Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
11th Edition
ISBN: 9780135639221
Author: Jay Heizer, Barry Render
Publisher: PEARSON+
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 2P
James Lawson has decided to run for a seat as Congressman from the House of Representatives, District 34, in Florida. He views his 8-month campaign for office as a major project and wishes to create a work breakdown structure (WBS) to help control the detailed
Help Lawson by providing details where the blank lines appear. Are there any other major (level-2) activities to create? If so, add an ID no. 1.6 and insert them.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
James Lawson has decided to run for a seat as Congressman from the House of Representatives, District 34, in Florida. He views his 8-month campaign for office as a majorproject and wishes to create a work breakdown structure (WBS) to help control the detailed scheduling. So far, he has developed the following pieces of the WBS: Help Lawson by providing details where the blank lines appear. Are there any other major (Jevel-2) activities to create? If so, add an ID no. 1.6 and insert them.
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task?
Discuss the use of the Program Evaluation and ReviewTechnique (PERT) to schedule the tasks of a large complicatedproject. How widely is PERT used?
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What are the benefits of using flowcharts as part of the requirement model in project management.arrow_forwardCreate a graphical format Work Breakdown Structure (WBS) based on the project information below. The name in brackets is the name of a resource/team member responsible for the activity. The activities indicating “completed” are phases and/or work packages. PROJECT INFORMATION Project Title: Construction of a house (Bheka) Level 1: Design (Jim) • “Permits” are completed (Thulani) • “Drawings” are completed (James) Level 2: Construction (Nokubonga) • “Building” is completed (Neetu) • “Interior” is completed under “Building” (Suzan) • “Exterior” is completed under “Building” (Steve) • “Inspection” is completed (Nadia).arrow_forwardDevelop a Work Breakdown Structure (WBS) for the following case study by using Top-down Approach. You are hired as a project manager to develop the Campus Management System (CMS) of a famous educational complex. CMS is designed to promote automated university administration and provides a medium for teachers, staff and administration to work in harmony. CMS has a complete role based access where in various resources are made available depending upon the role assigned. The Student module includes students to add, modify and view features designed to ease registration. The Academic Management module deals with academic history of the students and it allows determining student's expertise level through his obtained grades. The Fee Management module keeps track of fees paid and dues and allows printing of fee voucher. The Course Management module allows maintaining different courses, the respective instructors and session details. The Alerts and Notification module is email based alerts…arrow_forward
- Work Breakdown Structure (WBS) for A millionares mansion with four to five (4-5) high level tasks and an average of four to five (4-5) sub-tasks for each high level task. Under these 4 phases Planning - Interior Design - Landscape/Outdoor Entertainment - Project Closeoutarrow_forwardDescribe how a Project Manager controls the SOW or the schedule for his/her project with a resource requirements planarrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H IMG_A2D52FAF8F3D-1.jpeg Activity This answer has not been graded yet. A B с (c) Develop the activity schedule for the project. D Survey building site Develop initial design Obtain board approval E F G Description H Select architect Establish budget Finalize design Obtain financing 0 Hire contractor L L | (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Immediate Predecessor Earliest Start (b) Identify the critical path. (Enter your answers as a comma-separated list.) 4 A, B с Latest Start с D, E E F, G Time (weeks) 5 5 9 Earliest Finish 13 4 7 15 11 6 9 Latest Finish 4 Slack (d) Does it appear…arrow_forward
- Dayagsky Construction Firm, Inc. will soon begin to work on a building for US tea that was initially started by another firm that has gone out of business. The construction firm’s schedule of activities and related expected completion time for US tea project are presented in the following time table: Activity Code Activity Description Estimated Time (in weeks) A - B Obtain on-site work permits 2 B – E Repair damages done by vandals 8 B – C Inspect construction materials left on site 1 C – E Order and receive construction materials 2 C – D Apply for waiver to…arrow_forwardWork Breakdown Structure (WBS) for A millionares mansion with four to five (4-5) high level tasks and an average of four to five (4-5) sub-tasks for each high level task.arrow_forwardKindly help out with work breakdown structurearrow_forward
- Stan's No Touch Car Wash is looking to implement a new ERP system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Tasks Predecessors mu_t sigma_t Start 0 0 A start 25 12 B A 17 14.11 C A 45 46.35 D A 32 15.36 E A 37 10.36 F C,D 10 11.8 G B,F 41 15.17 H E,G 44 44.44 end H 0 0 Colin has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: Metric Description E[ES_i] Expected early start time for task i E[EF_i] Expected early finish time for task i E[LS_i] Expected late start time for task i E[LF_i] Expected late finish time for task i Pr(S_i =< t) Probability the start time for task I =< t Pr(F_i =< t) Probability the finish time for task I…arrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Description Survey Soils report C Traffic design D Lot layout E Approve design Illumination G Drainage H Landscape I Signage J Bid proposal ID A B The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 13 22 21 a 9 74 20 20 22 17 15 12 days. day(s).arrow_forwarda. Work Breakdown Structure (WBS): Develop a detailed work breakdown structure thatlists all the tasks required to launch the product or service. Organise the tasks into logicalphases and sub-phases.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY