a)
Summary Introduction
To determine: Labor productivity, material productivity, and multifactor productivity in different weeks.
Introduction
Productivity can be explained as the measure of level of competitiveness of an organization. It is measured by calculating the ratio of number of outputs produced to the number of inputs used. An increase in the productivity increases the level of wages of the individuals.
b)
Summary Introduction
To calculate: Material productivity
c)
Summary Introduction
To calculate: Multifactor productivity
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Posey Ceramics makes ceramic vases for a chain of de-partment stores. The output and cost figures over the past
four weeks are shown here. Labor costs $10 an hour, and
materials are $4 a pound. Calculate the (a) labor produc-tivity (in hrs), (b) material productivity (in lbs), and (c)
multifactor productivity for each week. Comment on theresults.
Week 1 2 3 4Units of output 2000 4000 5000 7000No. of workers 4 4 5 6Hours per week per worker 40 48 56 70Material (lbs) 286 570 720 1000
Ternes Manufacturing produces metal products primarily used in the construction industry. The three main inputs in production are
materials (metal), labor, and overhead. Data for the previous three reporting periods follow:
Materials cost
Labor cost
Overhead
Value of product produced
Period
Period 3
Period 2
Period 1
Period 3
$ 51,000
30,150
43,050
137,930
Total Factor
Productivity
Period 2
Required:
a. Compute the total factor productivity for the previous three reporting periods.
Note: Round your answers to 2 decimal places.
$ 65,500
39,820
48,600
179,504
Period 1
$ 60,750
36,200
46,850
164,604
Chetan
Chapter 1 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 1.S - Prob. 1PCh. 1.S - Prob. 2PCh. 1.S - Prob. 3PCh. 1.S - Prob. 4PCh. 1.S - Prob. 5PCh. 1.S - In Problem S1-5 assume that Nicole, with the help...Ch. 1.S - Prob. 7PCh. 1.S - Prob. 8PCh. 1.S - Telecomp, a computer manufacturer with a global...Ch. 1.S - Prob. 10P
Ch. 1.S - Prob. 11PCh. 1.S - Prob. 12PCh. 1.S - Prob. 13PCh. 1.S - Prob. 14PCh. 1.S - Prob. 15PCh. 1.S - Prob. 16PCh. 1.S - Prob. 17PCh. 1.S - Prob. 18PCh. 1.S - In Problem S1-18, assume the Weight Club is able...Ch. 1.S - Prob. 20PCh. 1.S - Prob. 21PCh. 1.S - Prob. 22PCh. 1.S - Prob. 23PCh. 1.S - Prob. 24PCh. 1.S - Prob. 25PCh. 1.S - Prob. 26PCh. 1.S - Prob. 27PCh. 1.S - Prob. 28PCh. 1.S - Prob. 29PCh. 1.S - Prob. 30PCh. 1.S - Prob. 31PCh. 1.S - Prob. 33PCh. 1.S - Prob. 34PCh. 1.S - Alex Mason has a wide-curving, uphill driveway...Ch. 1.S - Prob. 36PCh. 1.S - Prob. 39PCh. 1.S - Prob. 40PCh. 1.S - State University has three healthcare plans for...Ch. 1.S - The Orchard Wine Company purchases grapes from one...Ch. 1.S - Prob. 43PCh. 1.S - Prob. 1.1CPCh. 1.S - Prob. 2.1CPCh. 1.S - Evaluating Projects at Nexcom Systems Nexcom...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Feeding America Each year, the Feeding America...Ch. 1 - Prob. 1QCh. 1 - What constitutes operations at (a) a bank, (b) a...Ch. 1 - Prob. 3QCh. 1 - Prob. 4QCh. 1 - Prob. 5QCh. 1 - Prob. 17QCh. 1 - What is the difference between an order winner and...Ch. 1 - Prob. 21QCh. 1 - Prob. 22QCh. 1 - Prob. 23QCh. 1 - Prob. 24QCh. 1 - Prob. 1PCh. 1 - Prob. 2PCh. 1 - Prob. 3PCh. 1 - Prob. 4PCh. 1 - Prob. 5PCh. 1 - Omar Industries maintains production facilities in...Ch. 1 - Rushing yardage for three Heisman Trophy...Ch. 1 - Carpet City recorded the following data on carpet...Ch. 1 - Prob. 9PCh. 1 - Prob. 10PCh. 1 - Prob. 11PCh. 1 - Prob. 12PCh. 1 - Prob. 13PCh. 1 - Prob. 14PCh. 1 - Prob. 15PCh. 1 - Prob. 1.1CPCh. 1 - Prob. 1.2CPCh. 1 - Prob. 1.3CPCh. 1 - Prob. 1.4CPCh. 1 - Prob. 1.5CPCh. 1 - Prob. 2.1CPCh. 1 - Prob. 2.2CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- ABC Corporation is a furniture manufacturing company working on a 40 hour per week basis makes 135 chairs. The sales price is $75 each, and the company has the following costs:• Direct materials $790• Direct labor $360• Overhead $550Required:a. Calculate the productivity of the company.b. What will be the new productivity if the company decides to make 150 chairs per week?c. If the company decides to improve productivity through materials costs reduction only, how much these costs must be reduced in order to achieve a 10 percent increase in total productivity?d. If the company repeats the same exercise as in (c) above, but through labor costs reduction, how much these costs must be reduced in order to achieve a 10 percent increase in total productivity?arrow_forwardConsider the output and the labor hour figures shown in the following table: calculate the labor productivity for one week, as well as average labor productivity for one week.arrow_forwardThe manager of a crew that installs wood floors has tracked the crew’s output over the past several weeks. Each worker works 40 hours per week, and earns $22 per hour. The wholesale cost of lumber to the company is $9 per square foot, and the company charges its customers $25 per square foot of flooring installed. Overhead rate is 100% a) using the best formula to determine labor productivity, calculate labor productivity for each of the weeks b) calculate multifactor productivity for each week using the dollar revenue of flooring installed in the numerator week crew size lumber used flooring installed week 1 4 480 420 week 2 3 371 325arrow_forward
- Pak Andi is a director of a cake factory in the Bekasi area. To produce 900 cakes per day it takes the following things: Labor 300 hours per day @ $ 96 per hour Raw material 3 tons per day @ $ 2 per kg Energy $ 10,000 per day Capital cost $ 5,000 per day a. What is the labor productivity per labor-hour for the production of cakes at the factory?b. What is the multifactor productivity for cake production at the factory?c. If Mr. Andi wants to increase his production to 1,500 cakes per day without changingother variables, what is the productivity now?arrow_forwardThe manager of a crew that installs carpeting has tracked the crew’s output over the past severalweeks, obtaining these figures:Week Crew Size Yards Installed1 4 962 3 723 4 924 2 505 3 696 2 52Compute the labor productivity for each of the weeks. On the basis of your calculations, what canyou conclude about crew size and productivity?arrow_forwardi need the answer quicklyarrow_forward
- A factory produces 14,000 desk staplers each week. The equipment used costs $50,000 and will remain productive for four years. The labor cost per year is $190,000. a. What is the productivity measure of "units of output per dollar of input" averaged over the four-year period? Assume that there are 52 weeks per year. Round your answer to two decimal places. units of output per dollar input b. We have the option of buying $55,000 of new equipment, with an operating life of seven years. It would reduce labor costs to $124,000 per year. Should we consider purchasing this equipment (using productivity arguments alone)? Assume that there are 52 weeks per year. Round your answer for productivity to two decimal places. For the newer machine, the productivity is -Select-, it would be a-Select- investment. -Select- higher lower units of output per dollar input. Because the productivity of the new machine isarrow_forwardBarry’s Tire Service completed 100 tire changes, six brake jobs, and 16 alignments in an eight-hour day with his standard crew of six mechanics. A brake specialist costs $16 per hour, a tire changer costs $8 per hour, an an alignment mechanic costs $14 per hour. The materials cost for days was $2,000, and overhead cost was $500. What is the shop’s labor productivity if the retail price for each respective service is $60, $150, and $40? What is the multifactor productivity, if the crew consisted of two of each type mechanicarrow_forwardCompute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Week 1 2 Click here for the Excel Data File Week 1 2 Output (units) 32,000 37,000 20,000 38,000 3 4 Workers MFP (Output/Total Cost) Material (169) 470 520 400 500arrow_forward
- Bear Lake Seafood produces 782 boxes of seafood per day. There are 3 working shifts, each is 5-hour. The company employs 25 workers for each shift, and pays each worker $15 per hour. The utility cost for the company is $67 per working hour (no utility cost when the company is not in operation). What is the utility productivity (in terms of cost) for the seafood company? Numbers only, keep three decimals if not exact, either round up or down is okarrow_forwardGiven the following information, calculate the multifactor productivity in terms of revenue per multifactor cost. (In other words, use money in the numerator and denominator.)Units produced: 5,000Standard price: $30/unitLabor input: 500 hoursCost of labor: $25/hourCost of materials: $5,000Cost of overhead: 2x labor costA) State the formulaB) Determine the unit of measure for the numeratorC) Determine the unit of measure for the denominatorD) Calculate ProductivityD) Interpret the resultsarrow_forwardMazen is a manager in a factory producing fabrics. In 2020, the daily production target was met in terms of quality and quantity. But, this target was achieved as a result of an increased number of workers and import of high quantities of cotton and piles of leftovers, meaning an extra inputs' costs. He decided to make negotiations with local industries to sell them cotton remnants to be recycled and re-used in pillow manufacturing.The productivity of this factory is: * Effective and efficient Neither effective nor efficient Effective but not efficient O Not effective but efficientarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.