EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 3, Problem 3P
Summary Introduction
To determine: To draw the Gantt chart for the construction of a botanical garden and picnic area.
Introduction: Gantt charts were developed by Mr. HG in the late 1800s. This chart was designed in a way in which both
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
As part of the final requirement for the course ES034- Engineering Management, class
M8C1 is planning to conduct an outreach program in Barangay Labangon. The following
are the conceptualized activities necessary to be undertaken for the accomplishment of
this endeavor. Along with conditions, the university president emphasized that the
following action plan shall be carried out within 15 days only.
Activity
A
B
C
D
E
F
G
H
I
Description
Project Team Planning
Consultation with the Barangay Officials
Reservation of Guest Speakers
Estimation of Materials & Equipment
Expenses
Fund Raising
Canvassing & Procurement of Materials
Renting of Sound Equipment
Printing of Certificates & Programme
Information Dissemination
Precedent
Activity
None
A
A
B
C, D
E
E
F
G, H
Time
Estimate
S
(Days)
2
1
2
1
???
1
1
1
3
What is the project completion time? When will fund raising activity end? When will fund
raising activity start?
The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table.
What is the Late Finish on Activity D?
Prepare a detailed WBS, Precedence diagram and a Gantt chart showing the critical Path of the propose project a playground.
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B 9 с D E F G H Description Survey building site Develop initial design Obtain board approval Select architect 9 Establish budget Finalize design Obtain financing Hire contractor This answer has not been graded yet. Immediate Predecessor A, B с с D, E E F, G Time (weeks) 5 9 12 2 LO 5 15 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen 13 8 (b) Identify the critical path. (Enter your answers as a comma-separated list.) B. C.E.F.H 9 9arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forwardSolve the following attached problem using PERT or CPM.arrow_forward
- I'm unable to answer the following question? What is the total cost of crashing the project from its current duration down to 13 weeks?arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity Immediate Predecessor(s) A B с D E F G || D, E Normal Time Crash Time Normal Cost (weeks) ($) 3 7,000 2 3,000 3 12,000 4 12,000 1 8,000 6 5,000 3 9,000 (weeks) 1 2 1 3 1 4 2 D Crash Cost ($) 14,000 3,000 40,000 22,000 8,000 13,000 16,000arrow_forwardDifferent construction activities are given in a table below. Please draw arrow network possible relationship. with best logical clear representation of activities is required.arrow_forward
- Al construction has developed tasks duration and predecessor relationships in the following table for building model houses. The manager has been concerned with the amount of time it took to complete several jobs, some of the company workers are very unreliable. A list of activities and their optimistic completion time, the most likely time and the pessimistic completion time (in days) for a new contract are given in the following table. Activity Predecessors Optimistic (a) Most likely (m) Pessimistic (b) A -- 1 2 3 B - 2 3 4 C A 4 5 6 D B 8 9 10 E C, D 2 5 8 F D 4 5 6 G E 1 2 3 1.Draw the activity network for this new contract (either AON or AOA). 2. Determine the Expected Time and Variance for each activity. 3.. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table).…arrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 7 B Develop initial design 9 C Obtain board approval A, B 12 D Select architect C 4 E Establish budget C 7 F Finalize design D, E 16 G Obtain financing E 13 H Hire contractor F, G 6 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G…arrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A Carrow_forward
- b) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G Description Survey building site Develop initial design Obtain board approval Select architect Establish budget Finalize design Obtain financing Hire contractor Immediate Predecessor A, B C C D, E E F, G Time (weeks) 7 11 15 4 6 14 12 H (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File no fie selected 9arrow_forwardBuild a PERT Network Diagram for a 3-month project with 6 activities (A to F) and 5 nodesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY