A
Interpretation: Construct a regression formula for anticipating the overhead expense using linear regression, based on the project duration.
Concept Introduction: The method followed in predicting the future value depending on the previous forecast including the portion of errors in the previous forecast is called Simple Exponential Smoothing forecast.
A

Answer to Problem 32P
The required regression equation for predicting overhead expense is Y=5399.22+29.7217x.
Explanation of Solution
Given Information:
Project Code | Project Duration (days) (X) | Overhead Expense (Y) | XY | X2 |
A11 | 72 | $5,900 | $424,800 | 5184 |
A12 | 158 | $10,303 | $1,627,874 | 24964 |
A14 | 124 | $9,054 | $1,122,696 | 15376 |
A18 | 96 | $6,644 | $637,824 | 9216 |
A22 | 152 | $10,718 | $1,629,136 | 23104 |
B2 | 174 | $10,332 | $1,797,768 | 30276 |
B33 | 124 | $8,804 | $1,091,696 | 15376 |
B23 | 105 | $8,884 | $932,820 | 11025 |
B10 | 63 | $7,916 | $498,708 | 3969 |
B14 | 58 | $8,267 | $479,486 | 3364 |
B7 | 83 | $8,503 | $705,749 | 6889 |
109.9090909 | 8665.9091 | 10948557 | 148743 | |
12080.00826 | ||||
b | 29.7217 | |||
a | 5399.22 |
Thus, the regression equation with the derived values will be,
B
Interpretation: Find out the coefficient of determination for the given projects.
Concept Introduction: The proportion of variance occurring in the dependent variable forecasted based on the independent variable is called the Coefficient of Determination.
B

Answer to Problem 32P
The coefficient of determination, r2 is 0.6264.
Explanation of Solution
Given Information:
Project Code | Project Duration (days) (X) | Overhead Expense (Y) |
A11 | 72 | $5,900 |
A12 | 158 | $10,303 |
A14 | 124 | $9,054 |
A18 | 96 | $6,644 |
A22 | 152 | $10,718 |
B2 | 174 | $10,332 |
B33 | 124 | $8,804 |
B23 | 105 | $8,884 |
B10 | 63 | $7,916 |
B14 | 58 | $8,267 |
B7 | 83 | $8,503 |
r2 | 0.6264 |
Thus, coefficient of determination is 0.6264.
C
Interpretation: Determine what the forecast of the overhead expense suggests for the project of 110 days long.
Concept Introduction: Using regression, we will be able to define relationship between any two variables, denoting the cause and effect. The method can also be used to forecast the future depending on the past performances.
C

Answer to Problem 32P
The forecasted expense of overhead for 110 days long project is $8,668.61.
Explanation of Solution
Given Information:
The project is 110 days long.
Thus, the forecasted overhead expense is $8,668.61.
D
Interpretation: With the information, build a better way in using linear regression for
Concept Introduction: Using regression, we will be able to define relationship between any two variables, denoting the cause and effect. The method can also be used to forecast the future depending on the past performances.
D

Answer to Problem 32P
The forecasted overhead expense is $8946.64.
Explanation of Solution
Given Information:
The given value of ‘a’ is 1542.02 and the given value of ‘b’ is 57.99.
Project Code | Project Duration (days) (X) | Overhead Expense (Y) | XY | X2 |
A11 | 72 | $5,900 | $424,800 | 5184 |
A12 | 158 | $10,303 | $1,627,874 | 24964 |
A14 | 124 | $9,054 | $1,122,696 | 15376 |
A18 | 96 | $6,644 | $637,824 | 9216 |
A22 | 152 | $10,718 | $1,629,136 | 23104 |
120.4 | $8,524 | 5442330 | 77844 | |
14496.2 | ||||
b | 57.99 | |||
a | 1542.02 | |||
r2 | 0.9655 |
Thus, with the above derived values of ‘a’ and ‘b’, the linear regression model would be:
Now, substituting the values in the previous linear regression equation:
For 110 days, the forecasted overhead expense is $7920.92.
Now, substituting the values in the later linear regression equation:
Thus, the forecasted overhead expense is $8946.64.
Want to see more full solutions like this?
Chapter 4 Solutions
Practical Operations Management
- With regard to reputation in negotiation, negotiators who use adversarial, stubborn, and ethically questionable behavior often have the effect of _____. A. improving their business relationships B. decreasing their effectiveness as a negotiator C. improving their business relationships D. decreasing their group statusarrow_forwardWhen it comes to assertiveness, there is only a modest link between negotiators' self-views and how the counterparty sees them. Many negotiators come away from a negotiation thinking they came on too strong with the counterparty. The _____ refers to the fact that negotiators believe they are coming on too strong with the counterparty, but they actually are not. A. Collective trap illusion B. Attribution error C. Aggressive anchoring bias D. Line-crossing illusionarrow_forwardAs you think about the issue of using chatbots in contract negotiations, consider whether other facets and concepts of negotiations that we have discussed and whether they would be adequately addressed.arrow_forward
- While I am not a fan of AI as of yet, I do understand the endless possibilities. Based on the research, it is clear that AI has great potential for negotiation (Yang, 2025). Herold et al. (2025) suggested that AI can flag potential risks and liabilities, allowing negotiators to address them and mitigate potential problems proactively. AI can draft new contract templates by examining industry standards and past contracts, and AI technology can help lawyers spot errors and inconsistencies in contract drafts. In relation to risk management, AI can flag possible risks and liabilities, allowing negotiators to proactively address them and lessen potential problems, which can speed up the negotiation process, making the negotiation efficient because AI can industrialize tasks like document review, redlining, and finding potential issues, significantly reducing negotiation time. Lastly, AI can analyze vast amounts of data and identify errors, inconsistencies, and irregularities in…arrow_forwardWhat is a main thought on using AI in contract negotiations?arrow_forwardWhat are some people thoughts on using AI in contract negotiations?arrow_forward
- 3. Develop a high-level or summary: a. Risk Management Plan Focus on specific, actionable steps for each risk and mitigation strategy.Provide detailed timelines for procurement, stakeholder engagement, and risk monitoring.Avoid over-simplifying and add more technical details in areas like quality assurance and financial control measures. Add a risk prioritization method and mention how risks will be monitored and reviewed throughout the project lifecycle. Overall, it is well organized andc overs key risks.arrow_forward3. Develop a high-level or summary: Human Resource Management Plan Provide more concrete timelines and actionable steps for human resource management.Include more detailed risk management strategies and link them more explicitly to the overall project plan.Expand on how training and development will be evaluated and tracked.Also, the overall length is good, but some sections could be condensed by eliminating repetition (e.g., you discuss stakeholder communication and engagement in two sections without adding new information).Try not to repeat the same risk management ideas (e.g., resource sharing and stakeholder concerns) in multiple sections without adding value.arrow_forwardBased on the U.S. Department of Transporation's publication on the number of inrternatioal passengers that come through New York airport (JFK) in 2012, how would I estimate the passenger volume for the coming year?arrow_forward
- What are the role of trends and seasonality based on the Department of Transportation publication of the number of international passengers that come through New York (JFK) in 2012?arrow_forward(All info i was given, i simplified it) Gas sales across type: 80% of gas sales tend to be regular. 15% midgrade, 5% tend to be premium. $0.10 increase in price per gallon tends to decrease gallons sold by 1 to 3%. Jan-0.87, Feb-0.95, Mar-1.00, Apr-1.05, May-1.08, Jun1.15, Jul-1.13, Aug-1.07, Sep-1.02, Oct-0.94, Nov-0.89, Dec-0.85. You want the MAPE to be below 20%, if ypu can get it to or below 10% they'll throw in extra $10k bonus. They wont get bonus if it is above 11% or 20%. It cannot be over 20%. Forecast for January 2025 andarrow_forwardWhat variables can I expect to influence the number of international travelers to New York (JFK) airport based on the U.S. Department of Transportation?arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub