Project Management at Arnold Palmer Hospital
Video Case
The equivalent of a new kindergarten class is born every day at Orlando’s Arnold Palmer Hospital. With more than 13,000 births in the mid-2000s in a hospital that was designed 15 years earlier for a capacity of 6,500 births a year, the newborn intensive care unit was stretched to the limit. Moreover, with continuing strong population growth in central Florida, the hospital was often full. It was clear that new facilities were needed. After much analysis,
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1,000 planning meetings (lasting from 45 minutes to a whole day). They even created a ‘Supreme Court’ to deal with conflicting views on the multifaceted issues facing the new hospital.
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1000 planning meetings (lasting from 45 minutes to a whole day). They even created a “Supreme Court” to deal with conflicting views on the multifaceted issues facing the new hospital.
Funding and regulatory issues added substantial complexity to this major expansion, and Hodges was very concerned that the project stay on time and within budget Tom Hyatt, director of facility development, was given the task of onsite manager of the $103 million project, in addition to overseeing ongoing renovations, expansions, and other projects. The activities in the multiyear project for the new building at Arnold Palmer are shown in Table 3.7.
*This list of activities is abbreviated for purposes of this case study. For simplification, assume each week = .25 months (i.e., 2 weeks = .5 month, 6 weeks = 1.5 months, etc.).
1. Develop the network for planning and construction of the new hospital at Arnold Palmer.
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Additional Business Textbook Solutions
Operations Management, Binder Ready Version: An Integrated Approach
Business in Action (8th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management
Operations Management: Processes and Supply Chains (11th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
- Milestone Project: Sample Project BriefEstablished in 2010, Jimmy Jonas Famous Sandwiches (JJFS) is a new, yet fast growing, sandwichshop. They established an early reputation for the best bread west of the Mississippi with qualityingredients and friendly, efficient service. Recently, however, efficiency has slipped. JJFS cannotkeep up with the increase in sales, especially in their catering orders. Although new employees havebeen added, the demand for their services is greater than their ability to handle it. As a result, somecustomers have deflected to other sandwich shops and catering orders have greatly declined. At thisrate, JJFS will develop a poor reputation, which could ultimately mean the end of their business.JJFS specializes in exceptional service and delivery. Along with their hundreds of stores, they arealso known for delivering at supersonic speed. JJFS caters all types of business luncheons, birthdayparties and other celebrations. JJFS has a comprehensive training…arrow_forwardWhat is the total cost for this project? (question a)iv.)arrow_forwardDraw a network diagram for the project. Find the minimum project completion time. Identify the critical activities and critical path.arrow_forward
- 46 Question 23 The project manager must be willing to manage within the guidelines, policies, procedures, rules, and directives of the parent company. True Falsearrow_forwardQUESTION 2 You are the project manager of a software installation project. You would like to find the minimum-cost schedule for your project. There is a $1000-per-week penalty for each week the project is delayed beyond 25 weeks. In addition, your project team determined that indirect costs are $2,500 per week. Activity A B C D E FC G H Immediate Normal Time Normal Cost Predecessor (weeks) 5 8 10 4 3 9 2 8 9 A A, B B D E, F G C, F ($) 2,000 5,000 10,000 3,000 4,000 8,000 2,000 6,000 7,000 Crash Time (weeks) 3 7 8 3 2 6 2 5 7 a) What is the target completion week? b) How much would you save in total project costs with your schedule? Crash Cost ($) 4,000 8,000 12,000 7,000 5,000 14,000 2,000 9,000 15,000arrow_forward7arrow_forward
- Construct a network diagram for this project? TABLE 1: Activities and duration project Duration in weeks __________________________________ Activity Proceeding activity Optimistic Most likely Pessimistic A - 2 3 3 B - 10 12 15 C A 4 5 8 D B 2 2 2 E A, D 3 3 3 F…arrow_forwardBelow is the first set of activities (Phase I) in constructing a new house, the respective time required to finish each activity, and the precedence relations. Activity A Description Predecessor Duration (in wks) 1 Clear site Bring utilities to the site Excavate 2 A 1 D Pour Foundation Outside Plumbing 2 E B,C 6 Frame House 8 G Do electric wiring Lay Floor Lay Roof Inside Plumbing 3 G 2 F 1 E,H (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying the project? (g) If there will be a delay in doing the outside plumbing without delaying the entire project, how long should it be?arrow_forwardInformation provided is for end of day 6: 1. What is the actual cost so far? 2. What is the estimated time to completion? ( show formula and working) 3. What is the estimated cost to completion? ( show formula and working)arrow_forward
- Textbook PB Question 1A/BD: a) Draw a project network from the table above b) What activity(s) is a burst activity? What activity(s) is a merge activity? 3. What is the length of the project? 4. What is the critical path? c) Make the Gantt chart d) Build the project network using expected activity times based on the new table below e) What would be the expected length of the project? f) What would be the project standard deviation? g) Using a z-table (one can be found here: https://statisticsbyjim.com/hypothesis-testing/z-table/ ), what is the probability that the project can be completed in 28 weeks?arrow_forwardP11-1 Drawing simple CPM diagram and determining critical path From the following information draw a network showing the critical path and calculate the minimum time required to complete the work. Activity Duration (days) A B C D E F G H I 1 2 3 1 8 3 2 1 2 A must be completed before starting the other activities, B, C and E can commence concurrently after completion of A. D can commence after completion of B and C. F can commence after completion of C and E. G follows F, and H follows D. I can commence after completion of G and H. Number your nodes.arrow_forwardU2arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.