Question
Chapter 3, Problem 7P
Summary Introduction
To develop: An activity on arrow (AOA) network diagram, given a sequence of project activities between various nodes and to determine its minimum duration.
Introduction: In the activity on arrow (AOA) project network diagram, the arrow represents an activity which has a starting point and an ending point. The starting and ending points are nodes in an activity network diagram. The activity consumes time and other resources, which are shown by the arrow between two nodes.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations.
Activity
Predecessor
Duration in Weeks
A
-
5
B
-
3
C
A, B
8
D
C
3
E
-
4
F
E
10
G
F
8
H
E
18
I
D
20
J
D, G, I
7
K
I
5
L
H
10
6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation:
the first pic:
First: Draw the precedence diagram.
Second: Using the notation given identify the duration of the project: you can type it.
Third: identify the critical part and explain the critical path.
Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found.
6B. Draw the project’s Gantt chart
First: The…
OPERATIONS
Duration and requirement of workforce for each activity is tabulated below for a network
Activity
Duration
Number of men
1-2
3
5
2-4
2
3
2-3
3
7
3-4
0
0
3-5
3
2
4-5
7
2
3-6
2
1
5-6
6
6
4-6
5
5
Use either PERT or CPM to
(i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce
(ii) Re-schedule the activities for smooth development
(iii) Find the project schedule if only 4 men are available
Can anybody draw a network analysis diagram of this problem?
Chapter 3 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using AOA, diagram the network describedbelow for Lillian Fok’s construction project. Calculate itscritical path. How long is the minimum duration of thisnetwork?arrow_forwardDr. Ell has been given a budget of $5,000 to organize a conference at her university in less than 2.5 months' time (9 weeks) via an educational grant. She has a team of 2 research assistants and after some deliberation, they identified the following activities that are required to be completed for hosting a successful conference. Immediate Predecessor Activity A B с D E F G H Description Deciding Dates and Number of sessions Determining Venue for conference Sending out a Call for Papers Inviting Special Speakers Responding to presenters Organizing Sessions with papers Getting registrations and confirmations Last minute Edits and Finalizing Program Dr. Ell has approached you, her student, to help her figure this out, as a part of her Management Science class assignment. Please give your respo with appropriate explanations, tables, and formulas, where relevant, to the following questions: BUAE U H 000000 1. PART 1. PERT/CPM with varying times a. Follow a PERT/CPM model to identify the…arrow_forwardPreceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!arrow_forward
- The Mobicom Corporation is in the design phase of a system project. The project manager wants to develop a network analysis diagram to plan the activities of designing the system outputs. The activities are as follows. ACTIVITY PRECEDING TIME[WEEKS] A ----- 5 B ---- 6 C ---- 4 D A,B 7 E C 8 F C,D 10 G D 8 Required Draw a network diagram for the design phasearrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardDraw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D…arrow_forward
- Q1: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7| 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50%]arrow_forward1.arrow_forwardMaladroit Cosmetics Company The plant manager of the Maladroit Cosmetics Company must replace several of her filling machines that have become obsolete. She is about to take delivery of six machines at a total cost of $4 million. These machines must be installed and fully tested in time to be used on a new production line scheduled to begin operation in 6 months. Because this project is important, the plant manager would like to devote as much time as possible to the job, but she is currently handling several other projects. She thinks she has three basic choices: (1) she can handle the project informally out of her office; (2) she can assign the project to a member of her staff; or (3) the company that manufactures the machines can handle the installation project for a fee close to what the installation would cost Maladroit. Questions A. Would you classify the work of installing the six machines as a project? B. Why or why not? C. Explain how the PM might trade off one of the…arrow_forward
- Make a list of the tasks that is necessary to build a duplex house (around 3000 sft) for you. Develop a table showing each task, its duration, preceding event(s), and expected duration. Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardCan you provide a clear drawing and step by step explanation?arrow_forwardThe director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administra assistant identified the various activities that must be done and their relationships to each other, as shown in the following table: Click the icon to view the activities. Because of the uncertainty in planning the new course, the assistant also has supplied the following time estimates for each acti Click the icon to view the time estimates. The director wants to conduct the seminar 46 working days from now. What is the probability that everything will be ready in time the standard normal table. (Make sure to round all intermediate calculations for t, and variance to two decimal places) The probability that the seminar will be ready in time is 0.8643]. (Enter your response rounded to four decimal places.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY