Advent Software uses standards to manage the cost of the programming staff. There are two programmer levels, Level 1 and Level 2. Level 1 programmers normally work on the easier projects. Level 1 and Level 2 programmers are paid $25 and $35 per hour, respectively. It has been determined from experience that Level 2 programmers can complete 50 lines of code per hour. If a Level 1 programmer is assigned to a Level 2 task, the programming work will be slower than the Level 2 time standard, but will be accomplished at a lower labor rate.
During a recent week, a Level 2 project was assigned to a Level 1 programmer. The programmer worked 40 hours and completed 1,400 lines of code.
- a. Determine the direct labor time variance for this worker.
- b. Determine the direct labor rate variance for this worker.
- c. Using the information in (a) and (b), is it more cost effective to use a Level 1 worker or a Level 2 worker on a Level 2 project?
Trending nowThis is a popular solution!
Chapter 23 Solutions
Financial And Managerial Accounting
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning