Question
Chapter 16, Problem 1P
Summary Introduction
To draw: To identify the sequence of model for the final assembly line to smoothly carry the production.
Introduction
Lean production is a system for the management in which it focuses on reducing waste, checking the quality, and all the efforts are put to fulfill the market needs. All the activities starting from manufacturing to distribution are managed efficiently through the lean system.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How would you characterize the most important difference for the following issues when comparing a workcenter (job shop) and an assembly line? WorkcenterIssue (Job Shop) Assembly LineNumber of changeoversLabor content of productFlexibility
Describe what are the advantages of mixed model sequencing ?
Draw a diagram (a concept map), of the process of arriving at Target Kaizen Cost.
Chapter 16 Solutions
Operations and Supply Chain Management 9th edition
Ch. 16 - Prob. 1QCh. 16 - Prob. 2QCh. 16 - Prob. 3QCh. 16 - Prob. 4QCh. 16 - Prob. 5QCh. 16 - Prob. 6QCh. 16 - Prob. 7QCh. 16 - Prob. 8QCh. 16 - Prob. 9QCh. 16 - Prob. 10Q
Ch. 16 - Prob. 11QCh. 16 - Prob. 13QCh. 16 - Prob. 14QCh. 16 - Prob. 15QCh. 16 - Prob. 16QCh. 16 - Prob. 17QCh. 16 - Prob. 18QCh. 16 - Prob. 19QCh. 16 - Prob. 20QCh. 16 - Prob. 21QCh. 16 - Prob. 22QCh. 16 - Prob. 23QCh. 16 - Prob. 25QCh. 16 - Prob. 26QCh. 16 - Prob. 27QCh. 16 - Prob. 28QCh. 16 - Prob. 30QCh. 16 - Prob. 31QCh. 16 - Prob. 1PCh. 16 - As local developers prepare for an increase in...Ch. 16 - Prob. 3PCh. 16 - Prob. 4PCh. 16 - Prob. 5PCh. 16 - Prob. 6PCh. 16 - Prob. 7PCh. 16 - Prob. 8PCh. 16 - Prob. 9PCh. 16 - In a large microelectronics plant, the assembly...Ch. 16 - Prob. 11PCh. 16 - Prob. 12PCh. 16 - Prob. 13PCh. 16 - Prob. 2.1CPCh. 16 - Prob. 2.2CPCh. 16 - Prob. 2.3CPCh. 16 - Prob. 2.4CPCh. 16 - Prob. 3.1CPCh. 16 - Prob. 3.2CPCh. 16 - Prob. 3.3CPCh. 16 - Prob. 3.4CP
Knowledge Booster
Similar questions
- Car manufacturers typically used what types of production modes O Assemble-to-order and make-to-order O All of above Make-to-stock and assemble-to-order Make-to-stock and make-to-orderarrow_forwardHow does the requirement that the number of units of model LX produced be at least 60% of the total production affect profits?arrow_forwardTRUE/FALSE Henry Ford's introduction of the Model "T" was the first example of mass customization.arrow_forward
- For a consumer appliance consisting of numerous sub-assemblies that are assembled together, which joining characteristics will influence the assembly method for the different components?arrow_forwardA make-to-order strategy produces products to customer specifications in large volumes. True Falsearrow_forwardTwo years ago Top-Slice Company moved from just making golf balls to also producing oversized drivers. Top-Slice makes three different models: the Bomber, the Hook King, and the Sir Slice-A-Lot. As the names suggest, the last two clubs help correct for golfers who either hook or slice the ball when driving. While Top-Slice is pleased with the growing sales for all three models (see the following tables), the numbers present Jacob Lee, the production manager, with a dilemma. Jacob knows that the current manufacturing work cell is capable of producing only 2,700 drivers a month, and total sales seem to be rapidly approaching that number. Jacob’s staff has told him it will take at least three months to plan for and implement an expanded work cell. Develop a forecast for Top-Slice Company. Which forecast model works best? Why? Suppose information is received that makes clear that sales are expected to go down. How would this affect the choice of a forecasting model?arrow_forward
- Shorter production runs and multiple configurations of products do not work well in traditional manufacturing settings. Shorter runs require less material on the line. Most manufacturers still bring a full pallet to the line when needing only a third of the material on the pallet. As multiple product models flow through the assembly line, more pallets with parts for each model fill the work cell. These are necessary to accommodate quick changeovers on the line. The result is a high level of chaos. Aisles become more congested as traffic bringing (and returning) material to the line increases. Workers must use more steps to access the correct component for each model. The possibility of workers attaching the wrong material for the product model increases. Finally, safety issues rise. The good news is it is possible to reduce excess inventory and still meet production goals. With this regard, 1.1 Discuss how product defect becomes a waste in the production process. 1.2 Discuss some…arrow_forwardWhat are the advantages of a mixed-model line over a batch-model line for producing different product styles?arrow_forwardDiscussion about Poka Yoke (error proofing) and give examples.arrow_forward
- A-Plus Printing Setup fee: $20 Each poster: $0.10 Print More Setup fee: $55 Each poster: $0.05 Complete the table to see how much it would cost for different numbers of posters. After completing the table, what do you notice? the table is in the imagearrow_forwardWhat is the goal of a maintenance program?arrow_forwardSolvo produces three types of trucks on one assembly line: the long-haul (L), the short-haul (S), and the vocational truck (V). Next month the company has orders for 1,100 long-haul trucks, 1650 short-haul trucks, and 550 vocational trucks. Chris Riggs, the production manager for Solvo, wants to try uniform production and mixed-model sequencing. Assuming 30 working days per month, what assembly sequence would you recommend, and how many times per day should the sequence be repeated. (Round answer to 0 decimal places) Assembly sequence? (pick one) a.vocational,vocational, vocational, long-haul, long-haul, short-haul b.short-haul, long-haul, short-haul, vocational, short-haul, long-haul c.short-haul, short-haul, long-haul, long-haul, vocational, vocational How many times should sequence be repeated?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.