Which of the following is not a typical reason that project teams would use a predictive approach versus an agile approach to managing a project?
- a. The project has unclear up-front requirements.
- b. The project team is inexperienced and dispersed.
- c. Large risks are involved.
- d. The completion date is fairly rigid.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
This high-level initial estimate of the requirements is maintained by the Project Owner throughout the entire project. It is dynamic because management can constantly change it to reflect the needs of an evolving product, and its environment.
a.
A Timebox
b.
A Product Backlog
c.
An Iteration
d.
A Sprint Backlog
Please explain
Detailed answer please...
Chapter 3 Solutions
Information Technology Project Management
Ch. 3 - Briefly describe what happens in each of the five...Ch. 3 - Approximately how much time do good project...Ch. 3 - Why do organizations need to tailor project...Ch. 3 - Prob. 4DQCh. 3 - What are some of the typical challenges project...Ch. 3 - Prob. 6DQCh. 3 - Prob. 1QQCh. 3 - ____________ processes include coordinating people...Ch. 3 - Prob. 3QQCh. 3 - Prob. 4QQ
Ch. 3 - Prob. 5QQCh. 3 - A work breakdown structure, project schedule, and...Ch. 3 - Prob. 7QQCh. 3 - ____________ involves measuring progress toward...Ch. 3 - Which of the following is not a typical reason...Ch. 3 - Many people use ____________ to have a standard...Ch. 3 - Research a project management method, such as...Ch. 3 -
Read the “ResNet Case Study,” which is available...Ch. 3 - Review the sample documents provided for JWD...Ch. 3 - Prob. 5ECh. 3 - Prob. 6ECh. 3 - Prob. 7ECh. 3 - Prob. 8ECh. 3 - Prob. 9E
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Write a short paper based on the chapters opening case. Answer the following questions: a. What do you think the real problem was in this case? b. Does the case present a realistic scenario? Why or why not? c. Was Nick Carson a good project manager? Why or why not? d. What should top management have done to help Nick? e. What could Nick have done to be a better project manager?arrow_forwardRead at least two of the first five references cited in this chapter with statistics about the importance of IT and project management. Write a summary of the reports, key conclusions, and your opinion of them.arrow_forwardA(n). is a method to estimate and schedule the tasks of a project. Select one: a.adaptive systems diagram b.essential use case model c.project charter d.work breakdown structurearrow_forward
- In their paper, Andersen et al (2006) stated that the basic idea behind the traditional, rational and normative project approach is that projects are relatively simple, predictable and linear with clearlydefined boundaries which all makes it easy to plan in detail and follow that plan without much changes. On the other hand, Agile project management approach is intended for projects characterized by high level of uncertainty, unclear project goals or incomplete and unpredictable requests, for which it could be assumed that will be significantly changed during the course of the project .With reference to the statement and scenario above, Motivate why a mixed methodology (Agileand Traditional Methodology) is most ideal for this project. In your answer, ensure that you address what was established in the meeting.arrow_forwardSelect the most appropriate agile methodology for approaching the project for each of the five story problems. Justify your selection. In the “Methodology or Combination of Methodologies” column of the worksheet, list the methodology or combination (blend) of methodologies you selected. In the “Justification of Methodology or Combination of Methodologies” column, write a reflection (50-100 words) for each story problem that addresses the following: What is the specific problem in the scenario? Why did you choose the methodology or combination of methodologies? Because there is not necessarily one right or wrong answer, it is important to provide a clear justification for your choice. Cite evidence from the textbook or other sources in your justification. Explain how you think each selected methodology differs most significantly from a traditional project management approach STORY PROBLEM METHODOLOGY OR COMBINATION OF METHODOLOGIES JUSTIFICATION FOR THE METHODOLOGY OR…arrow_forwardYou are the project manager of a hybrid project incorporating the planning of a predictive project and the workflow of iterations of Agile. How will you likely manage changes to the project scope in this approach? a. Schedule and cost change control b. Process change control c. Product backlog prioritization d. No changes are allowed to the project scope once it has been baselinedarrow_forward
- 10 Which of the following is a classic organizational structure? A Functional B Projectized C Composite D Matrix 11 Defining a new project or a new phase of an existing project relates to A Initiating process. B. Planning process C Scope management process D. Control process 12 If you are developing a Project Management Plan, how should you determine the level of detail to be included in the plan? A Always only provide a summary or high level plan B Include only the details your manager specifically requested C Always provide the maximum level of detail possible D. Provide the level of detail based on the project complexity and application area 13 Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied? A. Crashing B. Reserve Analysis C. Forecasting D. Last Tracking 14.…arrow_forwardExplain the project execution Spiral Model and V Model.arrow_forwardDetailed and correct answer will be Upvoted. Thank youarrow_forward
- Explain the notion of project planning. Which considerations should be taken into account while estimating schedules?arrow_forwardDescribe project management. What is its aim, and why is it important? What are the primary aspects of a project which can be adjusted to correct a project that is in danger of missing one or more of its targets?arrow_forward17 The entical path method (CPM) calculates the theoretical early start and fish dates, and late start and finish dates. The difference between the late and early start of a task is called A Free float B. Feeding buffer C Danger zone D Total float 18 Which of the following is NOT a characteristic of a project? A Ongoing nature B Uniqueness C Clear objectives D Integration of interrelated tasks and resources 19. Which of the following is NOT managed by the project manager? A. Time, cost and scope B. The project team C. The project sponsor D Expectations of the stakeholders 20 When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented? -A Human resource management plan B RACI chart C Resource calendar D Resource Breakdown Structure (RBS) 21. Which of these is not a component of the scope baseline that is contained in the project management plan? A Work…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Database Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781285196145Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos CoronelPublisher:Cengage LearningManagement Of Information SecurityComputer ScienceISBN:9781337405713Author:WHITMAN, Michael.Publisher:Cengage Learning,
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
9.1.2 Software Development Approaches; Author: EIToppo;https://www.youtube.com/watch?v=Z9znuSQ7Sz8;License: Standard YouTube License, CC-BY