Summary Introduction

To determine: The suitable outsourcing provider based on cultural risk factors using factor- rating method.

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

Expert Solution & Answer
Check Mark

Answer to Problem 9P

Ranga should select Mexico.

Explanation of Solution

Given information:

Current Selection Criterion Weight Mexico Panama Costa Rica Peru
Trust 0.4 1 2 2 1
Society value of quality work 0.2 7 10 9 10
Religious attitudes 0.1 3 3 3 5
Individualism attitudes 0.1 5 2 4 8
Time orientation attitudes 0.1 4 6 7 3
Uncertainty avoidance attitudes 0.1 3 2 4 2

Low Risk = 1

High Risk = 10

Formula to calculate weighted risk:

Weighted Risk = Weight × Risk rating

Formula to calculate Total weighted risk:

Total weighted risk = Individualweightedrisk

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 2, Problem 9P , additional homework tip  1

Excel Formula:

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 2, Problem 9P , additional homework tip  2

Excel Explanation:

Calculation of weighted risk for Mexico:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Trust:

Trust = 0.4 × 1=0.4

The weighted risk for Trust is 0.4.

Society value of quality work:

Society value of quality  work = 0.2 × 7=1.4

The weighted risk for society value of quality work is 1.4.

Religious attitudes:

Religious attitudes = 0.1 × 3=0.3

The weighted risk for Religious attitudes is 0.3.

Individualism attitudes:

Individualism attitudes = 0.1 × 5=0.5

The weighted risk for Individualism attitudes is 0.5.

Time orientation attitudes:

Time orientation attitudes = 0.1 × 4=0.4

The weighted risk for Time orientation attitudes is 0.4.

Uncertainty avoidance attitudes:

Uncertainty avoidance attitudes = 0.1 × 3=0.3

The weighted risk for Uncertainty avoidance attitudes is 0.3.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.4 + 1.4 + 0.3 + 0.5 + 0.4 + 0.3= 3.3

The total weighted risk for Mexico is 3.3.

Calculation of weighted risk for Panama:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Trust:

Trust = 0.4 × 2=0.8

The weighted risk for Trust is 0.8.

Society value of quality work:

Society value of quality  work = 0.2 × 10=2

The weighted risk for society value of quality work is 2.

Religious attitudes:

Religious attitudes = 0.1 × 3=0.3

The weighted risk for Religious attitudes is 0.3.

Individualism attitudes:

Individualism attitudes = 0.1 × 2=0.2

The weighted risk for Individualism attitudes is 0.2.

Time orientation attitudes:

Time orientation attitudes = 0.1 × 6=0.6

The weighted risk for Time orientation attitudes is 0.6.

Uncertainty avoidance attitudes:

Uncertainty avoidance attitudes = 0.1 × 2=0.2

The weighted risk for Uncertainty avoidance attitudes is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.8 + 2 + 0.3 + 0.2 + 0.6 + 0.2= 4.1

The total weighted risk for Panama is 4.1.

Calculation of weighted risk for Costa Rica:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Trust:

Trust = 0.4 × 2=0.8

The weighted risk for Trust is 0.8.

Society value of quality work:

Society value of quality  work = 0.2 × 9=1.8

The weighted risk for society value of quality work is 1.8.

Religious attitudes:

Religious attitudes = 0.1 × 3=0.3

The weighted risk for Religious attitudes is 0.3.

Individualism attitudes:

Individualism attitudes = 0.1 × 4=0.4

The weighted risk for Individualism attitudes is 0.4.

Time orientation attitudes:

Time orientation attitudes = 0.1 × 7=0.7

The weighted risk for Time orientation attitudes is 0.7.

Uncertainty avoidance attitudes:

Uncertainty avoidance attitudes = 0.1 × 4=0.4

The weighted risk for Uncertainty avoidance attitudes is 0.4.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.8 + 1.8 + 0.3 + 0.4 + 0.7 + 0.4= 4.4

The total weighted risk for Costa Rica is 4.4.

Calculation of weighted risk for Peru:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Trust:

Trust = 0.4 × 1=0.4

The weighted risk for Trust is 0.4.

Society value of quality work:

Society value of quality  work = 0.2 × 10=2

The weighted risk for society value of quality work is 2.

Religious attitudes:

Religious attitudes = 0.1 × 5=0.5

The weighted risk for Religious attitudes is 0.5.

Individualism attitudes:

Individualism attitudes = 0.1 × 8=0.8

The weighted risk for Individualism attitudes is 0.8.

Time orientation attitudes:

Time orientation attitudes = 0.1 × 3=0.3

The weighted risk for Time orientation attitudes is 0.3.

Uncertainty avoidance attitudes:

Uncertainty avoidance attitudes = 0.1 × 2=0.2

The weighted risk for Uncertainty avoidance attitudes is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.4 + 2 + 0.5 + 0.8 + 0.3 + 0.2= 4.2

The total weighted risk for Peru is 4.2.

The weighted risk value for Mexico is 3.3. The weighted risk value for Panama is 4.1. The weighted risk value for Costa Rica is 4.4. The weighted risk value for Peru is 4.2. Since, the risk value for Mexico is less (3.3 < 4.1, 4.4, 4.2), Mexico is selected.

Hence, Ranga should select Mexico.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Government's new plan to shift cargo from roads back to rail 26TH JANUARY 2024 Government is seeking to finalise a plan aimed at improving its rail network and move cargo away from a billion rand per day to its logistics crises, government has said an urgentturnaround is needed to improve its 31 000km locomotive network as more and more cargo moves from rail to trucks. The Department of Transport (DoT) hosted a discussion with industry stakeholders regarding the Freight Road to Rail Migration Plan on Thursday - the latest development in the wake of President Cyril Ramphosa forming the National Logistics Crisis Committee last year. Transnet, the South African National Roads Agency (Sanral) and private sector companies were all in attendance. The Freight Road to Rail Migration Plan is part of government's strategies to improve the country's ongoing logistics crises. In October last year, the government unveiled its Freight Logistics Roadmap to improve the ports and rail networks and…
Assess what led to such logistical inefficiencies / collapse of a previously world class freight network
Which of the following statements concerning the evaluation of training programs is true?   Most companies thoroughly evaluate the return on investment of their training programs   It is relatively easy to establish a control group and a treatment group for evaluation   Results level of evaluation measures how well participants liked the program   Behavior level criteria measure whether skills learned in training result in behavior changes back on the job
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning