••• 16.9 Given the following information about a product at Michael gibson’s firm, what is the appropriate setup time?
Annual demand = 39,000 units
Daily demand = 150 units
Daily production = 1,000 units
Desired lot size = 150 units
Holding cost per unit per year = $10
Setup labor cost per hour = $40
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question 23
Company A carries 5,000 items. Customers ordered 1,000 items from inventory last week. Company A was able to fulfill 600 items of the order. What is the stock out probability for last week?
Group of answer choices
0.08
0.4
0.6
0.92
QUESTION 16
Products in an electronic store consist of the following: 20 TVs delivered on January 10th at a cost of $100 each and 30 TVs delivered on February 2nd at a cost of $110. They are
the FIFO inventory method, what would the remaining value of inventory be if 15 TV's were sold on February 28th?
the same model Using
$3.650
O $3,800
O $5,300
O $3,710
A cost that changes with the level of output is called a(n) _____.
Question 41 options:
a)
liquid cost
b)
independent cost
c)
variable cost
d)
indirect cost
Chapter 16 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 16 - Question 1. What is JIT?Ch. 16 - Prob. 2DQCh. 16 - Question 3. What is TPS?Ch. 16 - Question 4. What is level scheduling?Ch. 16 - Question 5. JIT attempts to remove delays, which...Ch. 16 - Prob. 6DQCh. 16 - Question 7. How does TPS contribute to competitive...Ch. 16 - Prob. 8DQCh. 16 - Question 9. Discuss how the Japanese word for card...Ch. 16 - Question 10. Standardized, reusable containers...
Ch. 16 - Prob. 11DQCh. 16 - Prob. 12DQCh. 16 - Question 16.8 Carol Cagle has a repetitive...Ch. 16 - Question 16.9 Given the following information...Ch. 16 - Question 16.10 Rick Wing has a repetitive...Ch. 16 - Prob. 4PCh. 16 - Question 16.2 Tej Dhakars company wants to...Ch. 16 - Question 16.3 Pauline Found Manufacturing, Inc.,...Ch. 16 - Prob. 7PCh. 16 - Question 16.5 Discount-Mart, a major East Coast...Ch. 16 - Question 16.6 Discount-Mart (see Problem 16.5),...Ch. 16 - Prob. 10PCh. 16 - Prob. 1.1VCCh. 16 - Prob. 1.2VCCh. 16 - Prob. 1.3VCCh. 16 - Question JIT at Arnold Palmer Hospital Video Case...Ch. 16 - Question JIT at Arnold Palmer Hospital Video Case...Ch. 16 - Question JIT at Arnold Palmer Hospital Video Case...Ch. 16 - Question JIT at Arnold Palmer Hospital Video Case...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 4 ) Case mix funding (e.g., using "diagnostic related groups" or "resource intensity weights") is designed to counter supplier induced demand True Falsearrow_forwardQuestion 25 The bullwhip effect can cause the variability in ________ to be substantially greater than variability in ________. Group of answer choices demand within the supply chain, supplier demand supplier demand, demand within the supply chain consumer demand, demand within the supply chain demand within the supply chain, consumer demand supplier demand, demand within the supply chainarrow_forwardQuestion Help Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 300 days. Setup labor cost Annual holding cost Daily production (8 hours) Annual demand for steering wheels Desired lot size (2 hours of production) Q = 260 units $60.00 per hour $11 per unit 1,040 units/day 31,500 (300 days x daily demand of 105 units) %3D a) Setup cost = $ 10.61 (round your response to two decimal places). b) Setup time = minutes (round your response to two decimal places).arrow_forward
- Question 5 O pts A new product that will sell for $75.00 has variable costs of $38.00 per unit. Fixed costs of $75,000 must be incurred every year to manufacture this product. What is the annual volume to break even? O 2000 units or more. O fewer than 1500 units. O 1750 to 1999 units. O 1500 to 1749 units.arrow_forwardQUESTION 2 When used effectively, S&OP Planning does not require cross-functional collaboration. O True Falsearrow_forwardLie Around Furniture manufactures two products: Futons and Recliners. The following data are available: Futons Recliners Sales price $550 $700 Variable costs $350 $395 The company can manufacture 3 futons per machine hour and 2 recliner per machine hour. The company's production capacity is 3500 machine hours per month.To maximize profits, what product and how many units should the company produce in a month? Question 36 options: 10,500 futons and 7000 recliners 7000 recliners 7000 futons and 6 recliners 10,500 futonsarrow_forward
- QUESTION 4 Mega Inc. manufactures hairdryers for the commercial market. One of the crucial partsrequired for the assembly of this product is ‘Part 123’. Requirement for this part is 60000units per year valued at RM 30 per unit and the handling cost is RM 0.50 per unit per month.The cost of preparing the order is RM 48. The plant operates 250 days per year. It is thecompany’s policy to maintain a buffer stock of 2 days usage.i. The maximum inventory level ii. The average level of inventoryarrow_forwardQUESTION 2 A) On the average, a firm has 10 weeks of work-in-process, and annual cost of goods sold is $15 million. Assuming that the company works 50 weeks a year: a) What is the dollar value of the work-in-process? b) If the work-in-process could be reduced to 7 weeks and the annual cost of carrying inventorv was 20% of the inventory value, what would be the annual saving? B). Warsop Factory sales are $10 million. The company spends $3.5 million for purchase of direct materials and $2.5 million for direct labor; overhead is $3.5 million and profit is $500,000. Direct labor and direct material vary directly with the cost of goods sold, but overhead does not. The company wants to triple its profit. By how much should the firm increase sales? By how much should the firm decrease material costs? By how much should the firm decrease labor cost? а. b. с.arrow_forwardQuestion is; After producing for one-year, which option will lead to more profits=arrow_forward
- Question NO. 4 Convinced by the efficiency of hybrid model, Sony, started to produce LED filaments of its Soy TV's itself while outsourcing all its other components. Initially, Sony can only produce these LED filaments at a very steady rate of eight hundred per day. Three hundred TVs are assembled daily in eight hours shift, 250 days a year. Due to difference in TVs demands and its production, LED filaments are only produced in batches of 2,000 units. Your are required to estimate; Annual production of LED filament batches in numbers b. Starting with zero inventory, if usage and production remains the same what would be the inventory levels after 76 hrs. Calculate average inventory levels when each production cycle starts with zero inventory. d. The same equipment that is used to make the LED filaments could also be used to make another filament used in the firm's other products. That job would require four days, including setup time. Setup time for making a batch of the LED filament…arrow_forward(information may be needed from main question) Holding cost = 19% * 42(unit cost) = $ 7.98 Reordering cost =$ 515 280 days per year annual demand = 16200 Q* = 418 Lead times recorded from the past 10 cycles 4.6 6.2 4.1 4.1 4.9 5.0 5.6 6.2 4.6 4.0 1. The most recent order for compressors has been placed on Sunday April 19, 2020 at 8:00 a.m. What is the probability that the order will not have arrived by the end of Sunday April 26, 2020?arrow_forwardSubject: Entrprenuership Need to develop lean canvas model of "Careem"arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY