EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 3, Problem 17P

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.

Chapter 3, Problem 17P, Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor

a) What is the expected (estimated) time for activity C?

b) What is the variance for activity C?

c) Based on the calculation of estimated times, what is the critical path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before week 36?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The expected time for activity C.

Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.

Answer to Problem 17P

The expected time for activity C is 12 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of expected time for activity C:

AON project network diagram shown below, given the precedence relationships of various activities,

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 17P , additional homework tip  1

Figure 1

With the given predecessor AON diagram is constructed. To Calculate the expected time for activity C given the data that the optimistic time estimate “a” of activity C of 8 weeks, the most likely time estimate “m” of 12 weeks and the pessimistic time estimate “b” of 16 weeks using the formula.

Expectedtime=a+4m+b6 (1)

Where ‘a’ is the optimistic time estimate, ‘m’ is the most likely time estimate and ‘b’ is the pessimistic time estimate

Substitute into the equation (1), the values of a=8 weeks, m=12 weeks and b=16 weeks to obtain the expected time for activity C.

t=8+(4×12)+166=726=12weeks

Therefore the expected time for activity C is calcualted by adding 8, 48 and16 and dividing the sum with 6 which gives 12weeks

Hence, the expected time for activity C is 12 weeks.

b)

Expert Solution
Check Mark
Summary Introduction

To calculate: The variance for activity C.

Answer to Problem 17P

The variance for activity C is 1.78 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of variance for activity C:

Calculate the variance for activity C using the formula

σ2=(b-a6)2 (2)

Substitute in equation (2) the values of b=16 weeks and a=8 weeks and obtain

σ2=(1686)2=169=1.78

The variance of activity C is calculated by squaring the value obtained by dividing the difference of 16 and 8 with 6 which gives the resultant as 1.28 weeks.

The variance in activity C is 1.78 weeks.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The critical path.

Answer to Problem 17P

The critical path AàCàFàHàJàK.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of critical path:

Using equation (1) and (2)calculate the expected times and variances for all the activitiesand obtain the values shown in table.

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 17P , additional homework tip  2

Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.

Hence, the critical path AàCàFàHàJàK.

d)

Expert Solution
Check Mark
Summary Introduction

To Compute: The estimated time of the critical path.

Answer to Problem 17P

The critical path AàCàFàHàJàK which is 40.18 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of estimated time of the critical path:

Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.

The various paths and the expected completion times are listed in the table

Various paths Completion times
AàBàEàFàIàK 37.18 weeks
AàBàEàGàJàK 31.18 weeks
AàCàFàHàJàK 40.18 weeks
AàCàGàJàK 31.51 weeks
AàDàJàK 22.84 weeks

Hence, the estimated time of the critical path AàCàFàHàJàK is 40.18 weeks.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The variance of the critical path.

Answer to Problem 17P

The variance of the critical path is 10.03 weeks.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of variance of the critical path:

The activity variance σ2along the critical path AàCàFàHàJàK is the sum of the variances of individual activities A, C, F, H, J and K.

Therefore,

σ2=1+1.78+5.44+0+1.78+0.03=10.03

The activity variance along the critical path is the sum of 1, 1.78, 5.44, 0, 1.78, 0.03 is 10.03 weeks.

Hence, the variance of the critical path is 10.03 weeks

f)

Expert Solution
Check Mark
Summary Introduction

To compute: The probability of completion of the project before week 36 weeks.

Answer to Problem 17P

The probability of completion of the project before week 36 weeks is 9.34%.

Explanation of Solution

Given information:

Activity Immediate predecessor Time estimates
Optimistic Most likely Pessimistic
A 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

Calculation of probability of completion of the project before week 36 weeks:

Use the normal distribution tables given that the estimated mean time is 40.18 weeks and the standard deviation is square root of 10.03 weeks.

First compute the standard deviation σ by computing the square root of 10.03 weeks.

σ=10.03=3.17weeks

Calculate the z value as shown below

z=36-40.183.17=-1.32

For a z value of -1.32, the probability is 9.34%.

Therefore, there is a probability of 9.34% that the project may be completed on or before 36 weeks.

Hence, the probability of completion of the project before week 36 weeks is 9.34%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Q1: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7| 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50%]
Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table. Question Viewer Activity Expected Time (weeks) Variance A 4.0 1.00 B 5.5 0.96 C 4.0 0.15 D 11.5 1.52 E 6.5 2.40 F 8.5 2.55 G 5.0 0.69 The probability that this path will take more than 15 weeks to complete is ☐. (Enter your response rounded to four decimal places.)
Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium.  He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity Predecessor Duration in Weeks A - 5 B - 3 C A, B 8 D C 3 E - 4 F E 10 G F 8 H E 18 I D 20 J D, G, I 7 K I 5 L H 10 6A.  Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation: the first pic: First: Draw the precedence diagram.     Second: Using the notation given identify the duration of the project: you can type it. Third: identify the critical part and explain the critical path.  Fourth:  Explain your answer.  This can be done by describing the process and the observations done once the answer has been found.     6B.  Draw the project’s Gantt chart First: The…

Chapter 3 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY