![Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)](https://www.bartleby.com/isbn_cover_images/9780135639221/9780135639221_largeCoverImage.gif)
Concept explainers
a)
To determine:The probability of completing the project in 17 months.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
a)
![Check Mark](/static/check-mark.png)
Answer to Problem 23P
The probability that the project completion time is 17 months is 0.0228.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 17 months:
The standard deviationis
Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the
Hence, the probability that the project completion time is 17 months is 0.0228.
b)
To determine:The probability of completing the project in 20 months.
b)
![Check Mark](/static/check-mark.png)
Answer to Problem 23P
The probability that the project completion time is 20 months is 0.3085.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 20 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.
Use the normal distribution tables to calculate the probability
The probability of project completion in 20 months is 0.3085.
Hence, the probability that the project completion time is 20 months is 0.3085.
c)
To determine:The probability of completing the project in 23 months.
c)
![Check Mark](/static/check-mark.png)
Answer to Problem 23P
The probability that the project completion time is 23 months is 0.8413.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 23 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.
Use the normal distribution tables to calculate the probability
The probability of project completion in 23 months is 0.8413.
Hence, the probability that the project completion time is 23 months is 0.8413.
d)
To determine:The probability of completing the project in 25 months.
d)
![Check Mark](/static/check-mark.png)
Answer to Problem 23P
The probability that the project completion time is 25 months is 0.9772.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 25 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.
Use the normal distribution tables to calculate the probability
The probability of project completion in 25 months is 0.9772.
Hence, the probability that the project completion time is 25 months is 0.9772.
e)
To compute: The due date that yields a 95% chance of completion.
e)
![Check Mark](/static/check-mark.png)
Answer to Problem 23P
The due date that yields a 95% chance of completionis 24.2 months.
Explanation of Solution
Given information:
Calculation of due date that yields a 95% chance of completion:
The z value from the normal distribution tables as shown below,
From the above tables, observe that the z value is 1.65.
Compute the due date that yields a 95% chance of completion.
The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.
Hence, the due date that yields a 95% chance of completion is 24.2 months.
Want to see more full solutions like this?
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Ness Engineering is a private limited company mainly engaged in the continuous production and assembly of domestic products. The annual turnover is $900,000,000. The largest area of expenditure is raw materials and components where the annual spend is approximately $450,000,000. The Managing Director, Bill, considers that profit margins are too small and has asked you to suggest how profitability might be increased. Bill suggests that this might be done by appointing additional sales staff and by an advertising campaign, which would, hopefully, increase turnover and thereby reduce overhead cost per item. You find that purchasing is little more than a post-office function. Specifications are received from the design or user departments and sent either to supplies designated by the directors or to the supplier providing the cheapest quotation. The company does, in fact, deal with many suppliers and issues many orders for low-cost items. All purchasing is done by manual means. None of the…arrow_forwardThe oasis outpost of Abu Ilan, in the heart of the Negev desert, has a population of 20 Bedouin tribesmen and 20 Farima tribesmen. El Kamin, a nearby oasis, has a population of 32 Bedouins and 8 Farima. A lost Israeli soldier, accidentally separated from his army unit, is wandering through the desert and arrives at the edge of one of the oases. The soldier has no idea which oasis he has found, but the first person he spots at a distance is a Bedouin. 1. What is the probability that he wandered into Abu Ilan? 2. What is the probability that he is in El Kamin?arrow_forward2-22 The lost Israeli soldier mentioned in Problem 2-21 decides to rest for a few minutes before entering the desert oasis he has just found. Closing his eyes, he dozes off for 15 minutes, wakes, and walks toward the center of the oasis. The first person he spots this time he again recognizes as a Bedouin. What is the posterior probability that he is in El Kamin?*Note* 2-21 The oasis outpost of Abu Ilan, in the heart of the Negev desert, has a population of 20 Bedouin tribesmen and 20 Farima tribesmen. El Kamin, a nearby oasis, has a population of 32 Bedouins and 8 Farima. A lost Israeli soldier, accidentally separated from his army unit, is wandering through the desert and arrives at the edge of one of the oases. The soldier has no idea which oasis he has found, but the first person he spots at a distance is a Bedouin. What is the probability that he has wandered into Abu Ilan? What is the probability that he is in El Kamin?arrow_forward
- Hello, please make an excel of this. Show all the cells thanks. some replied with a paper answer thank you I just cant understand the way the did it. Can someone show me all screenshots o fthis problem solved and in excel? i need to solver too for the constraints. I seen multiple times across other platforms that one of the chairs optimal solutions is 0 but they both have to be higher than 1 The Heinrich Company manufactures two types of plastic hangerracks (Foldaways and Straightaways) especially suited for mountingnear clothes dryers. Because permanent press clothing must be hungon hangers immediately after removal from the dryer, these items havebeen especially popular. However, there is some concern that thePreppie movement (popularized by its own handbook) will extinguishpolyester clothing; Heinrich is terribly interested in doing the best withthe resources it has while its products are still in demand. The firsttype of hanger rack, the Foldaway, requires 10 ounces of…arrow_forwardReview the Profit Ratio by Product chart again. What information is uncovered when the data is less aggregated than the data in Profit Ratio by Category chart?arrow_forwardWhat is the correlation between Measure A and Measure B in this example?arrow_forward
- 1) View the video ON Unveils ‘Lightspray’ Technology (4.55 mins, Ctrl+Click in the link), and The Secret of Lightspray (8.27 mins, Ctrl+Click in the link), answer the following questions: https://www.youtube.com/watch?v=wjmeaC-wlZs a) What is new about the design of ON’s shoes? b) How will ON’s new manufacturing technique affect location planning for footwear firms? c) How does ON focus on it sustainability strategy? Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions. 2) Unimed Hospital currently processes patient admissions through three admitting clerks who are set up to work in series, with respective reliabilities of 0.96, 0.95, and 0.90 (see figure below). a) Find the reliability of the current admission process. Due to rising patient complaints, the hospital administrator, Chimeg Ganbaatar, has decided to improve the reliability of the admission process by providing backup clerks for two of the…arrow_forward+ < Question 21 of 39 What is the correct common name for the compound shown here? 2-methoxyprop ane | 3-1-2- n-tert- iso sec- eth prop meth methoxy propoxy ethoxy yl acid ether ester ane Reset ☑ Submitarrow_forward(25 Marks) Discuss how you would "reset the store estate" to remain competitive and relevant in the market?arrow_forward
- Hello, please make an excel of this. Show all the cells thanks The Heinrich Company manufactures two types of plastic hangerracks (Foldaways and Straightaways) especially suited for mountingnear clothes dryers. Because permanent press clothing must be hungon hangers immediately after removal from the dryer, these items havebeen especially popular. However, there is some concern that thePreppie movement (popularized by its own handbook) will extinguishpolyester clothing; Heinrich is terribly interested in doing the best withthe resources it has while its products are still in demand. The firsttype of hanger rack, the Foldaway, requires 10 ounces of plasticmaterial and 0.3 hours of labor. Plastic costs Heinrich 10 cents anounce; labor costs Heinrich $20 per hour. The second type of hangerrack, the Straightaway, requires 15 ounces of plastic and 0.175 hoursof labor. The prices of these resources are the same as those for theFoldaway. Under current market conditions, Heinrich can sell…arrow_forwardFORMATIVE ASSESSMENT 1 Read the article below and answer ALL the questions Pick n Pay reveals strategy to restore its business 27 May 2024 [100 MARKS] Following a disappointing full year performance for FY24, Pick n Pay CEO Sean Summers has unveiled the new board- approved six-point strategy to restore the Group's core Pick n Pay supermarket business to profitability. PHASED APPROACH IMPLEMENTATION Leverage strength of partnerships Leadership and people 2 Reset the store estate 3 Improve offer to drive sales 4 Optimise operating model Leverage strength of partnerships Recapitalisation Pick n Pay Prod FY26 FY27 Before Tax break-even FY25 Halve Group H2 FY24 H1 FY25 H2 FY25 H1 FY26 H2 FY26 HI FY27 H2 FY27 KEY IMPACT AND/OR TARGETED OUTCOMES Appointing the right people, in the optimal roles, to Directly and indirectly impact revenue growth drivers and 1 drive sales and realise margin improvement 5 enhances gross and operating margins 2 Expected notable associated savings/loss avoidance…arrow_forwardWith an enormous amount of data stored in databases and data warehouses, it is increasinglyimportant to develop powerful tools for analysis of such data and mining interestingknowledge from it. Data mining is a process of inferring knowledge from such huge data. Themain problem related to the retrieval of information from the World Wide Web is theenormous number of unstructured documents and resources, i.e., the difficulty of locating andtracking appropriate sources. Your company is considering investing in a Human Resource Information System (HRIS).Briefly explain the strategies for justifying HRIS investments.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)