Textbook Question
Chapter 3, Problem 10P
The activities described by the following table are given for the Howard Corporation in Kansas:
a) Draw the appropriate AON PERT diagram for J.C. Howard’s management team.
b) Find the critical path.
c) What is the project completion time?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table:
a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team.
b) Find the critical path.
c) What is the project completion time?
• • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede:
ACTIVITY
DURATION (WEEKS)
PRECEDES
A (start)
1
B, C
B
1
E
C
4
F
E
2
F
F (end)
2
—
ACTIVITY
IMMEDIATE PREDECESSOR(S)
TIME (DAYS)
A
—
2
B
—
5
C
—
1
D
B…
Mary is planning her wedding and develops the following preliminary information.
Construct an early start date Gantt chart.
The following table contains information related to the major activities of a research project. Use theinformation to do the following:a. Draw a precedence diagram using AOA.b. Find the critical path.c. Determine the expected length of the project.ActivityImmediatePredecessorExpectedTime (days)a — 5c a 8d c 2b a 7e — 3f e 6i b, d 10m f, i 8g — 1h g 2k h 17end k, m
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate 1 2345 6 7 8 9 10 A B с D E F G H I J Questions: Predecessor( Optimistic s) A A B B C D E,F,G H Estimates of Activity Duration (Weeks) Most Likely Pessimisti (Tm) c (Tp) 4 ? I (To) 2 1 1 ? 3 2 ? 3 3 2 3 2 ? 5 ? 3 2 4 ? 1 4 6 5 ? 4 6 5 3 Averag e (Te) ? 2 2.2 a. Calculate ALL the missing (?) data points b. Draw the PERT network from the given data. c. Determine ALL the paths, the critical path and its total duration in days 5 4 3 2.2 ? 4 ?arrow_forwardThe following table contains information related to the major activities of a research project. Use the as for d dif- 17.13 SO information to do the following: ty of ents 1. Draw a precedence diagram using AOA. b. Find the critical path. c. Determine the expected length of the project. low ats 6 y of Immediate Expected Time (days) Activity Predecessor na C a 8 and C ect 7 a jes e hi- f e 10 i b, d ts. 8 f, i nd he 1 g h ay to 17 k rs end k, marrow_forwardDraw a fully analyzed AON network diagram in Word and determine the project duration. Include all activity times (ES, LS, EF, LF) in the network diagram. Also, prepare an activities boundary timetable for the project don't forget to include the chartarrow_forward
- SOLVED PROBLEMS The following table contains information related to the major activities of a research project. Use the information to do the following: Problem 1 a. Draw a precedence diagram using AOA. b. Find the critical path. c. Determine the expected length of the project. Immediate Expected Time (days) Activity Predecessor a 8 d. 2 a 7 e e 6 b, d 10 f, i 8 1 g h g k 17 end k, marrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10arrow_forwardThe activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.b) Find the critical path.c) What is the project completion time?arrow_forward
- production planning and control. please help pleasearrow_forwardThe activities described by the following table aregiven for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard’smanagement team.b) Find the critical path.c) What is the project completion time?arrow_forwardSubject: Construction Quality Management In planning projects, it is essential that planners bring out critical project characteristics so that the project manager may direct the work toward completion. Discuss the criteria for project managers that encompasses four areas which must be considered during planning and the plan must include the provisions to support these actions.arrow_forward
- Assuming that you are a project manager for a consulting firm that is planning a feasibility study for a new city centre scheme. The activities for the final phase of the study project have been identified. The logical relationships for the identified activities is as shown in the dependency table below. Table 3.2: Activities for the Final Phase of a Feasibility Study Activity Immediate /predecessor (s) Duration (weeks) No. of Staff Needed A 3 B 5 3 C 4 B D A 7 2 E B.C 8 2 F C 6 5 G EF B 3 H F 10 B D.G 6 5 Table 3.2: Dependency Table Based on the information provided in the table: i. Draw and analyze the network diagram; and ii. Indicate the type of dependency relationships.arrow_forward17. Objectives are both targets and A) Barriers B) Measuring sticks C) Threats D) Priorities E) Flow charts 18. The -------- asserts that a minority of causes, inputs, or effort usually is responsible for a majority of the results, outputs, or rewards. A) MBO B) Principle of diminishing returns C) Project life cycle D) PERT network E) 80/20 principle 19. . is the second step in the MB0 process. A) Reviewing plans B) Performance appraisal C) Task analysis D) Developing action plans E) Setting objectives 20. As defined, decision making involves A) Eliminating uncertainty B) Leadership C) Information technology D) Choosing E) Overcoming fears 18. When the situation in which a problem occurs is changed so that the problem no longer exists, the problem is A) Dissolved Doc. No.: EXM/F/03 Page No.: 4/5 Issue No.: 1 Last Update: 15/04/15 Revision No.: 1.1 Date: 12/04/06 Author: EC Approved: Provost B) Created C) Optimized D) Resolved E) Satisfied 19. Which of the following is not one of the…arrow_forwardA national quality consultation firm has identified the following set of activities that must occur to carry out an audit for one of their major clients. As the project manager of this audit, answer the following questions related to the project plan. Q1. Draw the Network Diagram of the project plan for the consultation firm. Q2. 1) What is the expected project completion time:a. 54 daysb. 34 daysc. 61 daysd. 59 days2) What is the Slack period for task C:a. 12 daysb. 3 daysc. 4 daysd. 11 days3) What is the task with the longest slack time:a. Task Hb. Task Fc. Task Bd. Task J4) What is the slack period for task G:a. 6 daysb. 5 daysc. 8 daysd. 0 days5) What is the early start for task C:a. Day 12b. Day 25c. Day 19d. Day 16arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY