Concept explainers
The estimated times and immediate predecessors for the activities in a project at George Kyparis’s retinal scanning company are given in the following table. Assume that the activity times are independent.
a) Calculate the expected time and variance for each activity.
b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?
c) What is the variance of the critical path? What is the variance of the other path in the network?
d) If the time to complete path A–C is
e) If the time to complete path B–D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?
f) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.
a)
To determine: The expected time and variance.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
Answer to Problem 20P
The expected times and varianceare shown in Table 1.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Formula:
Calculate the expected time t and the variances for each activity by using the equations
where ‘a’ is the optimistic time, ‘m’ is the most likely time and ‘b’ is the most pessimistic time.
Calculation of expected time and variance:
The calculations are shown below.
Activity | Immediate predecessor | Time in weeks | t | Variance | ||
a | m | b | ||||
A | 9 | 10 | 11 | 10 | 0.11 | |
B | 4 | 10 | 16 | 10 | 4 | |
C | A | 9 | 10 | 11 | 10 | 0.11 |
D | B | 5 | 8 | 11 | 8 | 1 |
Table 1
Excel worksheet:
Hence, the expected times and variance are shown in Table 1.
b)
To determine: The expected completion of critical path and other path (non-ciritical paths).
Answer to Problem 20P
The critical path is AàC and its expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Calculation of expected completion of critical path and other path (non-ciritical paths):
AON diagram is constructed which is shown below.
The critical path is AàC and expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.
Hence, the critical path is AàC and its expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.
c)
To determine: The variance of critical path and other path (non-ciritical paths).
Answer to Problem 20P
The variance of the critical path AàC is 0.222 weeks and other path BàD is5 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Calculation of variance of critical path and other path:
The variance of the critical path AàC is the sum of the variances of activities A and C.
The variance of the critical path is the sum of 0.1111 and 0.1111 (refer table 1) which is 0.2222 weeks.
The variance of the other path BàD is the sum of the variances of activities B and D.
The variance of the other path is the sum of 4 and 1 (refer table 1) which is 5 weeksThe variance of the other path BàD is 5 weeks.
Hence, the variance of the critical path AàC is 0.222 weeks and other path BàD is 5 weeks.
d)
To determine: The probability of finishing the project in 22 weeks, when A-C is normally distributed.
Answer to Problem 20P
Probability of finishing the project in 22 weeks is almost 1.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Probability of finishing the project in 22 weeks, when A-C is normally distributed:
The expected completion time of critical path AàC is 20 weeks with a variance of 0.22 weeks.
The standard deviation:
The standard deviation is calculated by taking square root of the variance which is 0.22 which yields 0.469.
Z value is calculated by dividing the difference of 22 and 20 with 0.469 which yields 4.264.
Reading from normal distribution tables given the mean is 20 weeks, the variance
Hence, probability of finishing the project in 22 weeks is almost 1.
e)
To determine: The probability of finishing the project in 22 weeks, when B-D is normally distributed.
Answer to Problem 20P
Probability of finishing the project in 22 weeks is 0.963.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Probability of finishing the project in 22 weeks, when B-D is normally distributed:
The expected completion time of path BàD is 18 weeks with a variance of 5 weeks.
The standard deviation:
The standard deviation is calculated by taking square root of the variance which is 5 which yields 2.236.
Z value is calculated by dividing the difference of 22 and 18 with 2.236 which yields 1.79.
Reading from normal distribution tables given the mean is 18 weeks, the variance
Hence, the probability of finishing the project in 22 weeks is 0.963.
f)
To explain: The reason for the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time in weeks | ||
a | m | b | ||
A | 9 | 10 | 11 | |
B | 4 | 10 | 16 | |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Explanation for the reason for the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less:
The critical path AàC has a very small variance of only 0.22 weeks compared to the variance along path BàD which is 5 weeks. That is why, despite having lower expected time of completion of 18 weeks, the probability that the path BàD would be completed in 22 weeks is0.963.and is lower than the probability
The project is completed only when all the activities are completed.
Despite the probability of the critical path AàC, being completed in 22 weeks being almost 1, the probability that the project is completed in 22 weeks is0.963.
Want to see more full solutions like this?
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: O Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E F A B C D Dave's earliest start (ES) and earliest finish (EF) are: 5 8 00 2 2 Activity HOT G ES Н EF 5 5 5 10 7 B B C, E D.Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B с D 7 8 80 31 3 A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A EFI G H ES EF 7 4 5 11 6 B B C, E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 2 A Activity A F G H ES | FF 5 6 9 7 B B C. E D, Farrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 6 3 2 A A Activity A ES EFGH EF 7 3 6 11 6 B B C, E D, Farrow_forwardConsider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and type your work and answers or write them neatly please* Thank youarrow_forwardConsider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and either type your work and answers or write them neatly showing each step, please* NO EXCEL Thank you!arrow_forward
- Suppose that the project team has arrived at the following time estimates for activity B (Select site and survey) of the St. John’s Hospital project: a = 7 weeks, m = 8 weeks, and b = 15 weeks a. Calculate the expected time and variance for activity B. b. Calculate the expected time and variance for the other activities in the project.arrow_forwardConsider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forwardA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.