Question
Chapter 1.S, Problem 15P
a)
Summary Introduction
To determine: The best decision by calculating the expected value for each decision.
Introduction: Decision analysis can be interpreted as the most common technique to decide in the situation when there is uncertainty. It uses quantitative measures to analyse the decision that is also used in operation of the firms.
b)
Summary Introduction
To determine: The best overall decision.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Bloom's Jeans is searching for new suppliers, and DebbieBloom, the owner, has narrowed her choices to two sets. Debbie isvery concerned about supply disruptions, so she has chosen to usethree suppliers no matter what. For option l, the suppliers are wellestablished and located in the same country. Debbie calculates the" unique-event" risk for each of them to be 4%. She estimates theprobability of a nationwide event that would knock out all three suppliersto be 2.5%. For option 2, the suppliers are newer but located inthree different countries. Debbie calculates the " unique-event" riskfor each of them to be 20%. She estimates the "super-event" probabilitythat would knock out all three of these suppliers to be 0.4%.Purchasing and transportation costs would be $1 ,000,000 per yearusing option 1 and $1,0 I 0,000 per year using option 2. A total disruptionwould create an annualized loss of$500,000.a) What is the probability that all three suppliers will be disru pled using option 1?b) What…
Philibert Enterprises Inc is a manufacturing and distribution company that is engaged in
supplying exotic Caribbean Food products of high quality for the European and North
American markets. The Product Quality and consistency of supplies of the product are two
critical success factors. Philibert Enterprises Inc. has been using its website as its principal
point of contact for its customers, It recently won a major contract to supply the Marks&
Spencer chain in the UK, where persons of Caribbean origin are a significant group in the
population. This is in addition to the growing popularity of Caribbean Cuisine
internationally. High productivity levels are necessary to meet the product quality and
delivery time requirements. The Marketing Manager is expected to work closely with the
Human Resource Manager to develop a reward system that will enable greater reliability
with respect to response time and assure quality and compliance with HACCAP
equirements.
tline the factors that…
Macrosoft Corporation is a software giant in personal computers (PCs). Although its flagship operating system ‘Meadow’ is still dominating in the PC market, the burgeoning of tablets and smartphones in recent years has been chewing up the PC market. In fact, the numbers of new Meadow users was shrinking every year. In view of this situation, Macrosoft is considering making an offer to purchase Oats Production, and upstart smartphone producer in China. The management of Macrosoft hopes that the acquisition could allow the company to explore the smartphone software market and bring in new revenue to the firm. The treasurer of Macrosoft has collected the following information:
Macrosoft Corporation
Oats Production
Shares outstanding
1,500,000
800,000
Earnings
$8,400,000
$2,400,000
Divdends
$4,200,000
$1,800,000
Price-earnings ratio
18X
15X
The treasurer also discovers that the earnings and dividends of Oats will grow at a constant rate of 6% every year. If the acquisition…
Chapter 1 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 1.S - Prob. 1PCh. 1.S - Prob. 2PCh. 1.S - Prob. 3PCh. 1.S - Prob. 4PCh. 1.S - Prob. 5PCh. 1.S - In Problem S1-5 assume that Nicole, with the help...Ch. 1.S - Prob. 7PCh. 1.S - Prob. 8PCh. 1.S - Telecomp, a computer manufacturer with a global...Ch. 1.S - Prob. 10P
Ch. 1.S - Prob. 11PCh. 1.S - Prob. 12PCh. 1.S - Prob. 13PCh. 1.S - Prob. 14PCh. 1.S - Prob. 15PCh. 1.S - Prob. 16PCh. 1.S - Prob. 17PCh. 1.S - Prob. 18PCh. 1.S - In Problem S1-18, assume the Weight Club is able...Ch. 1.S - Prob. 20PCh. 1.S - Prob. 21PCh. 1.S - Prob. 22PCh. 1.S - Prob. 23PCh. 1.S - Prob. 24PCh. 1.S - Prob. 25PCh. 1.S - Prob. 26PCh. 1.S - Prob. 27PCh. 1.S - Prob. 28PCh. 1.S - Prob. 29PCh. 1.S - Prob. 30PCh. 1.S - Prob. 31PCh. 1.S - Prob. 33PCh. 1.S - Prob. 34PCh. 1.S - Alex Mason has a wide-curving, uphill driveway...Ch. 1.S - Prob. 36PCh. 1.S - Prob. 39PCh. 1.S - Prob. 40PCh. 1.S - State University has three healthcare plans for...Ch. 1.S - The Orchard Wine Company purchases grapes from one...Ch. 1.S - Prob. 43PCh. 1.S - Prob. 1.1CPCh. 1.S - Prob. 2.1CPCh. 1.S - Evaluating Projects at Nexcom Systems Nexcom...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Prob. 1QCh. 1 - What constitutes operations at (a) a bank, (b) a...Ch. 1 - Prob. 3QCh. 1 - Prob. 4QCh. 1 - Prob. 5QCh. 1 - Prob. 17QCh. 1 - What is the difference between an order winner and...Ch. 1 - Prob. 21QCh. 1 - Prob. 22QCh. 1 - Prob. 23QCh. 1 - Prob. 24QCh. 1 - Prob. 1PCh. 1 - Prob. 2PCh. 1 - Prob. 3PCh. 1 - Prob. 4PCh. 1 - Prob. 5PCh. 1 - Omar Industries maintains production facilities in...Ch. 1 - Rushing yardage for three Heisman Trophy...Ch. 1 - Carpet City recorded the following data on carpet...Ch. 1 - Prob. 9PCh. 1 - Prob. 10PCh. 1 - Prob. 11PCh. 1 - Prob. 12PCh. 1 - Prob. 13PCh. 1 - Prob. 14PCh. 1 - Prob. 15PCh. 1 - Prob. 1.1CPCh. 1 - Prob. 1.2CPCh. 1 - Prob. 1.3CPCh. 1 - Prob. 1.4CPCh. 1 - Prob. 1.5CPCh. 1 - Prob. 2.1CPCh. 1 - Prob. 2.2CP
Knowledge Booster
Similar questions
- The Global Sourcing Wire Harness Decision Sheila Austin, a buyer at Autolink, a Detroit-based producer of subassemblies for the automotive market, has sent out requests for quotations for a wiring harness to four prospective suppliers. Only two of the four suppliers indicated an interest in quoting the business: Original Wire (Auburn Hills, MI) and Happy Lucky Assemblies (HLA) of Guangdong Province, China. The estimated demand for the harnesses is 5,000 units a month. Both suppliers will incur some costs to retool for this particular harness. The harnesses will be prepackaged in 24 12 6-inch cartons. Each packaged unit weighs approximately 10 pounds. Quote 1 The first quote received is from Original Wire. Auburn Hills is about 20 miles from Autolinks corporate headquarters, so the quote was delivered in person. When Sheila went down to the lobby, she was greeted by the sales agent and an engineering representative. After the quote was handed over, the sales agent noted that engineering would be happy to work closely with Autolink in developing the unit and would also be interested in future business that might involve finding ways to reduce costs. The sales agent also noted that they were hungry for business, as they were losing a lot of customers to companies from China. The quote included unit price, tooling, and packaging. The quoted unit price does not include shipping costs. Original Wire requires no special warehousing of inventory, and daily deliveries from its manufacturing site directly to Autolinks assembly operations are possible. Original Wire Quote: Unit price = 30 Packing costs = 0.75 per unit Tooling = 6,000 one-time fixed charge Freight cost = 5.20 per hundred pounds Quote 2 The second quote received is from Happy Lucky Assemblies of Guangdong Province, China. The supplier must pack the harnesses in a container and ship via inland transportation to the port of Shanghai in China, have the shipment transferred to a container ship, ship material to Seattle, and then have material transported inland to Detroit. The quoted unit price does not include international shipping costs, which the buyer will assume. HLA Quote: Unit price = 19.50 Shipping lead time = Eight weeks Tooling = 3,000 In addition to the suppliers quote, Sheila must consider additional costs and information before preparing a comparison of the Chinese suppliers quotation: Each monthly shipment requires three 40-foot containers. Packing costs for containerization = 2 per unit. Cost of inland transportation to port of export = 200 per container. Freight forwarders fee = 100 per shipment (letter of credit, documentation, etc.). Cost of ocean transport = 4,000 per container. This has risen significantly in recent years due to a shortage of ocean freight capacity. Marine insurance = 0.50 per 100 of shipment. U.S. port handling charges = 1,200 per container. This fee has also risen considerably this year, due to increased security. Ports have also been complaining that the charges may increase in the future. Customs duty = 5% of unit cost. Customs broker fees per shipment = 300. Transportation from Seattle to Detroit = 18.60 per hundred pounds. Need to warehouse at least four weeks of inventory in Detroit at a warehousing cost of 1.00 per cubic foot per month, to compensate for lead time uncertainty. Sheila must also figure the costs associated with committing corporate capital for holding inventory. She has spoken to some accountants, who typically use a corporate cost of capital rate of 15%. Cost of hedging currencybroker fees = 400 per shipment Additional administrative time due to international shipping = 4 hours per shipment 25 per hour (estimated) At least two five-day visits per year to travel to China to meet with supplier and provide updates on performance and shipping = 20,000 per year (estimated) The international sourcing costs must be absorbed by Sheila, as the supplier does not assume any of the additional estimated costs and invoice Sheila later, or build the costs into a revised unit price. Sheila feels that the U.S. supplier is probably less expensive, even though it quoted a higher price. Sheila also knows that this is a standard technology that is unlikely to change during the next three years, but which could be a contract that extends multiple years out. There is also a lot of hall talk amongst the engineers on her floor about next-generation automotive electronics, which will completely eliminate the need for wire harnesses, which will be replaced by electronic components that are smaller, lighter, and more reliable. She is unsure about how to calculate the total costs for each option, and she is even more unsure about how to factor these other variables into the decision. Calculate the total cost per unit of purchasing from Happy Lucky Assemblies.arrow_forwardThe Global Sourcing Wire Harness Decision Sheila Austin, a buyer at Autolink, a Detroit-based producer of subassemblies for the automotive market, has sent out requests for quotations for a wiring harness to four prospective suppliers. Only two of the four suppliers indicated an interest in quoting the business: Original Wire (Auburn Hills, MI) and Happy Lucky Assemblies (HLA) of Guangdong Province, China. The estimated demand for the harnesses is 5,000 units a month. Both suppliers will incur some costs to retool for this particular harness. The harnesses will be prepackaged in 24 12 6-inch cartons. Each packaged unit weighs approximately 10 pounds. Quote 1 The first quote received is from Original Wire. Auburn Hills is about 20 miles from Autolinks corporate headquarters, so the quote was delivered in person. When Sheila went down to the lobby, she was greeted by the sales agent and an engineering representative. After the quote was handed over, the sales agent noted that engineering would be happy to work closely with Autolink in developing the unit and would also be interested in future business that might involve finding ways to reduce costs. The sales agent also noted that they were hungry for business, as they were losing a lot of customers to companies from China. The quote included unit price, tooling, and packaging. The quoted unit price does not include shipping costs. Original Wire requires no special warehousing of inventory, and daily deliveries from its manufacturing site directly to Autolinks assembly operations are possible. Original Wire Quote: Unit price = 30 Packing costs = 0.75 per unit Tooling = 6,000 one-time fixed charge Freight cost = 5.20 per hundred pounds Quote 2 The second quote received is from Happy Lucky Assemblies of Guangdong Province, China. The supplier must pack the harnesses in a container and ship via inland transportation to the port of Shanghai in China, have the shipment transferred to a container ship, ship material to Seattle, and then have material transported inland to Detroit. The quoted unit price does not include international shipping costs, which the buyer will assume. HLA Quote: Unit price = 19.50 Shipping lead time = Eight weeks Tooling = 3,000 In addition to the suppliers quote, Sheila must consider additional costs and information before preparing a comparison of the Chinese suppliers quotation: Each monthly shipment requires three 40-foot containers. Packing costs for containerization = 2 per unit. Cost of inland transportation to port of export = 200 per container. Freight forwarders fee = 100 per shipment (letter of credit, documentation, etc.). Cost of ocean transport = 4,000 per container. This has risen significantly in recent years due to a shortage of ocean freight capacity. Marine insurance = 0.50 per 100 of shipment. U.S. port handling charges = 1,200 per container. This fee has also risen considerably this year, due to increased security. Ports have also been complaining that the charges may increase in the future. Customs duty = 5% of unit cost. Customs broker fees per shipment = 300. Transportation from Seattle to Detroit = 18.60 per hundred pounds. Need to warehouse at least four weeks of inventory in Detroit at a warehousing cost of 1.00 per cubic foot per month, to compensate for lead time uncertainty. Sheila must also figure the costs associated with committing corporate capital for holding inventory. She has spoken to some accountants, who typically use a corporate cost of capital rate of 15%. Cost of hedging currencybroker fees = 400 per shipment Additional administrative time due to international shipping = 4 hours per shipment 25 per hour (estimated) At least two five-day visits per year to travel to China to meet with supplier and provide updates on performance and shipping = 20,000 per year (estimated) The international sourcing costs must be absorbed by Sheila, as the supplier does not assume any of the additional estimated costs and invoice Sheila later, or build the costs into a revised unit price. Sheila feels that the U.S. supplier is probably less expensive, even though it quoted a higher price. Sheila also knows that this is a standard technology that is unlikely to change during the next three years, but which could be a contract that extends multiple years out. There is also a lot of hall talk amongst the engineers on her floor about next-generation automotive electronics, which will completely eliminate the need for wire harnesses, which will be replaced by electronic components that are smaller, lighter, and more reliable. She is unsure about how to calculate the total costs for each option, and she is even more unsure about how to factor these other variables into the decision. Based on the total cost per unit, which supplier should Sheila recommend?arrow_forwardThe Global Sourcing Wire Harness Decision Sheila Austin, a buyer at Autolink, a Detroit-based producer of subassemblies for the automotive market, has sent out requests for quotations for a wiring harness to four prospective suppliers. Only two of the four suppliers indicated an interest in quoting the business: Original Wire (Auburn Hills, MI) and Happy Lucky Assemblies (HLA) of Guangdong Province, China. The estimated demand for the harnesses is 5,000 units a month. Both suppliers will incur some costs to retool for this particular harness. The harnesses will be prepackaged in 24 12 6-inch cartons. Each packaged unit weighs approximately 10 pounds. Quote 1 The first quote received is from Original Wire. Auburn Hills is about 20 miles from Autolinks corporate headquarters, so the quote was delivered in person. When Sheila went down to the lobby, she was greeted by the sales agent and an engineering representative. After the quote was handed over, the sales agent noted that engineering would be happy to work closely with Autolink in developing the unit and would also be interested in future business that might involve finding ways to reduce costs. The sales agent also noted that they were hungry for business, as they were losing a lot of customers to companies from China. The quote included unit price, tooling, and packaging. The quoted unit price does not include shipping costs. Original Wire requires no special warehousing of inventory, and daily deliveries from its manufacturing site directly to Autolinks assembly operations are possible. Original Wire Quote: Unit price = 30 Packing costs = 0.75 per unit Tooling = 6,000 one-time fixed charge Freight cost = 5.20 per hundred pounds Quote 2 The second quote received is from Happy Lucky Assemblies of Guangdong Province, China. The supplier must pack the harnesses in a container and ship via inland transportation to the port of Shanghai in China, have the shipment transferred to a container ship, ship material to Seattle, and then have material transported inland to Detroit. The quoted unit price does not include international shipping costs, which the buyer will assume. HLA Quote: Unit price = 19.50 Shipping lead time = Eight weeks Tooling = 3,000 In addition to the suppliers quote, Sheila must consider additional costs and information before preparing a comparison of the Chinese suppliers quotation: Each monthly shipment requires three 40-foot containers. Packing costs for containerization = 2 per unit. Cost of inland transportation to port of export = 200 per container. Freight forwarders fee = 100 per shipment (letter of credit, documentation, etc.). Cost of ocean transport = 4,000 per container. This has risen significantly in recent years due to a shortage of ocean freight capacity. Marine insurance = 0.50 per 100 of shipment. U.S. port handling charges = 1,200 per container. This fee has also risen considerably this year, due to increased security. Ports have also been complaining that the charges may increase in the future. Customs duty = 5% of unit cost. Customs broker fees per shipment = 300. Transportation from Seattle to Detroit = 18.60 per hundred pounds. Need to warehouse at least four weeks of inventory in Detroit at a warehousing cost of 1.00 per cubic foot per month, to compensate for lead time uncertainty. Sheila must also figure the costs associated with committing corporate capital for holding inventory. She has spoken to some accountants, who typically use a corporate cost of capital rate of 15%. Cost of hedging currencybroker fees = 400 per shipment Additional administrative time due to international shipping = 4 hours per shipment 25 per hour (estimated) At least two five-day visits per year to travel to China to meet with supplier and provide updates on performance and shipping = 20,000 per year (estimated) The international sourcing costs must be absorbed by Sheila, as the supplier does not assume any of the additional estimated costs and invoice Sheila later, or build the costs into a revised unit price. Sheila feels that the U.S. supplier is probably less expensive, even though it quoted a higher price. Sheila also knows that this is a standard technology that is unlikely to change during the next three years, but which could be a contract that extends multiple years out. There is also a lot of hall talk amongst the engineers on her floor about next-generation automotive electronics, which will completely eliminate the need for wire harnesses, which will be replaced by electronic components that are smaller, lighter, and more reliable. She is unsure about how to calculate the total costs for each option, and she is even more unsure about how to factor these other variables into the decision. Are there any other issues besides cost that Sheila should evaluate?arrow_forward
- The Global Sourcing Wire Harness Decision Sheila Austin, a buyer at Autolink, a Detroit-based producer of subassemblies for the automotive market, has sent out requests for quotations for a wiring harness to four prospective suppliers. Only two of the four suppliers indicated an interest in quoting the business: Original Wire (Auburn Hills, MI) and Happy Lucky Assemblies (HLA) of Guangdong Province, China. The estimated demand for the harnesses is 5,000 units a month. Both suppliers will incur some costs to retool for this particular harness. The harnesses will be prepackaged in 24 12 6-inch cartons. Each packaged unit weighs approximately 10 pounds. Quote 1 The first quote received is from Original Wire. Auburn Hills is about 20 miles from Autolinks corporate headquarters, so the quote was delivered in person. When Sheila went down to the lobby, she was greeted by the sales agent and an engineering representative. After the quote was handed over, the sales agent noted that engineering would be happy to work closely with Autolink in developing the unit and would also be interested in future business that might involve finding ways to reduce costs. The sales agent also noted that they were hungry for business, as they were losing a lot of customers to companies from China. The quote included unit price, tooling, and packaging. The quoted unit price does not include shipping costs. Original Wire requires no special warehousing of inventory, and daily deliveries from its manufacturing site directly to Autolinks assembly operations are possible. Original Wire Quote: Unit price = 30 Packing costs = 0.75 per unit Tooling = 6,000 one-time fixed charge Freight cost = 5.20 per hundred pounds Quote 2 The second quote received is from Happy Lucky Assemblies of Guangdong Province, China. The supplier must pack the harnesses in a container and ship via inland transportation to the port of Shanghai in China, have the shipment transferred to a container ship, ship material to Seattle, and then have material transported inland to Detroit. The quoted unit price does not include international shipping costs, which the buyer will assume. HLA Quote: Unit price = 19.50 Shipping lead time = Eight weeks Tooling = 3,000 In addition to the suppliers quote, Sheila must consider additional costs and information before preparing a comparison of the Chinese suppliers quotation: Each monthly shipment requires three 40-foot containers. Packing costs for containerization = 2 per unit. Cost of inland transportation to port of export = 200 per container. Freight forwarders fee = 100 per shipment (letter of credit, documentation, etc.). Cost of ocean transport = 4,000 per container. This has risen significantly in recent years due to a shortage of ocean freight capacity. Marine insurance = 0.50 per 100 of shipment. U.S. port handling charges = 1,200 per container. This fee has also risen considerably this year, due to increased security. Ports have also been complaining that the charges may increase in the future. Customs duty = 5% of unit cost. Customs broker fees per shipment = 300. Transportation from Seattle to Detroit = 18.60 per hundred pounds. Need to warehouse at least four weeks of inventory in Detroit at a warehousing cost of 1.00 per cubic foot per month, to compensate for lead time uncertainty. Sheila must also figure the costs associated with committing corporate capital for holding inventory. She has spoken to some accountants, who typically use a corporate cost of capital rate of 15%. Cost of hedging currencybroker fees = 400 per shipment Additional administrative time due to international shipping = 4 hours per shipment 25 per hour (estimated) At least two five-day visits per year to travel to China to meet with supplier and provide updates on performance and shipping = 20,000 per year (estimated) The international sourcing costs must be absorbed by Sheila, as the supplier does not assume any of the additional estimated costs and invoice Sheila later, or build the costs into a revised unit price. Sheila feels that the U.S. supplier is probably less expensive, even though it quoted a higher price. Sheila also knows that this is a standard technology that is unlikely to change during the next three years, but which could be a contract that extends multiple years out. There is also a lot of hall talk amongst the engineers on her floor about next-generation automotive electronics, which will completely eliminate the need for wire harnesses, which will be replaced by electronic components that are smaller, lighter, and more reliable. She is unsure about how to calculate the total costs for each option, and she is even more unsure about how to factor these other variables into the decision. Based on this case, do you think international purchasing is more or less complex than domestic purchasing? Why? Is it worth the additional effort?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forward
- Claudia Pragraro Technologies, Inc., has narrowed its choice of outsourcing provider to two firms located in different countries. Pragram wants to decide which one of the two countries is the better choice, based on risk-avoidance criteria. She has polled her executives and established four cntena. The resulting ratings for the two countries are presented in the table belove where i o lower risk and 3 is a higher risk. Assume that the executives have determined four critena weightings: Price, with a weight of 0.1; Neamess, with 0.6: Technology, with 0.2; and History, with 0.1. a) Using the weighted factor-rating method, which country would you select? in the following table, compute the total weighted score for each candidate (enter your responses rounded to one decimal place) Based on a comparison of weighted risk scores, Claudia Pragram should choose b) Double each of the weights used in part (a) (to 0.20, 1.20, 0.40, and 0.20, respectively). If each weight is doubled. Claudia…arrow_forwardClaudia Pragram Technologies, Inc., has narrowed its choice of outsourcing provider to two firms located in different countries. Pragram wants to decide which one of the two countries is the better choice, based on risk-avoidance criteria. She has polled her executives and established four criteria. The resulting ratings for the two countries are presented in the table below, where 1 is a lower risk and 3 is a higher risk. The executives have determined four criteria weightings: Price, with a weight of 0.1; Nearness, with 0.6; Technology, with 0.2; and History, with 0.1. a) Using the factor-rating method, which country would you select? b) Double each of the weights used in part (a) (to 0.2, 1.2, 0.4, and 0.2, respectively). What effect does this have on your answer? Why?arrow_forwardClaudia Pragram Technologies, Inc., has narrowed its choice of outsourcing provider to two firms located in dif-ferent countries. Pragram wants to decide which one of the two countries is the better choice, based on risk-avoidance criteria. She has polled her executives and established four crite-ria. The resulting ratings for the two countries are presented in the table below, where 1 is a lower risk and 3 is a higher risk. SELECTION CRITERION ENGLAND CANADAPrice of service from outsourcer 2 3Nearness of facilities to client 3 1Level of technology 1 3History of successful outsourcing 1 2The executives have determined four criteria weightings: Price,with a weight of 0.1; Nearness, with 0.6; Technology, with 0.2;and History, with 0.1.a) Using the factor-rating method, which country would youselect?b) Double each of the weights used in part (a) (to 0.2, 1.2, 0.4,and 0.2, respectively). What effect does this have on youranswer? Why?arrow_forward
- Gulf Coast Electronics is ready to award contracts to suppliers for providing reservoir capacitors for use in its electronic devices. For the past several years, Gulf Coast Electronics has relied on two suppliers for its reservoir capacitors: Able Controls and Lyshenko Industries. A new firm, Boston Components, has inquired into the possibility of providing a portion of the reservoir capacitors needed by Gulf Coast. The quality of products provided by Lyshenko Industries has been extremely high; in fact, only 0.5% of the capacitors provided by Lyshenko had to be discarded because of quality problems. Able Controls has also had a high quality level historically, producing an average of only 1% unacceptable capacitors. Because Gulf Coast Electronics has had no experience with Boston Components, it estimated Boston Components' defective rate to be 10%. Gulf Coast would like to determine how many reservoir capacitors should be ordered from each firm to obtain 75,000 acceptable-quality…arrow_forwardMistral plc is a wholesaler of fast-moving consumer goods throughout the UK. The board of directors has decided Mistral pic should use the principles of Supply Chain Management to spise ta activities, and a consultant has made the following specific recommendations to the board as a result(1)Focus on a reduced number of suppliers and high value customers(2)Engage in joint problem-solving with suppliers and customers(3)Restrict information for suppliers about how much inventory is needed Which of these recommendations apply applies the principles of Supply Chain Management? A. (3) onlyB. (1) and (2)C. (1) onlyD. (2) and (3)arrow_forwardQ)Arslan is an exporter and producer of cutlery products. For the last few years, he is facing problems in his business. After a detailed investigation, he realized that he has severe problems in his organizational supply chain management system. One of the major problems identified is that he can’t measure the supply chain management system's performance properly. He wants to improve the supply chain management system and want to develop an effective model to measure the performance supply chain management system. Being an expert in the supply chain suggests a standardized modelto measure the performance properly.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning