of nowhere” (Radio…arrow_forwardIn making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity Tarrow_forwardGive typing answer with explanation and conclusionarrow_forward
- Duration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth development (iv) Find the project schedule if only 4 men are availablearrow_forwardExample: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2arrow_forwardOn January 1, Jack signed a contract with AT &T for his mobile phone services. The contract includes three lines with a $120 fixed payment each month plus $15 per gigabit if the data usage is more than 9 gigabits. On March 1, Jack wants to add one more phone line to the existed contract, and the payment becomes $150 fixed payment each month plus $15 per gigabit if the data usage is more than 12 gigabits. Is this change a contract modification? Please use one sentence to explain why?arrow_forward
- illustrate unscaled activity bar type of early start and late startarrow_forwardThe shortest-route technique wouldbest be used to: plan the routes for avacation driving tour.plan the route for a school bus.determine the path for a truck making frequent runsfrom a factory to a warehouse.All of the aboveNone of the abovearrow_forwardDefine the phrase " route " in your own words.arrow_forward
- A commercial company has a main branch located in Beirut with around 35 employees. The company is looking to expand its activities by opening 3 new branches in Lebanon. To facilitate information and data sharing, the company decided to implement a network in each branch, then to connect all the branches into a single network. Also, the new network will be based on giving employees the facility to use their laptops and smartphones in most of their operations. On the other hand, the company has a major problem with organizing its data. The human resource, finance, sales, and customer service departments have all developed separately their own systems and data files, which created a lot of redundancy and poor security. Managers can't have access to timely, accurate, or relevant information for analysis because the data have been poorly organized and maintained in separated files. The main concern for the company, regarding this problem, is to discover new and hidden patterns of customers'…arrow_forwardLorraine has received a lump sum of R500 000.00 from her retirement fund. She intends to use these funds to start a student accommodation business. In order to start this business, Lorraine would need approximately R1 million, funds are needed for building the students accommodation apartments and to register with various regulatory bodies. She has to source additional funding in order to realise this dream. In the business plan, Lorraine has outlined the following:• Accommodation will be offered ONLY to students in Cape Town, Johannesburg, Mpumalanga and Polokwane.• ONLY females will be approved to reside in these houses, between the age of 18 - 35.• Marketing of the business will be done on community Radio stations only at the fourmentioned cities.• It is going to be a family business, Friends and relatives are in support of the idea but are not able to support the business financially. 4.1 Discuss ANY TWO labour legislations that applies to and will impact Lorraine’s business.…arrow_forwardLorraine has received a lump sum of R500 000.00 from her retirement fund. She intends to use these funds to start a student accommodation business. In order to start this business, Lorraine would need approximately R1 million, funds are needed for building the students accommodation apartments and to register with various regulatory bodies. She has to source additional funding in order to realise this dream. In the business plan, Lorraine has outlined the following:• Accommodation will be offered ONLY to students in Cape Town, Johannesburg, Mpumalanga and Polokwane. • ONLY females will be approved to reside in these houses, between the age of 18 - 35.• Marketing of the business will be done on community Radio stations only at the fourmentioned cities.• It is going to be a family business, Friends and relatives are in support of the idea but are not able to support the business financially. Discuss ANY TWO labour legislations that applies to and will impact Lorraine’s business.…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY