a)
To determine: The suitable outsourcing provider for logistics services using factor- rating method.
Introduction:
Factor-rating method:
The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.
a)

Answer to Problem 10P
Garza should select worldwide delivery.
Explanation of Solution
Given information:
Ratings of Logistics Providers | ||||
Criterion | Weight | Overnight Shipping | Worldwide Delivery | United Freight |
Quality | 5 | 90 | 80 | 75 |
Delivery | 3 | 70 | 85 | 70 |
Cost | 2 | 70 | 80 | 95 |
Weights = 1-5 (5 – Highest)
Ratings = 1-100 (100 – Highest)
Formula to calculate weighted rating:
Formula to calculate weighted average:
Excel Formula:
Calculation for Overnight Shipping:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 450.
Delivery:
The weighted rating for Delivery is 210.
Cost:
The weighted rating for Cost is 140.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for Overnight shipping is 80.
Calculation for Worldwide delivery:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 400.
Delivery:
The weighted rating for Delivery is 255.
Cost:
The weighted rating for Cost is 160.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for worldwide delivery is 81.5.
Calculation for United Freight:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 375.
Delivery:
The weighted rating for Delivery is 210.
Cost:
The weighted rating for Cost is 190.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for United Freight is 77.5.
The weighted average value for Overnight Shipping is 80. The weighted average value for worldwide delivery is 81.5. The weighted average value for united Freight is 77.5. The weighted average value is more for worldwide delivery (81.5 > 80, 77.5)
Hence, Garza should select worldwide delivery.
b)
To determine: The suitable outsourcing provider for logistics services using factor- rating method when the weights are changed.
Introduction:
Factor-rating method:
The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.
b)

Answer to Problem 10P
There is No Change.
Explanation of Solution
Given information:
Ratings of Logistics Providers | ||||
Criterion | Weight | Overnight Shipping | Worldwide Delivery | United Freight |
Quality | 10 | 90 | 80 | 75 |
Delivery | 6 | 70 | 85 | 70 |
Cost | 4 | 70 | 80 | 95 |
Weights = 1-10 (10 – Highest)
Ratings = 1-100 (100 – Highest)
Formula to calculate weighted rating:
Formula to calculate weighted average:
Excel Formula:
Calculation for Overnight Shipping:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 900.
Delivery:
The weighted rating for Delivery is 420.
Cost:
The weighted rating for Cost is 280.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for Overnight shipping is 80.
Calculation for Worldwide delivery:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 800.
Delivery:
The weighted rating for Delivery is 510.
Cost:
The weighted rating for Cost is 320.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for worldwide delivery is 81.5.
Calculation for United Freight:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 750.
Delivery:
The weighted rating for Delivery is 420.
Cost:
The weighted rating for Cost is 380.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for United Freight is 77.5.
The weighted average value for Overnight Shipping is 80. The weighted average value for worldwide delivery is 81.5. The weighted average value for united Freight is 77.5. The weighted average value is more for worldwide delivery (81.5 > 80, 77.5)
There is no change in the result because there is no change made to the ratings. The weights were doubled without changes to any other parameter. Hence, there is no change in the conclusion attained in part (a).
Hence, there is No change.
c)
To determine: The suitable outsourcing provider for logistics services using factor- rating method when there is 10% increase in Overnight Shipping ratings.
Introduction:
Factor-rating method:
The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.
c)

Answer to Problem 10P
The best outsourcing provider is Overnight Shipping.
Explanation of Solution
Given information:
Ratings of Logistics Providers | ||||
Criterion | Weight | Overnight Shipping | Worldwide Delivery | United Freight |
Quality | 10 | 90 | 80 | 75 |
Delivery | 6 | 70 | 85 | 70 |
Cost | 4 | 70 | 80 | 95 |
Weights = 1-10 (10 – Highest)
Ratings = 1-100 (100 – Highest)
Formula to calculate weighted rating:
Formula to calculate weighted average:
Formula to calculate 10% of Overnight Shipping ratings:
Formula to calculate New Overnight Shipping rating:
Excel Formula:
Calculation of 10 % of Overnight Shipping ratings:
Quality:
The 10% value of Quality is 9.
Delivery:
The 10% value of delivery is 7.
Cost:
The 10% value of cost is 7.
Calculation of New Overnight Shipping ratings:
Quality:
The new quality overnight shipping rating is 99.
Delivery:
The new delivery overnight shipping rating is 77.
Cost:
The new cost overnight shipping rating is 77.
Calculation for Overnight Shipping:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 495.
Delivery:
The weighted rating for Delivery is 231.
Cost:
The weighted rating for Cost is 154.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for Overnight shipping is 88.
Calculation for Worldwide delivery:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 400.
Delivery:
The weighted rating for Delivery is 255.
Cost:
The weighted rating for Cost is 160.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for worldwide delivery is 81.5.
Calculation for United Freight:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the individual rating with the weight assigned for each criterion.
Quality:
The weighted rating for Quality is 375.
Delivery:
The weighted rating for Delivery is 210.
Cost:
The weighted rating for Cost is 190.
Calculation of weighted average:
The weighted average is calculated by dividing the summation of the individual weighted rating by the summation of the individual weights.
The weighted average for United Freight is 77.5.
The weighted average value for Overnight Shipping is 88. The weighted average value for worldwide delivery is 81.5. The weighted average value for united Freight is 77.5. The weighted average value is more for Overnight Shipping (88 > 81.5, 77.5)
Hence, Garza should select Overnight Shipping.
Want to see more full solutions like this?
Chapter 2 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- in the MABE: learning to be multinational case report, what is the reccomended course of action?arrow_forwardIn the MABE case report what would be the reccomened course of action?arrow_forwardQuestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i) Solve this LPP by using graphical analysis ii) What will be the slack at the optimal solution point? Show calculation.arrow_forward
- qusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forwardG ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forwardNot use ai pleasearrow_forward
- Items removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forwardCould you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forwardApple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forward
- Critical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forwardNeed help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing