Concept explainers
A producer of inkjet printer is planning to add a new line of printers, and you have been asked to balance the process, given the following task time and precedence relationship. Assume that cycle time is to be the minimum possible.
a. Do each of the following:
(1) Draw the precedence diagram.
(2) Assign tasks to stations in order of most following tasks. Tiebreaker, greatest positional weight.
(3) Determine the percentage of idle time.
(4) Compute the late of output in printers per day that could be expected for that line assuming a 420-minute working day.
b. Answer these questions:
(1) What it the shortest cycle tone that will permit use of only two workstations? Is this cycle time feasible? Identify the tasks you would assign to each station.
(2) Determine the percentage of idle time that would results if two stations were used.
(3) What is the daily output under this arrangement?
(4) Determine the output rate that would be associated with the maximum cycle time.
a) 1
To draw: The precedence diagram.
Answer to Problem 4P
Answer: Precedence diagram:
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
Precedence diagram:
The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.
2)
To assign: Tasks to workstations in the order of most following tasks.
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
The positional weight of a task is the sum of the task times of the task itself and all of the following tasks.
Task | Following tasks | Number of following tasks | Calculation of positional weight | Positional weight |
a | b, d, g, h | 4 | 0.2 + 0.4 + 1.3 + 0.3 + 1.2 | 3.4 |
b | d, g, h | 3 | 0.4 + 1.3 + 0.3 + 1.2 | 3.2 |
c | d, g, h | 3 | 0.3 + 1.3 + 0.3 + 1.2 | 3.1 |
d | g, h | 2 | 1.3 + 0.3 + 1.2 | 2.8 |
e | f, g, h | 3 | 0.1 + 0.8 + 0.3 + 1.2 | 2.4 |
f | g, h | 2 | 0.8 + 0.3 + 1.2 | 2.3 |
g | h | 1 | 0.3 + 1.2 | 1.5 |
h | Nil | 0 | 1.2 | 1.2 |
Calculation of cycle time:
The cycle is said to be the minimum time possible.
Therefore, the cycle time is 1.3 minutes / unit.
Assigning tasks to workstations:
Workstation number | Eligible task | Assigned task | Task time | Unassigned cycle time | Reason |
1.3 | |||||
1 | a, c, e | a | 0.2 | 1.1 | Task 'a' has more number of following tasks |
b, c , e | b | 0.4 | 0.7 | Task 'b' has greatest positional weight | |
c, e | c | 0.3 | 0.4 | Task 'c' has greatest positional weight | |
d, e | e | 0.1 | 0.3 | Task 'e' has greatest positional weight | |
d, f | None | 0.3 (Idle time) | The task time is greater than the unassigned cycle time. | ||
1.3 | |||||
2 | d, f | d | 1.3 | 0 | Task 'd' has greatest positional weight |
1.3 | |||||
3 | f | f | 0.8 | 0.5 | Task 'f' is the only eligible task available |
g | g | 0.3 | 0.2 | Task 'g' is the only eligible task available | |
h | None | 0.2 (Idle time) | The task time is greater than the unassigned cycle time. | ||
1.3 | |||||
4 | h | h | 1.2 | 0.1 | Task 'h' is the only task remaining |
0.1 (Idle time) | All tasks completed |
Overview of tasks assignment:
Workstation | Assigned tasks | Total cycle time used | Idle time |
1 | a, b, c, e | 1 | 0.3 |
2 | d | 1.3 | 0 |
3 | f, g | 1.1 | 0.2 |
4 | h | 1.2 | 0.1 |
3)
To determine: The percentage of idle time.
Answer to Problem 4P
Explanation of Solution
Formula to calculate percentage of idle time:
Calculation of percentage of idle time:
The percentage of idle time is 11.54%.
4)
To determine: The rate of output printers per day.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output printers per day:
Calculation of output printers per day:
The rate of output printers per day is 323.08 printers / day.
b) 1
To determine: The shortest cycle time that will permit the use of only 2 workstations and to check if it is feasible.
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
Calculation of shortest cycle time:
The shortest cycle time is calculated by summing all the task times and dividing the resultant value by 2 workstations.
The obtained shortest cycle time is feasible based on the task times. Every task time is either equal to or less than 2.3 minutes. The feasibility is checked by assigning the tasks to the 2 workstations.
Assigning tasks to workstations:
Workstation number | Eligible task | Assigned task | Task time | Unassigned cycle time | Reason |
2.3 | |||||
1 | a, c, e | a | 0.2 | 2.1 | Task 'a' has more number of following tasks |
b, c , e | b | 0.4 | 1.7 | Task 'b' has greatest positional weight | |
c, e | c | 0.3 | 1.4 | Task 'c' has greatest positional weight | |
d, e | e | 0.1 | 1.3 | Task 'e' has more number of following tasks | |
d, f | d | 1.3 | 0 | Task 'd' has greatest positional weight | |
2.3 | |||||
2 | f | f | 0.8 | 1.5 | Task 'f' is the only eligible task available |
g | g | 0.3 | 1.2 | Task 'g' is the only eligible task available | |
h | h | 1.2 | 1.2 | Task 'h' is the only task available |
Overview of tasks assignment:
Workstation | Assigned tasks | Total cycle time used | Idle time |
1 | a, b, c, e, d | 2.3 | 0 |
2 | f, g, h | 2.3 | 0 |
The shortest cycle time of 2.3 minutes is feasible.
2)
To determine: The percentage of idle time.
Answer to Problem 4P
Explanation of Solution
Formula to calculate percentage of idle time:
Calculation of percentage of idle time:
The percentage of idle time is 0.00%.
3)
To determine: The daily output under this arrangement.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output under this arrangement:
Calculation of output under this arrangement:
The rate of output under this arrangement is 182.61 units / day.
4)
To determine: The output rate associated with cycle time.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output under this arrangement:
Calculation of output under this arrangement:
The maximum cycle time is the sum of all task times.
The sum of all task times is:
The rate of output under this arrangement is 91.30 units / day.
Want to see more full solutions like this?
Chapter 6 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Emotional intelligence is defined as the ability to understand and manage your emotions, as well as recognize and influence the emotions of those around you. True Falsearrow_forwardAt the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?arrow_forwardAt the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?arrow_forward
- Community Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.arrow_forwardDavison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000 Davison’s objective is to determine the cost-minimizing production planarrow_forwardAnecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…arrow_forward
- 3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].arrow_forwardexamine the production concept and operations management, what are the key steps required to achieve success? Be specific in your response.arrow_forwardProduce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.arrow_forward
- 問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the abovearrow_forwardElaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…arrow_forwardAssess the role of EDI in ensuring supply chain security and data integrity. How does EDI contribute to reducing vulnerabilities in supply chain operations, and what best practices should organizations adopt to maintain a secure and reliable EDI system? (10) 1.3. Examine how the adoption of modern EDI systems influences the strategic decision-making process in supply chain management. How does EDI provide supply chain managers with actionable insights, and what are the implications of these insights for long-term supply chain planning? (10) 1.4. Evaluate the potential challenges and risks associated with the modernization of EDI systems in supply chain management. How can organizations effectively manage these challenges to ensure successful EDI implementation and ongoing optimization? (10)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing