PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 3, Problem 23P

a)

Summary Introduction

To determine:The probability of completing the project in 17 months.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

a)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 17 months is 0.0228.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 17 months:

The standard deviationis σ=2 , given the variance is 4. Therefore the z value is:

z=17212=2

Z is calculated by dividing the difference of 17 and 21 with 2 which gives -2. From the normal distribution tables z value -2 corresponds to 0.0228

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 3, Problem 23P , additional homework tip  1

Hence, the probability that the project completion time is 17 months is 0.0228.

b)

Summary Introduction

To determine:The probability of completing the project in 20 months.

b)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 20 months is 0.3085.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 20 months:

Calculate the standard deviation σ=2 , and compute the z value first:

z=21202=0.5

Z is calculated by dividing the difference of 21 and 20 with 2 which gives -0.5. From the normal distribution tables z value -0.5 corresponds to 0.3085.

Use the normal distribution tables to calculate the probability

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 3, Problem 23P , additional homework tip  2

The probability of project completion in 20 months is 0.3085.

Hence, the probability that the project completion time is 20 months is 0.3085.

c)

Summary Introduction

To determine:The probability of completing the project in 23 months.

c)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 23 months is 0.8413.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 23 months:

Calculate the standard deviation σ=2 , and compute the z value first

z=23212=1

Z is calculated by dividing the difference of 23 and 21 with 2 which gives 1. From the normal distribution tables z value 1 corresponds to 0.8413.

Use the normal distribution tables to calculate the probability

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 3, Problem 23P , additional homework tip  3

The probability of project completion in 23 months is 0.8413.

Hence, the probability that the project completion time is 23 months is 0.8413.

d)

Summary Introduction

To determine:The probability of completing the project in 25 months.

d)

Expert Solution
Check Mark

Answer to Problem 23P

The probability that the project completion time is 25 months is 0.9772.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of probability of completing the project in 25 months:

Calculate the standard deviation σ=2 , and compute the z value,

z=25212=2

Z is calculated by dividing the difference of 25 and 21 with 2 which gives 2. From the normal distribution tables z value 2 corresponds to 0.9772.

Use the normal distribution tables to calculate the probability

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 3, Problem 23P , additional homework tip  4

The probability of project completion in 25 months is 0.9772.

Hence, the probability that the project completion time is 25 months is 0.9772.

e)

Summary Introduction

To compute: The due date that yields a 95% chance of completion.

e)

Expert Solution
Check Mark

Answer to Problem 23P

The due date that yields a 95% chance of completionis 24.2 months.

Explanation of Solution

Given information:

Projectcompletion=21monthsProjectvariance=4months

Calculation of due date that yields a 95% chance of completion:

The z value from the normal distribution tables as shown below,

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 3, Problem 23P , additional homework tip  5

From the above tables, observe that the z value is 1.65.

Compute the due date that yields a 95% chance of completion.

=21months+(1.6×2months)=24.2months .

The due date is calculated by adding 21 months with the product of 1.6 and 2 which yields 24.2 months.

Hence, the due date that yields a 95% chance of completion is 24.2 months.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Anecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…
3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].
examine the production concept and operations management, what are the key steps required to achieve success?  Be specific in your response.

Chapter 3 Solutions

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY