Numerical Methods for Engineers
Numerical Methods for Engineers
7th Edition
ISBN: 9780073397924
Author: Steven C. Chapra Dr., Raymond P. Canale
Publisher: McGraw-Hill Education
bartleby

Videos

Textbook Question
Book Icon
Chapter 16, Problem 5P

A chemical plant makes three major products on a weekly basis. Each of these products requires a certain quantity of raw chemical and different production times, and yields different profits. Thepertinentin formation is in Table P16.5. Note that there is sufficient warehouse space at the plant to store a total of 450 kg/week.

TABLE P16.5

Product 1 Product 2 Product 3 Resource Availability
Raw chemical 7 k g / k g 5 k g / k g 13kg/kg 3000 k g
Production time 0.005 h r / k g 0.1 h r / k g 0.2hr/kg 55 h r / w e e k
Product $ 30 / k g $ 30 / k g $ 35 / k g

(a) Set up a linear programming problem to maximize profit.

(b) Solve the linear programming problem with the simplex method.

(c) Solve the problem with a software package.

(d) Evaluate which of the following options will raise profits the most: increasing raw chemical, production time, or storage.

(a)

Expert Solution
Check Mark
To determine

A linear programming problem for a chemical plant that makes three products on a weekly basis. The data is given below:

Product 1Product 2Product 3Resource AvailabilityRaw Chemical7 kg/kg5 kg/kg13 kg/kg3000 kgProduction Time0.05 hr/kg0.1 hr/kg0.2 hr/kg55 hr/weekProfit$30/kg$30/kg$35/kg

Answer to Problem 5P

Solution:

The Linear Programming formulation is given as:

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Explanation of Solution

Given Information:

Following data is given for a chemical plant that makes three products on a weekly basis:

Product 1Product 2Product 3Resource AvailabilityRaw Chemical7 kg/kg5 kg/kg13 kg/kg3000 kgProduction Time0.05 hr/kg0.1 hr/kg0.2 hr/kg55 hr/weekProfit$30/kg$30/kg$35/kg

Also, the warehouse can store a total of 450 kg/week.

Let x1, x2, x3 be respectively the weights needed of Product 1, Product 2 and Product 3 to maximize profit and satisfy the provided conditions.

The Linear Programming Model can be set up as follows:

As Profit is to be maximized, the objective function is Maximize C= 30x1+30x2+35x3.

The constraints are:

The raw chemical constraint is 7x1+5x2+13x33000.

As the total production time must be equal to or less than 55 hr. Thus, the time constraint is 0.05x1+0.1x2+0.2x355.

The storage available is 450 kg/week. Thus, the storage constraint is x1+x2+x3450.

Also, the weights can never be negative. Thus, positivity constraint is x10, x20, x30

Hence, the Linear Programming formulation is given as:

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

(b)

Expert Solution
Check Mark
To determine

To calculate: The solution of the linear programming problem given below:

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Answer to Problem 5P

Solution:

The values of variables are x1=0, x2=356.25, x3=93.75. The maximum C=13968.75.

Explanation of Solution

Given Information:

A linear programming problem,

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Calculation:

Consider the provided linear programming problem,

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

First convert the above problem to standard form by adding slack variables.

As the constraints are subjected to less than condition, non- negative slack variables are added to reach equality.

Let the slack variables be S10, S20 and S30.

Thus, the linear programming model would be:

Maximize C= 30x1+30x2+35x30S1+0S2+0S3

7x1+5x2+13x3+S1=30000.05x1+0.1x2+0.2x3+S2=55x1+x2+x3+S3=450

x10, x20, x30, S10, S20 and S30

The above linear programming models consist of three non-basic variables (x1, x2, x3) and three basic variables (S1, S2, S3).

Now the apply the Simplex method and solve the above problem as:

BasisCx1x2x3S1S2S3SolutionMinimum RatioP13030350000S1075131003000230.7692S200.050.10.201055275S30111001450450

The negative minimum, P is 35 and it corresponds to variable x3. So, the entering variable is x3

The minimum ratio is 230.7692 and it corresponds to basis variable S1. So, the leaving variable is S1.

Therefore, the pivot element is 13.

BasisCx1x2x3S1S2S3SolutionMinimum RatioP111.153816.538502.69231008076.923x300.538460.3846210.0769200230.7692600S200.057690.0230800.01538108.846154383.3333S300.461540.6153900.0769201219.2308356.25

The negative minimum, P is 16.5385 and it corresponds to variable x2. So, the entering variable is x2.

The minimum ratio is 356.25 and it corresponds to basis variable S3. So, the leaving variable is S3.

Therefore, the pivot element is 0.61539.

BasisCx1x2x3S1S2S3SolutionMinimum RatioP11.25000.625026.87513968.75x300.25010.12500.62593.75750S200.075000.012510.03750.62550x200.75100.12501.625356.252580

Since P0, optimal solution is obtained.

Hence, the values of variables are x1=0, x2=356.25, x3=93.75. The maximum C=13968.75.

(c)

Expert Solution
Check Mark
To determine

To calculate: The solution of the linear programming problem given below using software package:

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Answer to Problem 5P

Solution:

The values of variables are x1=0, x2=356.25, x3=93.75. The maximum C=13968.75.

Explanation of Solution

Given Information:

A linear programming problem,

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Calculation:

Consider the provided linear programming problem,

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

The solution can be obtained using Excel.

Set up the values and use the formula as shown below:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  1

The values obtained are:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  2

Now press Solver under Data tab and enter the constraints and objective as shown below:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  3

The resulting solution is:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  4

Hence, the values of variables are x1=0, x2=356.25, x3=93.75. The maximum C=13968.75.

(d)

Expert Solution
Check Mark
To determine

The factor among increasing raw material, production time or storage that will rise profits the most for the linear programming problem given below:

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Answer to Problem 5P

Solution:

Increasing storage will result in the most profits.

Explanation of Solution

Given Information:

A linear programming problem,

Maximize C= 30x1+30x2+35x3

Subject to Constraints:

7x1+5x2+13x33000

0.05x1+0.1x2+0.2x355

x1+x2+x3450

x10, x20, x30

Calculation:

Open the Excel sheet of part (c), then Press Solver under Data and select Simplex LP as a solving method as shown below:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  5

Press solve then select Sensitivity in reports as shown below:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  6

The sensitivity report obtained is:

Numerical Methods for Engineers, Chapter 16, Problem 5P , additional homework tip  7

The high shadow price for storage implies that increasing storage will result in the most profits.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The prices of agricultural commodities for 1946-47 and for the inonth of Dece:mber 1950 are given below along with the value of the output of hese commodities in 1946-47: Value of outptl in million (Rs.) Prices ELIII Commodities Unit 1946-47 (Rs.) Dec. 1950 (Rs.) (1946-47) 13.75 9-70 8364 Rice Wheat Jowar maund таund 13-75 9.70 2207 6:03 8.00 876 maund 466 00 433.00 701 Cotton (raw) Tea Ibs. 1:25 1:75 534 Ibs. Calculate the weighted index mumber of prices of these commodities for December 1950 taking 1946-47 as base.
1. The number of pounds of steam used per month by a chemical plant is thought to be related to the average ambient temperature (in degF) for that month. The past year's usage and temperature are shown in the following table: Month Temp. Usage/1000 Month Temp. Usage/1000 Jan. 21 185.79 July 68 621.55 Feb. 24 214.47 Aug. 74 675.06 Mar. 32 288.03 Sept. 62 562.03 Apr. 47 424.84 Oct. 50 452.93 May 50 454.58 Nov. 41 369.95 June 59 539.03 Dec. 30 273.98 (a) Assuming that a simple linear regression model is appropriate, fit the regression model relating steam usage (y) to the average temperature (x). (b) What is the estimate of expected steam usage when the average temperature is 55F?
QUESTION 2 The technical supervisor of South Africa Breweries wishes to investigate how the plant's water usage depends upon the plant's production. The production and water usage table is as shown below. Water Usage (ZAR million) (million m³) 2.48 2.26 Production 4.51 Janury February March 3.58 4.31 2.47 Аpril May June July August September October | November | December 5.06 2.77 5.64 2.99 4.99 3.05 3.18 5.29 5.83 3.46 3.03 4.70 3.26 2.67 2.53 5.61 4.90 4.20 Table 2: SAB plant water usage data set 2.1.Plot the data on a scatter plot. [2] 2.2.List the independent and the dependent variables. [2] 2.3.Develop a regression model [16]

Chapter 16 Solutions

Numerical Methods for Engineers

Knowledge Booster
Background pattern image
Advanced Math
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Linear Algebra: A Modern Introduction
Algebra
ISBN:9781285463247
Author:David Poole
Publisher:Cengage Learning
Text book image
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:9781133382119
Author:Swokowski
Publisher:Cengage
Text book image
College Algebra
Algebra
ISBN:9781938168383
Author:Jay Abramson
Publisher:OpenStax
Hypothesis Testing using Confidence Interval Approach; Author: BUM2413 Applied Statistics UMP;https://www.youtube.com/watch?v=Hq1l3e9pLyY;License: Standard YouTube License, CC-BY
Hypothesis Testing - Difference of Two Means - Student's -Distribution & Normal Distribution; Author: The Organic Chemistry Tutor;https://www.youtube.com/watch?v=UcZwyzwWU7o;License: Standard Youtube License