Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
11th Edition
ISBN: 9780135639221
Author: Jay Heizer, Barry Render
Publisher: PEARSON+
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 3, Problem 23P

a)

Summary Introduction

To determine:The probability of completing the project in 17 months.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

a)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 17 months is 0.0228.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 17 months:

The standard deviationis σ=2 , given the variance is 4. Therefore the z value is:

z=17212=2

Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the normal distribution tables z value -2 corresponds to 0.0228

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  1

Hence, the probability that the project completion time is 17 months is 0.0228.

b)

Summary Introduction

To determine:The probability of completing the project in 20 months.

b)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 20 months is 0.3085.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 20 months:

Calculate the standard deviation σ=2 , and compute the z value first:

z=21202=0.5

Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  2

The probability of project completion in 20 months is 0.3085.

Hence, the probability that the project completion time is 20 months is 0.3085.

c)

Summary Introduction

To determine:The probability of completing the project in 23 months.

c)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 23 months is 0.8413.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 23 months:

Calculate the standard deviation σ=2 , and compute the z value first

z=23212=1

Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  3

The probability of project completion in 23 months is 0.8413.

Hence, the probability that the project completion time is 23 months is 0.8413.

d)

Summary Introduction

To determine:The probability of completing the project in 25 months.

d)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 25 months is 0.9772.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 25 months:

Calculate the standard deviation σ=2 , and compute the z value,

z=25212=2

Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  4

The probability of project completion in 25 months is 0.9772.

Hence, the probability that the project completion time is 25 months is 0.9772.

e)

Summary Introduction

To compute: The due date that yields a 95% chance of completion.

e)

Expert Solution
Check Mark

Answer to Problem 23P

The due date that yields a 95% chance of completionis 24.2 months.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of due date that yields a 95% chance of completion:

The z value from the normal distribution tables as shown below,

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  5

From the above tables, observe that the z value is 1.65.

Compute the due date that yields a 95% chance of completion.

=21months+(1.6×2months)=24.2months .

The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.

Hence, the due date that yields a 95% chance of completion is 24.2 months.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Note: A waiting line model solver computer package is needed to answer these questions. The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) La = L = Wa W = h…
Burger Dome sells hamburgers, cheeseburgers, french fries, soft drinks, and milk shakes, as well as a limited number of specialty items and dessert selections. Although Burger Dome would like to serve each customer immediately, at times more customers arrive than can be handled by the Burger Dome food service staff. Thus, customers wait in line to place and receive their orders. Burger Dome analyzed data on customer arrivals and concluded that the arrival rate is 40 customers per hour. Burger Dome also studied the order-filling process and found that a single employee can process an average of 56 customer orders per hour. Burger Dome is concerned that the methods currently used to serve customers are resulting in excessive waiting times and a possible loss of sales. Management wants to conduct a waiting line study to help determine the best approach to reduce waiting times and improve service. Suppose Burger Dome establishes two servers but arranges the restaurant layout so that an…
Agan Interior Design provides home and office decorating assistance to its customers. In normal operation, an average of 2.6 customers arrive each hour. One design consultant is available to answer customer questions and make product recommendations. The consultant averages 10 minutes with each customer. (a) Compute the operating characteristics of the customer waiting line, assuming Poisson arrivals and exponential service times. (Round your answers to four decimal places. Report time in hours.) λ= μ = = L = Wa W = P. W h (b) Service goals dictate that an arriving customer should not wait for service more than an average of 5 minutes. Is this goal being met? (Round your answer to one decimal place.) W₁ (in minutes) = min, which is ---Select--- than the desired wait time, so the goal ---Select--- met. What action do you recommend? (Select all that apply.) Hire another consultant. Increase the hours of operation. Decrease the mean service rate. Increase the mean service rate. There is…

Chapter 3 Solutions

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY