OPERATION MANAGEMENT
2nd Edition
ISBN: 9781260242423
Author: CACHON
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7, Problem 11PA
a)
Summary Introduction
To determine: The capacity of the machine (Housings per hour).
b)
Summary Introduction
To determine: The utilization of the machine.
c)
Summary Introduction
To determine: The average inventory of housings.
d)
Summary Introduction
To determine: The number of D7000 housing to be produced in each batch.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Hammond Inc. has analyzed the setup time on its computer-controlled lathe. The setup requires changing the type of fixture that holds a part. The average setup time has been 135 minutes, consisting of the following steps:
Step
Time (in minutes)
Turn off machine and remove fixture from lathe
13
Go to tool room with fixture
15
Record replacement of fixture to tool room
18
Return to lathe
20
Clean lathe
17
Return to tool room
20
Record withdrawal of new fixture from tool room
12
Return to lathe
15
Install new fixture and turn on machine
8
Total setup time
138
Why should management be concerned about improving setup time?
What do you recommend to Hammond Inc. for improving setup time?
How much time would be required for a setup, using your suggestion in (b)?
Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers as follows:
Activity
Expected Cost
Activity Driver
Activity Capacity
Engineering
$1,000,000
Engineering hours
5,000 hours
Setups
900,000
Setups
200 setups
Machining
2,000,000
Machine hours
25,000 machine hours
Inspection
800,000
Inspection hours
2,500 inspection hours
Quasi-Tech produces two models: Model C and Model D. The following table…
Consider the two stage process depicted below:
Stage 1
Stage 2
The first stage of the process requires 6 minutes of work for a single employee to
complete. There are 8 employees working at this process stage - each for a total of 5
hours per day. This stage includes an inspection where 14% of WIP is rejected and
exits the system after completing Stage 1.
The remaining WIP continues to Stage 2 of the process. At this stage, 7 employees
work - each for a total of 4 hours per day. WIP is processed at Stage 2 in 10 minutes
by a single employee.
What is the daily process capacity? Round your answer to the nearest first decimal
place.
Your Answer:
Answer
Chapter 7 Solutions
OPERATION MANAGEMENT
Ch. 7 - Prob. 1CQCh. 7 - Prob. 2CQCh. 7 - Prob. 3CQCh. 7 - Prob. 4CQCh. 7 - Prob. 5CQCh. 7 - Prob. 6CQCh. 7 - Prob. 7CQCh. 7 - Prob. 8CQCh. 7 - Prob. 9CQCh. 7 - Prob. 10CQ
Ch. 7 - Prob. 11CQCh. 7 - Prob. 12CQCh. 7 - Prob. 13CQCh. 7 - Prob. 14CQCh. 7 - Prob. 1PACh. 7 - Prob. 2PACh. 7 - Prob. 3PACh. 7 - Prob. 4PACh. 7 - Prob. 5PACh. 7 - Sarahs Organic Soap Company makes four kinds of...Ch. 7 - Prob. 7PACh. 7 - Prob. 8PACh. 7 - Bruno Fruscalzo decided to set up a small...Ch. 7 - Prob. 10PACh. 7 - Prob. 11PACh. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A bicycle component manufacturer produces hubs for bike wheels. Two processes are possible for manufacturing, and the parameters of each process are as follows: Process 1 Process 2 35 parts/ hour 4 hours/ day 15 parts/hour 7 hours/day 20% 9% Production rate Daily production time Percent of parts rejeted based on visual inspection Assume that the daily demand for hubs allows all defect-free hubs to be sold. Additionally, tested or rejected hubs cannot be sold. Find the process that maximizes profit per day if each part is made from Php 200 worth of material and can be sold for Php 1,500. Both processes are fully automated, and variable overhead cost is charged at the rate of Php 2,000 per hour.arrow_forwardSmooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec…arrow_forwardSmooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high--end electric razors. These razors are produced using a machine--paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec…arrow_forward
- JCL Inc. is a major chip manufacturing firm that sells its products to computer manufacturers like Dell, Gateway, and others. In simplified terms, chip making at JCL Inc. involves three basic operations: depositing, patterning, and etching. • Depositing: Using chemical vapor deposition (CVD) technology, an insulating material is deposited on the wafer surface, forming a thin layer of solid material on the chip. Patterning: Photolithography projects a microscopic circuit pattern on the wafer surface, which has a light-sensitive chemical like the emulsion on photographic film. It is repeated many times as each layer of the chip is built. • Etching: Etching removes selected material from the chip surface to create the device structures. The table below lists the required processing times and setup times at each of the steps. There is unlimited space for buffer inventory between these steps. Assume that the unit of production is a wafer, from which individual chips are cut at a later…arrow_forwardA chemical process involves adding various agents to a vat and then waiting for theagents to react to make a final compound. The vat holds up to 1000 gallons. Chemicalagents are added to the vat at a rate of 4.5 gallons per minute. Once the agents have beenadded to the vat, the reaction takes 85 minutes no matter the actual number of gallonsin the batch. After the batch is complete, the vat must be cleaned. Cleaning always takes15 minutes. What is the setup time of this process?a. 15 minutes c. 100 minutesb. 85 minutes d. 222.22 minutesarrow_forwardA bicycle component manufacturer produces hubs for bike wheels. Two processes are possible for manufacturing, and the parameters of each process are as follows: Process 1 Process 2 Production Rate 35 parts per hour 15 parts per hour Daily production time 4 hours per day 7 hours per day Percent of Parts Rejected 20% 9% Assume that the daily demand for hubs allows all defect-free items to be sold. Additionally, defective hubs cannot be sold and their material cannot be recovered anymore. Find the process that minimizes the total cost per piece if each part is made from $4 worth of material. Both processes are fully automated, and the variable overhead cost is charges at $40 per hour.arrow_forward
- A small, privately owned Asian company is producing a private-label soft drink called Yoggo. A bottling line puts the soft drinks into plastic bottles and then packages the bottles into boxes holding 10 bottles each. The bottling line is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes 3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottle into a box. When a box has been filled with 10 bottles, a worker tending the packaging machine removes the filled box and replaces it with an empty box. Assume that the time for the worker to remove a filled box and replace it with an empty box is negligible and hence does not affect the capacity of the line. Problem data are summarized in the following table. Process Step Number of Machines Seconds per Bottle Bottling 1 1 Apply a lid 1 3 Labeling 1 3 Packaging 1 4…arrow_forwardA small, privately owned Asian company is producing a private-label soft drink called Yoggo. A bottling line puts the soft drinks into plastic bottles and then packages the bottles into boxes holding 10 bottles each. The bottling line is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes 3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottle into a box. When a box has been filled with 10 bottles, a worker tending the packaging machine removes the filled box and replaces it with an empty box. Assume that the time for the worker to remove a filled box and replace it with an empty box is negligible and hence does not affect the capacity of the line. Problem data are summarized in the following table. Assuming unlimited demand, what would be the flow rate? Assuming unlimited demand, what would be the utilization at…arrow_forwardThe following are applications of recycle in a process except? a. Diluting a process stream b. Increasing efficiency of the process c. Improving the process stream's flow d. Getting rid of impuritiesarrow_forward
- This four-step process loop is termed a machine cycle. Most individuals prioritise which machine cycle factors? Should I worry about replacing worn machine cycle parts? Can increasing the number of modules simplify switching between them?arrow_forwardThe casting method adopted for ornaments and toys of non-ferrous alloys, is_ a•permanent mould casting b•slush casting c•die casting d•centrifugal castingarrow_forwardA process control system consists of ________ elements.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.