Cooper River Glass Works (RGW) produces four different models of desk lamps as shown in Figure 5.15. The operations manager knows that total monthly demand exceeds the capacity available for production. Thus, she is interested in determining the product mix which will maximize profits. Each model’s price, routing, processing times, and material cost are provided in Figure 5.15. Demand next month is estimated to be 200 units of model Alpha, 250 units of model Bravo, 150 units of model Charlie, and 225 units of model Delta. CRGW operates only one 8-hour shift per day and is
- Which station is the bottleneck?
- Using the traditional method, which bases decisions solely on a product’s contribution to profits and overhead, what is the optimal product mix and what is the overall profitability?
- Using the bottleneck-based method, what is the optimal product mix and what is the overall profitability?
Want to see the full answer?
Check out a sample textbook solutionChapter 5 Solutions
OPERATIONS MANAGEMENT CUSTOM ACCESS
Additional Business Textbook Solutions
Principles Of Operations Management
Business in Action (8th Edition)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Operations Management
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardSoutheast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: demand forecast. Quarter Forecast 1 1,900 2 1,200 3 1,600 4 800 Costs/Other Data Previous quarter's output=1,200 cases Beginning inventory=0 cases Stockout cost of backorders=$160 per case Inventory holding cost=$40 per case at end of quarter Hiring employees=$35 per case Terminating employees=$80 per case Subcontracting cost=$65 per case Unit cost on regular time=$30 per case Overtime cost=$20 extra per case Capacity on regular time=1,900 cases per quarter John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that…arrow_forward
- sniparrow_forwardCapacity planning requires a demand forecast for an extended period of time into the future. What concerns would you have regarding an extended forecast as a capacity planner?arrow_forwardNozone, Inc., a manufacturer of Freon recovery units (for automotive air conditioner maintenance), experiences a strongly seasonal demand pattern, driven by the summer air conditioning season. This year Nozone has put together a six-month production plan, where the monthly demands D, for recovery units are given in the table below. Each recovery unit is manufactured from one chassis assembly plus a variety of other parts. The chassis assemblies are produced in the machining center. Since there is a single chassis assembly per recovery unit, the demands in the table below also represent demands for chassis assemblies. The unit cost, fixed setup cost and monthly holding cost for chassis assemblies are also given in this table. The fixed setup cost is the firm's estimate of the cost to changeover the machining center to produce chassis assemblies, including labor and materials cost and the cost of disruption of other product lines. t D₁ C₁ A₁ h₂ 1 1,000 50 2,000 1 2 1,200 50 2,000 1 3 500…arrow_forward
- Handerson Corporation makes a product with the following standard costs: Direct materials Direct labor Variable overhead Standard Quantity or Hours 8.5 kilos 0.4 hours 0.4 hours Standard Price or The company reported the following results concerning this product in August. Actual output Raw materials used in production Purchases of raw materials Rate $ 6.00 per kilo $ 20.00 per hour $ 6.00 per hour 3,200 units 29,030 kilos 31,600 kilos Actual direct labor-hours 1,160 hours Actual cost of raw materials purchases $ 195,920 $ 22,736 Actual variable overhead cost $ 7,540 Actual direct labor cost The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The materials price variance for August is: Multiple Choice $5,440 Farrow_forwardCharles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and excellent location, demand has increased by 5555% in the last year. On far too many occasions, customers have not been able to purchase the bread of their choice. Because of the size of the store, no new ovens can be added. At a staff meeting, one employee suggested ways to load the ovens differently so that more loaves of bread can be baked at one time. This new process will require that the ovens be loaded by hand, requiring additional manpower. This is the only production change that will be made in order to meet the increased demand. The bakery currently makes 1,800 loaves per month. Employees are paid $8 per hour. In addition to the labor cost, Charles also has a constant utility cost per month of $800 and a per loaf ingredient cost of $0.35 Current multifactor productivity for 640 work hours per month =0.27loaves/dollar (round your response to three decimal places).arrow_forwardThe current data for five trees that will be analyzed in the exercise are shown in the following table Expected Yearly Demand Quantity For Sale In-Field Quantity 440 74 Trees Christmas Palm Washingtonia Gumbo Limbo Yellow Poinciana Weeping Podo 81 165 159 49 185 Trees Christmas Palm Washingtonia Std Dev 31 155 35 32 68 Gumbo Limbo Yellow Poinciana The "expected yearly demand" is an estimate of the demand over the next year for the tree. The "std dev" is the standard deviation, a measure of the error, that corresponds to the forecast. For-sale and in-field quantities are given, and finally the total number of trees planted on the farm. The demand forecast and quantities are updated on an ongoing basis as trees are sold and planted on the farm. 374 70 42 290 Your first task is to evaluate the inventory "position" of each tree. The farm does not keep any backorder information, so the only data you have is "for-sale" and "in-field" quantities. Think about "for-sale" as on-hand trees, and…arrow_forward
- Please solve all part and do not give solution in image format thankuarrow_forwardABC Inn has 2 departments: rooms and F&B. the rooms department has a CMR of 0.6 and the F&B department has a CMR of 0.4 the rooms department take in 70% of total revenue and the F&B department takes in 30% of total revenue. If the combined total monthly fixed costs for the entire hotel are equal to $100,00. What is the break-even level of sales?arrow_forwardSmart Manufacturing Company (SMC) manufactures a variety of products other than the drum components for printers. Their high selling mobile juicer cup JG-142 has the following expected demand sales figures (in units) over the coming six months: Month 2 3 4 5 Expected Demand (units) 17680 23040 21120 16640 21760 The following planning parameters apply: Current number of workers Output rate per worker Number of regular time hours Number of working days Regular time labour cost Overtime labour cost Planning Parameters 26 4 units/hour 8 hours/day 20 days/month Maximum overtime hours allowed Hiring cost (including training) Layoff cost Inventory carrying cost Backorder cost Opening inventory Planned ending inventory (end of month 6) Material Cost Subcontracting Cost with material Maximum subcontracting allowed $14.00 /hour $21.00 /hour 6 18300 20% of regular worker-hours/month $950 /worker $1780 /worker $1.75 /unit/month Total 118540 $7.00/unit backordered 400 units 900 units $15 /unit $35…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing