Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
11th Edition
ISBN: 9780135639221
Author: Jay Heizer, Barry Render
Publisher: PEARSON+
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 3, Problem 23P

a)

Summary Introduction

To determine:The probability of completing the project in 17 months.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

a)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 17 months is 0.0228.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 17 months:

The standard deviationis σ=2 , given the variance is 4. Therefore the z value is:

z=17212=2

Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the normal distribution tables z value -2 corresponds to 0.0228

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  1

Hence, the probability that the project completion time is 17 months is 0.0228.

b)

Summary Introduction

To determine:The probability of completing the project in 20 months.

b)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 20 months is 0.3085.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 20 months:

Calculate the standard deviation σ=2 , and compute the z value first:

z=21202=0.5

Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  2

The probability of project completion in 20 months is 0.3085.

Hence, the probability that the project completion time is 20 months is 0.3085.

c)

Summary Introduction

To determine:The probability of completing the project in 23 months.

c)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 23 months is 0.8413.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 23 months:

Calculate the standard deviation σ=2 , and compute the z value first

z=23212=1

Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  3

The probability of project completion in 23 months is 0.8413.

Hence, the probability that the project completion time is 23 months is 0.8413.

d)

Summary Introduction

To determine:The probability of completing the project in 25 months.

d)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 25 months is 0.9772.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 25 months:

Calculate the standard deviation σ=2 , and compute the z value,

z=25212=2

Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.

Use the normal distribution tables to calculate the probability

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  4

The probability of project completion in 25 months is 0.9772.

Hence, the probability that the project completion time is 25 months is 0.9772.

e)

Summary Introduction

To compute: The due date that yields a 95% chance of completion.

e)

Expert Solution
Check Mark

Answer to Problem 23P

The due date that yields a 95% chance of completionis 24.2 months.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of due date that yields a 95% chance of completion:

The z value from the normal distribution tables as shown below,

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 3, Problem 23P , additional homework tip  5

From the above tables, observe that the z value is 1.65.

Compute the due date that yields a 95% chance of completion.

=21months+(1.6×2months)=24.2months .

The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.

Hence, the due date that yields a 95% chance of completion is 24.2 months.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.

Chapter 3 Solutions

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY