EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 3, Problem 20P

The estimated times and immediate predecessors for the activities in a project at George Kyparis’s retinal scanning company are given in the following table. Assume that the activity times are independent.

Chapter 3, Problem 20P, The estimated times and immediate predecessors for the activities in a project at George Kypariss

a) Calculate the expected time and variance for each activity.

b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?

c) What is the variance of the critical path? What is the variance of the other path in the network?

d) If the time to complete path A–C is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

e) If the time to complete path B–D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

f) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The expected time and variance.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

Answer to Problem 20P

The expected times and varianceare shown in Table 1.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Formula:

Calculate the expected time t and the variances for each activity by using the equations

t=(a+4m+b)6 (1)

where ‘a’ is the optimistic time, ‘m’ is the most likely time and ‘b’ is the most pessimistic time.

Variance=[(ba)6]2 (2)

Calculation of expected time and variance:

The calculations are shown below.

ActivityImmediate predecessorTime in weekstVariance
amb
A91011100.11
B41016104
CA91011100.11
DB581181

Table 1

Excel worksheet:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 20P , additional homework tip  1

Hence, the expected times and variance are shown in Table 1.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The  expected completion of critical path and other path (non-ciritical paths).

Answer to Problem 20P

The critical path is AàC and its expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Calculation of expected completion of critical path and other path (non-ciritical paths):

AON diagram is constructed which is shown below.

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 20P , additional homework tip  2

The critical path is AàC and expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.

Hence, the critical path is AàC and its expected completion time is 20 weeks. The expected completion time of the other path BàD is 18 weeks.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The  variance of critical path and other path (non-ciritical paths).

Answer to Problem 20P

The variance of the critical path AàC is 0.222 weeks and other path BàD is5 weeks.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Calculation of variance of critical path and other path:

The variance of the critical path AàC is the sum of the variances of activities A and C.

=0.1111+0.1111=0.2222

The variance of the critical path is the sum of 0.1111 and 0.1111 (refer table 1) which is 0.2222 weeks.

The variance of the other path BàD is the sum of the variances of activities B and D.

=4+1=5

The variance of the other path is the sum of 4 and 1 (refer table 1) which is 5 weeksThe variance of the other path BàD is 5 weeks.

Hence, the variance of the critical path AàC is 0.222 weeks and other path BàD is 5 weeks.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability of finishing the project in 22 weeks, when A-C is normally distributed.

Answer to Problem 20P

Probability of finishing the project in 22 weeks is almost 1.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Probability of finishing the project in 22 weeks, when A-C is normally distributed:

The expected completion time of critical path AàC is 20 weeks with a variance of 0.22 weeks.

The standard deviation:

σ=0.22=0.469

The standard deviation is calculated by taking square root of the variance which is 0.22 which yields 0.469.

z=22weeks20weeks0.469=4.264

Z value is calculated by dividing the difference of 22 and 20 with 0.469 which yields 4.264.

Reading from normal distribution tables given the mean is 20 weeks, the variance σ=0.469 and Z=4.264, the area under the probability distribution curve is almost 1. Therefore the probability that the project along the critical path AàC would be completed in 22 weeks is almost equal to 1.

Hence, probability of finishing the project in 22 weeks is almost 1.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability of finishing the project in 22 weeks, when B-D is normally distributed.

Answer to Problem 20P

Probability of finishing the project in 22 weeks is 0.963.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Probability of finishing the project in 22 weeks, when B-D is normally distributed:

The expected completion time of path BàD is 18 weeks with a variance of 5 weeks.

The standard deviation:

σ=5=2.236

The standard deviation is calculated by taking square root of the variance which is 5 which yields 2.236.

z=22weeks18weeks2.236=1.79

Z value is calculated by dividing the difference of 22 and 18 with 2.236 which yields 1.79.

Reading from normal distribution tables given the mean is 18 weeks, the variance σ=2.236 and z=1.79, the area under the probability distribution curve is 0.963.

Hence, the probability of finishing the project in 22 weeks is 0.963.

f)

Expert Solution
Check Mark
Summary Introduction

To explain: The reason for the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.

Explanation of Solution

Given information:

ActivityImmediate predecessorTime in weeks
amb
A91011
B41016
CA91011
DB5811

Explanation for the reason for the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less:

The critical path AàC has a very small variance of only 0.22 weeks compared to the variance along path BàD which is 5 weeks. That is why, despite having lower expected time of completion of 18 weeks, the probability that the path BàD would be completed in 22 weeks is0.963.and is lower than the probability 1 of project completion in 22 weeks along path AàC.

The project is completed only when all the activities are completed.

Despite the probability of the critical path AàC, being completed in 22 weeks being almost 1, the probability that the project is completed in 22 weeks is0.963.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas

Chapter 3 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY