Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Refer to the information for Speedy Pete’s above. Speedy Pete’s controller wants to calculate the fixed and variable costs associated with its cutting-edge delivery service. Required: Using the high-low method, calculate the fixed cost of deliveries, calculate the variable rate per delivery, and construct the cost formula for total delivery cost. Use the following information for Brief Exercises 3-26 through 3-29: Speedy Pete’s is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows:
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Refer to the information for Speedy Pete’s above. Speedy Pete’s controller wants to calculate the fixed and variable costs associated with its cutting-edge delivery service. Required: Using the high-low method, calculate the fixed cost of deliveries, calculate the variable rate per delivery, and construct the cost formula for total delivery cost. Use the following information for Brief Exercises 3-26 through 3-29: Speedy Pete’s is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows:
Solution Summary: The author explains the high-low method to classify the mixed cost into fixed and variable cost.
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function
Refer to the information for Speedy Pete’s above. Speedy Pete’s controller wants to calculate the fixed and variable costs associated with its cutting-edge delivery service.
Required:
Using the high-low method, calculate the fixed cost of deliveries, calculate the variable rate per delivery, and construct the cost formula for total delivery cost.
Use the following information for Brief Exercises 3-26 through 3-29:
Speedy Pete’s is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows: