Concept explainers
a)
To determine:The probability of completing the project in 17 months.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
a)
Answer to Problem 23P
The probability that the project completion time is 17 months is 0.0228.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 17 months:
The standard deviationis
Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the
Hence, the probability that the project completion time is 17 months is 0.0228.
b)
To determine:The probability of completing the project in 20 months.
b)
Answer to Problem 23P
The probability that the project completion time is 20 months is 0.3085.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 20 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.
Use the normal distribution tables to calculate the probability
The probability of project completion in 20 months is 0.3085.
Hence, the probability that the project completion time is 20 months is 0.3085.
c)
To determine:The probability of completing the project in 23 months.
c)
Answer to Problem 23P
The probability that the project completion time is 23 months is 0.8413.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 23 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.
Use the normal distribution tables to calculate the probability
The probability of project completion in 23 months is 0.8413.
Hence, the probability that the project completion time is 23 months is 0.8413.
d)
To determine:The probability of completing the project in 25 months.
d)
Answer to Problem 23P
The probability that the project completion time is 25 months is 0.9772.
Explanation of Solution
Given information:
Calculation of probability of completing the project in 25 months:
Calculate the standard deviation
Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.
Use the normal distribution tables to calculate the probability
The probability of project completion in 25 months is 0.9772.
Hence, the probability that the project completion time is 25 months is 0.9772.
e)
To compute: The due date that yields a 95% chance of completion.
e)
Answer to Problem 23P
The due date that yields a 95% chance of completionis 24.2 months.
Explanation of Solution
Given information:
Calculation of due date that yields a 95% chance of completion:
The z value from the normal distribution tables as shown below,
From the above tables, observe that the z value is 1.65.
Compute the due date that yields a 95% chance of completion.
The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.
Hence, the due date that yields a 95% chance of completion is 24.2 months.
Want to see more full solutions like this?
Chapter 3 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14arrow_forwardKimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.arrow_forward1.) You have determined the following for a given project: Expected completion time of the project = 40 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 44 weeks? answer as a decimal and take it to four places.arrow_forward
- Need help solving C and D. D) Freeze Inc.’s CEO established as a goal for top management to complete the project on or before 22 weeks. What is the probability that this project will be completed on or before 22 weeks?arrow_forward11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 4. Part 2 a) The probability that the project will be completed in 20 months = ______ (round your response to four decimal places)arrow_forwardAnalyse the sensitivity analysis and summarise the implications of the analysis for the project, Property acquisition 50%, financing 70% and construction 50%.arrow_forward
- A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)arrow_forwardAnswer following 4 questions 1: The probability that the project would be completed within 40 days: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 2: The probability that the project would take longer than 40 days is: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 3: The probability that the project would be completed within 20 days: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 4: The probability that the project would take longer than 20 days to finish: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the abovearrow_forward34arrow_forward
- The following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)arrow_forwardSuppose the due date of the project is 18 months and the probability of completing it is 75%, while the deviation from the mean is 1.8 months. What will be the expected time of completion?arrow_forwardCreate a risk matrix for this project:Event Cost ($000) ProbabilityEquipment breakdown 40 .20Vendor is late with key segment 200 .60Subcontractor has labor issues 140 .30Weather problems 15 UnknownFunding delays 50 .40 to .60Testing delays 20 .40Explain your reasoning for your placement of the events Weather problems and Funding delays.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.